Martin v. Darcy

357 S.W.2d 457, 4 A.L.R. 3d 278, 1962 Tex. App. LEXIS 2440
CourtCourt of Appeals of Texas
DecidedApril 25, 1962
Docket13907
StatusPublished
Cited by5 cases

This text of 357 S.W.2d 457 (Martin v. Darcy) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Darcy, 357 S.W.2d 457, 4 A.L.R. 3d 278, 1962 Tex. App. LEXIS 2440 (Tex. Ct. App. 1962).

Opinion

POPE, Justice.

Plaintiff, Harris P. Darcy, sued Glen A. Martin for breach of a farm-out agreement, 1 and recovered $3,500 damages under *458 the express terms of the contract, and an additional $3,000 for loss of profits. Martin, by this appeal, insists that the trial court erred (1) in submitting the first special issue which called upon the jury to construe the legal instrument, (2) in submitting the second issue and rendering judgment upon it, when there was no evidence in support of the issue, and (3) in making its own findings upon the amount of lost profits, when there was no evidence of the elements of lost profits. In our opinion, Martin, is correct in his contentions about the first and third points, and wrong about the second.

In early July of 1959, Darcy owned the minerals under 671 acres of McMullen County land by force of an assignment from Sun Oil Company. Sun’s assignment obligated Darcy to “begin by August 10, 1959, the actual drilling of a well” on the tract. Darcy also held three dry hole contribution letters by which Ohio Oil Company agreed to contribute $6,500, Western Natural Gas Company, $3,150, and El Paso Natural Gas Company, $3,150 toward the drilling of a well. Sun’s assignment to Darcy and each of the dry-hole letters to Darcy, prohibited his assignment without prior written consent.

Darcy and Martin began negotiations by which Darcy would assign his rights and obligations to Martin. On July 29, 1959, Martin accepted the terms of a letter which Darcy had written him. By that agreement, Darcy assigned his rights and obligations to Martin. The letter described each of the four documents which Darcy had from the four oil companies. Martin assumed the obligation to drill the well. The contract provided that Darcy would receive $1,500 in the event Martin completed the well as a producer, or $3,500 in the event it was a dry hole. Darcy also retained one-eighth of the oil and other minerals in the property.'

Martinis letter of transmittal, from San Antonio to Darcy in Houston, called on Darcy to send him the consents to the assignment from the four oil companies. On July 31, upon receipt of Martin’s acceptance, Darcy wrote each oil company based in Texas, and asked for its consent. On August 4, Martin wrote Darcy, “since I do not have letters giving permission for you to assign cannot take the deal as outlined in our letter of agreement.” On August 6, Darcy went to Martin’s office with consents from Ohio and Western. Martin refused to examine or consider them. On August 7, Darcy returned to Martin’s office with the Sun consent and a telegram from El Paso, which stated that its consent was already mailed. It was received on August 8. During Darcy’s visit on August 7, he delivered a' letter to Martin with attached consents from all but El Paso Oil Company, whose telegram was attached. Darcy by his letter called on Martin to comply with his drilling obligation. Martin did not drill the well. It was later drilled by other persons and was completed as a dry hole. The parties treat the well as a dry hole. Darcy claimed that he was entitled to the contract amount of $3,500 because the well was a dry hole. Martin claimed that Darcy breached the contract by failing to furnish the consents.

Darcy’s first point is that the court improperly asked the jury whether the parties to the contract contemplated and agreed that Darcy would obtain the consents to the assignments in time for Martin, in the exercise of reasonable diligence, to commence the actual drilling of the well by August 10. The jury said “No”. According to the jury, the parties contemplated that Martin would proceed in disregard of the four contracts which required consents. This advice from the jury is not helpful, for Martin, as a matter of law, could move on the lease premises without Sun’s consent only at the risk of being a trespasser. Cage Bros. v. Whiteman, 139 Tex. 522, 163 S.W.2d 638; Kelvin Lumber & Supply Co. v. Copper State Mining Co., Tex.Civ.App., 232 S.W. 858. The first special issue, however, was surplusage, because the second was a proper submission.

*459 Defendant Martin’s next point is that there is no evidence which supports the jury’s finding to the second issue. The jury found that Darcy obtained the required written consents in sufficient time for Martin, in the exercise of reasonable diligence, to have commenced the actual drilling of the well by August 10, 1959. Martin’s sole attack upon that finding is that there is no evidence to support it. Our search of the record shows that there is much direct evidence and many inferences which support the finding. When Martin accepted the contract and mailed his letter on July 29 from San Antonio to Houston, he knew that he had only thirteen days before the crucial date. In a sense, both parties knew from the beginning that time was limited. Both parties knew that the consents were necessary. Sun’s consent to move on the premises was available on August 7. All consents were in hand on August 8. Martin still had August 8 and all of August 9 and 10, to begin actual drilling. Armstrong v. Palmer, Tex.Civ.App., 218 S.W. 627; Goldman v. Broyles, Tex.Civ.App., 141 S.W. 283; Andres v. Armstrong, 168 Cal.App.2d 344, 335 P.2d 1005; Heinsch v. Kirby, 223 Minn. 302, 26 N.W.2d 363. The question is not whether this Court disagrees with the finding, but to decide if there is more than a scintilla of evidence upon which the jury could have made such a finding. Martin details the steps incident to actual drilling. One must reach an agreement with a driller; a drilling permit must be obtained; the site must be surveyed, staked and cleared; pits must be dug; water must be obtained ; the rig must be moved, set up, and the bit actually turned. However, the evidence in the record shows that these steps usually are taken simultaneously. While one thing is being done, others are also being executed. There is proof that many steps, short of entering upon the premises, as normal procedure, would be taken even before Sun gave its consent. The proof shows that Martin had in fact already engaged a driller for the well, but let him go on August 4. The driller’s rig was in Live Oak County, which adjoins McMullen County, and was available. Martin could have taken steps to obtain a drilling permit. The proof from several witnesses is that even after August 8 he could have obtained a permit as a routine matter. The Railroad Commission has an office in San Antonio. There was evidence that applications may be made by telegraph and are often granted on the same day. One witness testified at length and offered several of his former telegraphic applications and permits in evidence. One permit was obtained in three hours. Witnesses testified that staking, clearing and digging the pits would take about half a day, and such work is usually and often done while the rig1 is moving along the highway to the premises. Mr. Scott, an experienced oil man, testified to these facts. He stated that men and equipment for this work were readily available. Mr. Rig-by, a driller, testified that it was not unusual for a driller to move and be completely rigged up on the same day. The most com>-pelling evidence, however, is supplied by Martin himself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Otolaryngology Associates v. Mobilease, Inc.
786 S.W.2d 399 (Court of Appeals of Texas, 1990)
Krupicka v. White
584 S.W.2d 733 (Court of Appeals of Texas, 1979)
Home-Stake Production Company v. Minnis
1968 OK 57 (Supreme Court of Oklahoma, 1968)
Dunham v. Stephens
423 S.W.2d 957 (Court of Appeals of Texas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
357 S.W.2d 457, 4 A.L.R. 3d 278, 1962 Tex. App. LEXIS 2440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-darcy-texapp-1962.