Marshalls of Nashville, Tennessee, Inc. v. Harding Mall Associates, Ltd.

799 S.W.2d 239, 1990 Tenn. App. LEXIS 393
CourtCourt of Appeals of Tennessee
DecidedJune 8, 1990
StatusPublished
Cited by16 cases

This text of 799 S.W.2d 239 (Marshalls of Nashville, Tennessee, Inc. v. Harding Mall Associates, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshalls of Nashville, Tennessee, Inc. v. Harding Mall Associates, Ltd., 799 S.W.2d 239, 1990 Tenn. App. LEXIS 393 (Tenn. Ct. App. 1990).

Opinion

TOMLIN, Presiding Judge, (W.S.)

Marshalls of Nashville, Tennessee, Inc. (hereafter “Plaintiff”) filed suit in the Chancery Court for Davidson County against Harding Mall Associates (hereafter “Defendant”) for damages resulting to Plaintiff’s premises and merchandise. Plaintiff leased its premises from Defendant and contends that the damages it sustained resulted from Defendant’s alleged breach of lease and tortious conduct. Following a bench trial, the chancellor found for Defendant and dismissed Plaintiff’s complaint. Plaintiff contends on appeal that the chancellor erred in dismissing its complaint. We find no error and affirm.

Plaintiff became a tenant in the Harding Mall Shopping Center owned by Defendant in 1983 when it took over the space occupied by Service Merchandise, assuming its lease. The lease was duly assigned to Plaintiff with the consent of Defendant. Plaintiff began to experience roof leaks almost immediately after it became Defendant’s tenant. These leaks continued over a two-year period. Defendant undertook to repair the roof in certain areas from time to time. In addition, Defendant installed a system of channels between the structural roof and the suspended ceiling in Plaintiff’s store in order to catch the water as it leaked through the roof. This water was diverted into a catch basin and ultimately removed.

Plaintiff initially filed suit against Defendant in December, 1985, alleging a breach of Article 16, the “Quiet Enjoyment” provision of the lease, contending that Defendant had failed to keep the roof in good repair as required by Article 4 of said lease. In addition, Plaintiff sought a declaratory judgment against Defendant that would require Defendant to replace the roof. At the same time, Plaintiff began paying its rent owed to Defendant under the lease into the Registry of the Chancery Court. Defendant counter-claimed for damages, alleging that any defects or deficiencies in the roof were caused by the Plaintiff’s negligent installation of two roof-top air conditioning units. Plaintiff filed a supplemental complaint alleging that it had suffered additional damages from continuing roof leaks.

In April, 1986, Defendant filed a motion seeking to have the funds on deposit with the court released or a limitation placed on the funds deposited in the court. Before a hearing could be held on the motion, the parties entered into a settlement agreement referred to as the “Mutual Release Agreement” (hereafter “MRA”) on June 18, 1986. The MRA provided that the parties agreed to release each other from any and all claims, liabilities and causes of action alleged by either party in the original action filed by Plaintiff. Defendant was committed to replacing the roof according to specifications set forth in a proposal by ENCON Roofing Consultants “by contract with a licensed, bonded, and responsible roofer chosen by defendant but acceptable to plaintiff.” Under the terms of the MRA, Plaintiff and Defendant were to share the cost of replacing the roof, with Defendant paying sixty percent and Plaintiff forty percent. The MRA provided that Plaintiff was to recover its forty-percent *241 contribution toward the replacement of the roof when Harding Mall was sold by Defendant or its successor.

Defendant recommended to Plaintiff that Richard Boyanton, d/b/a RGM Enterprises (hereafter “Boyanton”), a roofing contractor, be employed to replace the roof. Defendant’s attorney, Joel Leeman, contacted Lee Davies, Plaintiff’s attorney, for the purpose of obtaining Plaintiff’s approval of Boyanton. Leeman advised Davies that Boyanton had performed satisfactory work for Defendant in the past. Davies passed this information on to Plaintiff. Without checking his available references, Plaintiff approved Boyanton as the roofing contractor. Although not clearly stated in the record, it appears that the requirement that Boyanton be bonded was waived. Defendant thereupon entered into a contract with Boyanton to replace the roof. As such, Boyanton functioned as an independent contractor on the job. Plaintiff employed John Downs, d/b/a ENCON Roofing Consultants, (hereafter “Downs”) to monitor Boyanton’s work.

