Martha A. Powers Trust v. Board of Environmental Protection

2011 ME 40, 15 A.3d 1273, 2011 Me. LEXIS 41
CourtSupreme Judicial Court of Maine
DecidedMarch 24, 2011
StatusPublished
Cited by4 cases

This text of 2011 ME 40 (Martha A. Powers Trust v. Board of Environmental Protection) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martha A. Powers Trust v. Board of Environmental Protection, 2011 ME 40, 15 A.3d 1273, 2011 Me. LEXIS 41 (Me. 2011).

Opinion

GORMAN, J.

[¶ 1] Martha A. Powers Trust and Brian Raynes (collectively Trust) appeal, pursuant to 38 M.R.S. § 346(4) (2010),1 from a decision of the Board of Environmental Protection. The Board approved the issuance of permits to Evergreen Wind Power II, LLC (Evergreen), to construct the Oakfield Wind Project. The Trust contends that the Board abused its discretion in denying the Trust’s request to hold a public hearing, and that the Board erred in finding that Evergreen met applicable licensing requirements with respect to the health effects from noise, decommissioning the project, and financial capacity to fund the project. Because we conclude that the Board did not abuse its discretion or err in its findings, we affirm the Board’s decision.2

[1276]*1276I. BACKGROUND

[¶ 2] On April 7, 2009, Evergreen filed an application with the Department of Environmental Protection for permits to construct the Oakfield Wind Project, a fifty-one-megawatt wind energy generation facility, in the Town of Oakfield. See 35-A M.R.S. §§ 3452-3455 (2008);3 38 M.R.S. §§ 480-A to 480-GG, 481-490 (2008).4 Evergreen’s project involves the construction of thirty-four wind turbines, to be located along the ridgelines of Sam Drew Mountain and Oakfield Hills; access roads and a crane path; approximately twelve miles of an electrical collector line; an electrical collector substation; four meteorological towers; and an operations and maintenance building. This project is an “expedited wind energy development” because it is “a grid-scale wind energy development that is proposed for location within an expedited permitting area.” 35-A M.R.S. § 3451(4) (2010).

[¶ 3] In its application, Evergreen stated that the project would cost approximately $125 million, and that First Wind Holdings, LLC, would provide initial funding for the project. Evergreen submitted a letter from First Wind stating that First Wind is committed and able “to fund the development, construction, and operation of the approximately $125 million Oakfield Wind Project.” Evergreen’s application also included a letter from HSH Nord-bank, which recited that HSH Nordbank “has a strong working relationship with First Wind,” and that it is “a likely candidate to provide the debt financing for the Project.” In terms of a decommissioning plan, Evergreen stated that it would reserve $50,000 for decommissioning in each of the first seven years of the project, starting from the time of construction. Evergreen also proposed to reassess decommissioning costs by the end of year fifteen of the project’s operation. After the reassessment, Evergreen would then reserve the remaining balance of the decommissioning costs.

[¶ 4] With its application, Evergreen submitted a “Sound Level Assessment” prepared by an engineering company, which concluded that “sound levels from operation of the Oakfield Wind Project will not exceed Maine DEP sound level[ ] limits during construction or routine operation.” See 38 M.R.S. § 484(3)(B); 2 C.M.R. 06 096 375-6 to -15 § 10 (2001). To “verify” compliance with the Department’s sound level limits, the engineering company recommended that Evergreen monitor actual sound levels during operation of the project.

[¶ 5] During the Department’s review of Evergreen’s application for the Oakfield Wind Project, the Trust, which owns property in the vicinity of the project, submitted comments regarding concerns about the project. The Trust questioned the accuracy of the “Sound Level Assessment” prepared by the engineering company, and presented evidence in an effort to show that operation of the wind turbines would cause adverse health effects.

[¶ 6] In its review of Evergreen’s application, the Department hired a noise control consultant, who concluded that the sound assessment submitted by Evergreen was “reasonable and technically correct according to standard engineering practices and the Department Regulations on Con[1277]*1277trol of Noise.” The Department also consulted with the Maine Center for Disease Control (MCDC). The MCDC issued a report in June 2009, which stated that it “found no evidence in peer-reviewed medical and public health literature of adverse health effects from the kinds of noise and vibrations [emitted] by wind turbines.” In July 2009, the Department held a public meeting in Oakfield to provide an opportunity for the public to submit information or ask questions about the project.

[¶ 7] On January 21, 2010, the Commissioner of Environmental Protection approved Evergreen’s application for the Oakfield Wind Project.5 The Trust appealed the Commissioner’s decision to the Board of Environmental Protection. In its appeal, the Trust requested that the Board conduct a public hearing with respect to Evergreen’s compliance with the Department’s sound level limits and the health effects of noise from operation of the wind turbines.

[¶ 8] On June 11, 2010, the Board issued an order denying the Trust’s request for a public hearing and approving Evergreen’s application for development of the Oakfield Wind Project, subject to several conditions. The Board required Evergreen to submit final documentation of its financial capacity before beginning construction of the project, and also conditioned its approval on certain adjustments to Evergreen’s decommissioning plan. Finally, the Board ordered Evergreen to implement a sound level compliance plan to monitor actual sound levels during routine operation of the project. The Trust appeals from the Board’s decision.

II. DISCUSSION

A. Public Hearing

[¶ 9] On appeal, the Trust contends that the Board was required to hold a public hearing. We addressed this exact argument in Concerned Citizens to Save Roxbury v. Board of Environmental Protection, 2011 ME 39, ¶¶ 18-23, 15 A.3d 1263, 1270-71. In that case, we determined that the Board has discretion to decide whether to hold a public hearing when reviewing the Commissioner’s decision on an application for an expedited wind energy development. Concerned Citizens to Save Roxbury, 2011 ME 39, ¶ 23, 15 A.3d at 1271; see also 38 M.R.S. § 345-A(1-A), (2) (2010); 38 M.R.S. § 341-D(4), (4)(D) (2009);6 2 C.M.R. 06 096 002-4 to -5, -12 §§ 7(B)-(C), 24(B)(7) (2003).

[¶ 10] The Trust also argues that the Board abused its discretion in denying the Trust’s request to conduct a public hearing. In this case, the Board concluded that the record was “adequately developed with regard to the statutory criteria” and that the Trust “did not demonstrate that a public hearing is warranted due to conflicting technical evidence on a licensing criterion or in order for the Board to understand the evidence.” When the Board denied the Trust’s request for a public hearing on the issues of compliance with the Department’s sound level limits and the health effects of noise, the Board had before it a voluminous record. The record included numerous comments, letters, and reports questioning the accuracy of Evergreen’s sound assessment, includ[1278]*1278ing a review prepared by a noise consultant on behalf of the Trust; literature and articles relating to the health effects of nighttime noise; and other information relating to noise propagated by wind turbines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2011 ME 40, 15 A.3d 1273, 2011 Me. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martha-a-powers-trust-v-board-of-environmental-protection-me-2011.