Martik Bros. v. Huntington National Bank

356 F. App'x 602
CourtCourt of Appeals for the Third Circuit
DecidedDecember 8, 2009
DocketNo. 09-1455
StatusPublished

This text of 356 F. App'x 602 (Martik Bros. v. Huntington National Bank) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martik Bros. v. Huntington National Bank, 356 F. App'x 602 (3d Cir. 2009).

Opinion

OPINION OF THE COURT

GREENBERG, Circuit Judge.

This matter comes on before this Court on an appeal from an order for summary judgment entered in favor of the defendant-appellee Huntington National Bank (“Huntington”) on January 14, 2009, in this action that plaintiff-appellant Martik Brothers, Inc. (“Martik”) brought against Huntington. See Martik Bros., Inc. v. Huntington Nat’l Bank, 2009 WL 89282 (W.D.Pa. Jan.14, 2009) (“Martik”). The action arose from Kiebler Slippery Rock, LLC’s (“Kiebler”) development of a student housing project (“Project”) near Slippery Rock University in Slippery Rock Township, Butler County, Pennsylvania. Huntington financed the Project in accordance with a Construction Loan Agreement with Kiebler dated October 10, 2006, in which Huntington agreed to provide up to $29,521,368 for construction to be secured by two mortgages on the property on which Kiebler was constructing the Project. Martik was Kiebler’s general contractor on the Project pursuant to two contracts it entered into with Kiebler on or [603]*603about August 29, 2006. Though Huntington made its loan to Kiebler and not to Martik, it disbursed proceeds from the loan by wire transfer directly to Martik upon receipt of Martik’s approved draws as work on the Project progressed.1

During the course of the construction financial difficulties arose on the Project that resulted in Huntington not making payments on Martik’s final draw in September 2007. Consequently, Martik initiated arbitration proceedings against Kiebler in accordance with a standard arbitration provision in the construction contracts, and in those proceedings Mar-tik obtained an arbitration award against Kiebler for $2,687,781.38, plus interest and costs to cover the shortfall.2 Kie-bler, however, is in bankruptcy and has not paid the award. Martik did not have a contract with Huntington and thus ordinarily Martik, as it recognizes, would not be able to look to Huntington for payment on its contracts with Kie-bler even though Huntington had been making payments directly to Martik for its work on the Project.

Nevertheless Martik believes that Huntington is liable to it for an amount equal to the arbitration award as a consequence of certain representations that Huntington made to Martik. In this regard it is undisputed for purposes of these summary judgment proceedings that Martik expressed its concerns about payment to Richard Dexter, a Huntington construction risk manager, on three occasions.3 The first of the occasions followed a meeting regarding the Project in June 2007 at which Kiebler, Martik and Huntington were represented. Prior to that meeting Huntington had for a number of months been aware of financial difficulties on the Project and the meeting was held to address that situation. Following the meeting, Frank Martik, Martik’s representative at the meeting, asked Dexter who was present with another of Huntington’s representatives, whether Martik would have anything to worry about with respect to payment to it. Dexter said “No. There’s nothing to worry about.” App. at 171. The other Huntington representative present did not contradict Dexter on this point. Notwithstanding Dexter’s assurances to Frank Martik on the day of the meeting, Frank Martik obviously was uneasy, as it later turned out with good reason, for the next business day he called Dexter and again asked him if Kiebler had sufficient funds left in the loan to pay Martik for the remainder of the work under its contracts. Dexter answered “yes.”

Dexter’s assurances, however, were misplaced because in September 2007, on the third occasion when Frank Martik asked Dexter about payment for Martik’s work on the Project, at a time by which Martik [604]*604substantially had finished its work but had not been paid on its final draw, Dexter told him that there were not sufficient funds to cover the draw. Frank Martik during his deposition indicated that if Dexter had told him in June that the funds were not sufficient to pay Martik it would have pulled off the job. Instead, Martik remained on the job, which now has been completed, and Martik thereby became entitled to substantial additional payments on its construction contracts as evidenced by the arbitration award.4 Significantly, notwithstanding Dexter’s assurances to Frank Martik in June 2007, when Dexter told Frank Martik that there were sufficient funds to pay Martik, Dexter’s contemporaneous internal Construction Monitoring Report showed that there was a shortfall of $1,077,000 dollars on the Project. Dexter, however, did not advise Frank Martik of the shortfall or of the report.

By reason of its final draw on the Project not having been paid, Martik brought this action against Huntington advancing three theories in support of its claim with which we are concerned on this appeal. First, Martik contended that Huntington made misrepresentations regarding the availability of funding under the construction loan to pay Martik and the misrepresentations caused Martik to continue work on the Project and thereby become enti-tied to payments which have not been made. Second, Martik contended that it detrimentally relied on Huntington’s promises and stayed on the Project and thus Huntington, by reason of a legal theory predicated on promissory estoppel, is liable for an amount equal to the arbitration award.5 Third, Martik contended that Huntington was unjustly enriched at Mar-tik’s expense and therefore is liable to Martik.6 Martik, 2009 WL 89282, at *1.

After completion of discovery, Huntington successfully moved for summary judgment against Martik. In its opinion granting that motion the District Court explained that the elements of the tort of intentional misrepresentation under the applicable Pennsylvania law are a misrepresentation which is material to the transaction at hand made falsely, with knowledge of its falsity or recklessness as to whether it is true or false; with the intent of misleading another into relying on it; justifiable reliance on the misrepresentation; and a resulting injury being proximately caused by the reliance. Martik, 2009 WL 89282, at *6. See Bortz v. Noon, 556 Pa. 489, 729 A.2d 555, 560 (1999); Gibbs v. Ernst, 538 Pa. 193, 647 A.2d 882, 889 (1994). The District Court then set forth more completely than we have done the history of the events leading to this litigation including the two statements [605]*605that Dexter made to Frank Martik in June 2007 regarding the availability of funding and the circumstance that Dexter by that time had concluded that there was a financial shortfall on the Project.

The District Court concluded from the facts that:

It is doubtful that Mr. Dexter’s rather casual statements themselves or any other evidence adduced by Martik can support an inference that the representations were made falsely, with knowledge of their falsity or recklessness as to whether they were true or false, or that Martik would be justified in relying on such informal and non-specific conversations to assure it that there were sufficient funds to complete the project and pay Martik in full. [Huntington] offers evidence to support its contention that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santos Ex Rel. Beato v. United States
559 F.3d 189 (Third Circuit, 2009)
Mitchell v. Moore
729 A.2d 1200 (Superior Court of Pennsylvania, 1999)
Bortz v. Noon
729 A.2d 555 (Supreme Court of Pennsylvania, 1999)
Gibbs v. Ernst
647 A.2d 882 (Supreme Court of Pennsylvania, 1994)
Lehigh Valley Hospital v. County of Montgomery
768 A.2d 1197 (Commonwealth Court of Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
356 F. App'x 602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martik-bros-v-huntington-national-bank-ca3-2009.