Replacement of the roof began on or about June 23, 1986. On that same day Downs visited the site and inspected Boy-anton’s work. He discovered that Boyan-ton was not installing the new roof in a workmanlike manner, nor was the installation being done in accordance with standard roofing practices. Downs’ inspection revealed several deficiencies in Boyanton’s work, which he reported to the appropriate parties, to-wit: (1) The loose gravel that had been removed from the roof was piled up in such a manner as to create the danger of a roof cave-in; (2) there was insufficient roofing equipment on the job site to carry out the work required; (3) the roofing material stored on the site was not stored in a proper fashion to protect it from moisture; (4) materials dumped on the ground created a safety hazard; (5) there was no firefighting equipment on the job site; (6) the roofing felts were installed in an unacceptable manner and did not conform to standard roofing procedures; (7) there was a failure to put asphalt coating on the felts installed; and (8) the tie-in of the new roof to the existing roof was inadequate and was not leak-proof. When questioned by Downs about the potential for leaks in the area under repair, Boyanton responded “don’t worry about it, we’ll take care of it.” Downs immediately contacted Davies and advised him of the deficiencies. Davies in turn informed Leeman by telephone. According to Davies, the conversation with Leeman was to the effect that Plaintiff was overly concerned with the roofing project, and if there were any problems they would be corrected. Leeman, however, testified that he did not recall advising Davies that Plaintiff was overreacting.

A rainstorm of some proportions occurred on the night of June 23, 1986. As a result, water entered Plaintiff’s store through the portion of the roof that was being repaired by Boyanton, damaging the interior of Plaintiff’s store, including its merchandise. Plaintiff subsequently filed a second supplemental complaint in January, 1987 for damages sustained as a result of the June 23rd incident. That complaint alleged that Defendant breached “Article 4 Repairs” of the lease by failing to keep the roof in good order and repair at its own cost and expense, and that such failure to keep the roof in good repair interrupted Plaintiff’s quiet enjoyment of the leased premises in violation of “Article 16 Quiet Enjoyment.” In addition, Plaintiff alleged that Defendant had made negligent misrepresentations as to Boyanton’s abilities, that it was negligent in selecting an incompetent independent contractor, and was thus vicariously liable upon the theory that the work to be performed by Boyanton was inherently dangerous to Plaintiff.

In March, 1987, the chancellor entered an agreed order which referred to a second Mutual Release Agreement dated July 25, 1986. That order provided that certain claims had been compromised and settled, and that the causes of action alleged by Plaintiff in its initial complaint and the first supplemental complaint, and the causes of action set forth by Defendant in its counter-claim should be dismissed with prejudice. The order specifically provided that “[i]n accordance with the agreements be *242 tween these parties, said dismissal shall in no way affect ... those causes of action asserted on behalf of the Plaintiff in its ‘Second Supplemental Complaint’.... ”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weeks v. Sands
W.D. Tennessee, 2021
Anthony Parker v. ABC Technologies, Inc.
Court of Appeals of Tennessee, 2021
Abdighani K. Hashi v. Parkway Xpress, LLC
Court of Appeals of Tennessee, 2019
Turnage v. Oldham
346 F. Supp. 3d 1141 (W.D. Tennessee, 2018)
James Heflin v. Iberiabank Corporation
571 S.W.3d 727 (Court of Appeals of Tennessee, 2018)
Kim Brown v. Christian Brothers University
428 S.W.3d 38 (Court of Appeals of Tennessee, 2013)
Doe v. Catholic Bishop for the Diocese of Memphis
306 S.W.3d 712 (Court of Appeals of Tennessee, 2008)
Allen v. Sulcer
255 S.W.3d 51 (Court of Appeals of Tennessee, 2007)
Shelby v. Delta Air Lines, Inc.
842 F. Supp. 999 (M.D. Tennessee, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
799 S.W.2d 239, 1990 Tenn. App. LEXIS 393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshalls-of-nashville-tennessee-inc-v-harding-mall-associates-ltd-tennctapp-1990.