Marr v. Webb
This text of 930 So. 2d 734 (Marr v. Webb) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Stuart D. MARR, Appellant,
v.
Edward T. WEBB, et al., Appellees.
District Court of Appeal of Florida, Third District.
*735 Hershoff, Lupino & Yagel and Russell A. Yagel and James S. Lupino, Tavernier, for appellant.
Gus H. Crowell, Tavernier; Jose M. Herrera, Miami, for appellees.
Before RAMIREZ and CORTIÑAS, JJ., and SCHWARTZ, Senior Judge.
CORTIÑAS, Judge.
Appellant, Stuart Marr ("Marr"), appeals from an order vacating an arbitration award and reserving jurisdiction to modify the award.
In February 1994, Marr entered into three residential construction agreements ("contracts") with Edward T. Webb, Enrique Benitez, and Seagate Mechanical, Inc. (collectively the "Contractors"). The contracts were for the construction of three single family "spec" homes on real *736 property owned by Marr and located in Key Largo, Florida. Pursuant to the contracts: (1) the Contractors were to be paid upon the sale of the subject homes; (2) Marr would allow his real property to serve as collateral for loans to be taken out by the Contractors; and (3) the profits obtained would be equally divided (50/50) between Marr and the Contractors after the sale of the homes.
Additionally, the contracts provided that any dispute arising between the parties would be resolved by arbitration. The arbitration clause in the contracts specifically stated:
All claims or disputes between the Contractor and the Owner arising out of or relating to the Contract Documents, or the breach thereof, shall be decided by arbitration....
The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
The contracts also included "Addendum 4," which provided that, when the properties were sold, the monies would be divided as follows:
1. Owner will be reimbursed for land costs.
2. Contractor shall be reimbursed for construction costs incurred.
3. Balance of proceeds, after deducting sales costs, will be divided equally between owner and contractor.
In August 1996, Marr provided the Contractors with financing for the construction of the homes at an interest rate of 11.25%. The Contractors later advised Marr, by a letter dated January 5, 1997, that they were "unable to complete the three houses" and were modifying the contracts. The Contractors' letter requested that Marr loan funds and hire personnel to complete the construction on the homes. In return, the Contractors agreed to repay Marr at an 11% interest rate from the sale proceeds of the first home sold. Marr ultimately provided funding, and claims that he expended $1,033,475.67 of his own funds to complete the homes, which were eventually sold.
Thereafter, a dispute arose between Marr and the Contractors. The Contractors claimed that a net of $2,527,595.00 remained after all costs and construction loans were paid and that $1,242,595.00 remained after Marr reimbursed himself for his real property, but that Marr did not pay the Contractors their percentage of the profit. On the other hand, Marr claimed that the Contractors were not entitled to the money because no profit resulted from completing the homes, as said money was reimbursement for the costs he expended to complete the homes and pay off the construction loans.
The Contractors filed an action in the trial court, which was abated pending arbitration. An arbitration proceeding was held before a panel of three arbitrators, wherein the parties presented their evidence and claims. After three days of hearings, the arbitrators entered an award in favor of the Contractors for damages and pre-judgment interest in the amount of $80,000.00. The arbitrators further awarded $30,851.00 on a promissory note to a third party, Eric Benitez. The Contractors subsequently filed a motion to modify and/or correct the arbitrators' award. After a hearing, the trial court entered an order vacating the arbitration award and reserving jurisdiction to determine the correct amount of the award to be entered. The trial court found that the arbitrators exceeded their authority and departed from the parties' contractual agreement, and that the arbitrators failed to follow the parties' contractual formula in *737 "Addendum 4" for the payment and distribution of profits.
In reviewing the trial court's order, we review findings of fact for competent substantial evidence and questions of law de novo. LeNeve v. Via South Florida, L.L.C., 908 So.2d 530, 534 (Fla. 4th DCA 2005) (citing Boyhan v. Maguire, 693 So.2d 659, 662 (Fla. 4th DCA 1997)). However, our review of the arbitrators' decision to grant a certain award "`is very limited, with a high degree of conclusiveness attaching to an arbitration award.'" See Charbonneau v. Morse Operations, Inc., 727 So.2d 1017, 1019 (Fla. 4th DCA 1999) (quoting Applewhite v. Sheen Fin. Res., Inc., 608 So.2d 80, 83 (Fla. 4th DCA 1992)). This limited review is necessary to "avoid a `judicialization' of the arbitration process," and "to prevent arbitration from becoming merely an added preliminary step to judicial resolution rather than a true alternative." Charbonneau, 727 So.2d at 1019 (citing Chandra, M.D. v. Bradstreet, 727 So.2d 372 (Fla. 5th DCA 1999)).
Section 682.13(1), Florida Statutes (2005), enumerates five grounds for vacating an arbitration award, and provides, in relevant part:
(1) Upon application of a party, the court shall vacate an award when:
(a) The award was procured by corruption, fraud or other undue means.
(b) There was evident partiality by an arbitrator appointed as a neutral or corruption in any of the arbitrators or umpire or misconduct prejudicing the rights of any party.
(c) The arbitrators or the umpire in the course of her or his jurisdiction exceeded their powers.
(d) The arbitrators or the umpire in the course of her or his jurisdiction refused to postpone the hearing upon sufficient cause being shown therefor or refused to hear evidence material to the controversy or otherwise so conducted the hearing, contrary to the provisions of s. 682.06, as to prejudice substantially the rights of a party.
(e) There was no agreement or provision for arbitration subject to this law, unless the matter was determined in proceedings under s. 682.03 and unless the party participated in the arbitration hearing without raising an objection.
§ 682.13, Fla. Stat. (2005) (emphasis added). In the absence of one of the five factors set forth in the statute, neither the trial court nor this court has the authority to overturn the arbitration award. Schnurmacher Holding, Inc. v. Noriega, 542 So.2d 1327, 1328 (Fla.1989); LeNeve, 908 So.2d at 534. In the instant appeal, we only address subsection (c) to determine whether the arbitrators exceeded their powers in entering the arbitration award.
The Contractors contend that the arbitrators exceeded their authority by improperly accounting for costs, losses, and profits as if the parties had a joint venture relationship. The Contractors contend that the arbitrators should have followed the contractual formula in "Addendum 4" instead.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
930 So. 2d 734, 2006 WL 1196455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marr-v-webb-fladistctapp-2006.