Martin v. Williams

172 So. 3d 782, 2013 WL 1878899, 2013 Miss. App. LEXIS 239
CourtCourt of Appeals of Mississippi
DecidedMay 7, 2013
DocketNo. 2011-CA-01534-COA
StatusPublished
Cited by5 cases

This text of 172 So. 3d 782 (Martin v. Williams) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Williams, 172 So. 3d 782, 2013 WL 1878899, 2013 Miss. App. LEXIS 239 (Mich. Ct. App. 2013).

Opinion

LEE, C.J.,

for the Court:

PROCEDURAL HISTORY

¶ 1. On July 29, 2010, Jacques T. Martin Jr. (Martin) filed a complaint against Gregory L. Williams (Williams) in the Jackson County Chancery Court seeking a declaratory judgment for enforcement of an option contract to purchase real estate and damages for Williams’s alleged breach of a loan agreement.1 Williams filed an answer and counterclaim. In his counterclaim, Williams alleged Martin had breached the option contract and was responsible for Williams’s attorney’s fees. Williams later added Martin’s brother, Michael T. Martin (Michael), as a defendant.

¶ 2. After a hearing on the matter, the chancellor determined that Martin had failed to make a timely option-renewal payment, resulting in the expiration of the option period, and Williams was not required to accept the late payment. The chancellor also awarded Williams $13,959.49 in attorney’s fees.

¶ 3. Martin now appeals, asserting the following issues: (1) the chancellor erred in determining the renewal date of the thirty-day option period; (2) the chancellor erred in finding Williams did not waive any rights under the option contract by accepting a prior payment one day late; and (3) the chancellor erred in finding no compel[785]*785ling circumstances to warrant equitable relief. In his cross-appeal, Williams asserts that the chancellor should have assessed attorney’s fees against Michael in addition to Martin. Williams also asks this Court to award attorney’s fees in connection with the appeal.

FACTS

¶ 4. On February 4, 2010, Williams and Martin entered into an option contract to purchase real estate. The property in question was approximately eighty acres of land located in Gautier, Mississippi. The property was originally owned by Martin and had been in his family for thirty-five years.2 According to the terms of the option contract, Martin had the option to purchase the property from Williams for an initial option period of ninety days, commencing on January 21, 2010, and ending April 21, 2010. Martin paid the initial option payment of $30,000. On the same day the option contract was entered, Martin assigned the option to Michael; however, this assignment was never delivered to Michael or recorded.

¶ 5. The option contract provided for the extension of the option “for twelve (12) additional, separate thirty (30) day periods ... if, and only if, the Optionee pays the [additional [o]ption [m]oney to Optionor prior to 5 p.m. on the date of expiration of the preceding option period.” Under the agreement, $10,275 was due to Williams for each additional thirty-day option period. Pursuant to the option contract, Martin tendered $10,275 to Williams on April 13, 2010, to extend the initial option period for an additional thirty days past the expiration date of April 21, 2010. On May 21, 2010, Martin paid Williams $10,275 in order to exercise his second renewal option.

¶ 6. On June 21, 2010, Martin paid Williams $10,275 in order to exercise his third renewal option. The previous option period had ended on June 20, 2010, but Williams accepted payment on June 21 since his office had been closed on June 20, which was a Sunday. On July 21, 2010, Michael attempted to pay $10,275 to exercise a fourth renewal option. However, Williams refused to accept payment, as it was one day late. Shortly thereafter Martin filed suit against Williams.

STANDARD OF REVIEW

¶ 7. The Court will not disturb a chancellor’s findings if they are supported by substantial evidence unless the chancellor abused his or her discretion, was manifestly wrong, clearly erroneous, or applied an erroneous legal standard. Sanderson v. Sanderson, 824 So.2d 623, 625-26 (¶ 8) (Miss.2002). The principle of “manifest error” applies only to findings of fact. Boggs v. Eaton, 379 So.2d 520, 522 (Miss.1980). However, questions of law, including questions of contract construction, are reviewed de novo. McMurphy v. Three Rivers Planning & Dev. Dist., Inc., 966 So.2d 192, 195 (¶ 12) (Miss.Ct.App.2007).

DISCUSSION

I. RENEWAL DATE OF THIRTY-DAY OPTION PERIOD

¶ 8. In his first issue, Martin argues the chancellor erred in finding the third option renewal period commenced on June 20. Martin contends he purchased [786]*786an additional thirty days beginning on June 21, which was the date of his late payment, and ending at 5:00 p.m. on July 21. If so, Martin’s payment on July 21 would have been considered timely.

¶ 9. According to our rules of contract interpretation, “where the contract is not ambiguous, the intention of the contracting parties should be gleaned solely from the wording of the contract.” Turner v. Terry, 799 So.2d 25, 32 (¶ 16) (Miss.2001). If the terms of the contract are clear and unambiguous, parol evidence is inadmissible. HeartSouth, PLLC v. Boyd, 865 So.2d 1095, 1107 (¶ 36) (Miss.2008).

¶ 10. • The courts use a three-step approach to interpret a contract:

First, the “four corners” test is applied, wherein the reviewing court looks to the language that the parties used in expressing their agreement. Second, if the court is unable to translate a clear understanding of the parties’ intent, the court should apply the discretionary “canons” of contract construction. Finally, if the contract continues to evade clarity as to the parties’ intent, the court should consider extrinsic or parol evidence. It is only when the review of a contract reaches this point that prior negotiations, agreements^] and conversations might be considered in determining the parties’ intentions in the construction of the contract.

Tupelo Redevelopment Agency v. Abernathy, 913 So.2d 278, 284 (¶ 13) (Miss.2005) (internal citations omitted).

¶ 11. The contract clearly states the following in regard to extending the option:

This option shall be for a period of ninety (90) days, beginning on January 21, 2010, and ending on April 21, 2010[,] at 5:00 p.m. C.S.T. (the “Initial Option Period), and this option may be extended for twelve (12) additional, separate thirty (30) day periods (the “Additional Option Periods”) if, and only if, [Martin] pays the [additional [o]ption [m]oney to [Williams] prior to 5:00 p.m. on the date of the expiration of the preceding option period.

This contract does not, as Martin' would have us believe, provide for a new option period to begin whenever payment was attempted, offered, or accepted. Otherwise a new option period would have begun on April 13 when Martin paid $10,275 to exercise his first renewal option. Martin admittedly knew the payment made on July 21 was due July 20, and admitted that an early payment did not change when the option period started or ended. In fact, Martin testified that he “did not notice that” the contract called for twelve separate thirty-day periods. We find this issue to be without merit.

II. WAIVER

¶ 12. In his next issue, Martin contends Williams waived the “time is of the essence” provision in the option contract by accepting the late payment on June 21. The chancellor found that Williams did not waive any rights under the option contract by accepting the payment on June 21 rather than June 20 because his office was closed on June 20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
172 So. 3d 782, 2013 WL 1878899, 2013 Miss. App. LEXIS 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-williams-missctapp-2013.