Mark Latham Excavation, Inc. v. Deschutes County

281 P.3d 644, 250 Or. App. 543, 2012 Ore. App. LEXIS 779
CourtCourt of Appeals of Oregon
DecidedJune 20, 2012
Docket2011078; A150685, A150693
StatusPublished
Cited by9 cases

This text of 281 P.3d 644 (Mark Latham Excavation, Inc. v. Deschutes County) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Latham Excavation, Inc. v. Deschutes County, 281 P.3d 644, 250 Or. App. 543, 2012 Ore. App. LEXIS 779 (Or. Ct. App. 2012).

Opinion

NAKAMOTO, J.

Deschutes County, Eric and Ronna Hoffman, Sanders Nye, and Cascades Academy of Central Oregon (collectively, respondents) seek judicial review of a final opinion and order of the Land Use Board of Appeals (LUBA), in which LUBA remanded a land use decision of Deschutes County.1 The county’s decision granted petitioner, Mark Latham Excavation, Inc., site plan and conditional use approval to expand an existing mining operation but imposed a condition of approval that prohibited further mining of a headwall2 until a post-acknowledgement plan amendment is submitted and approved for that use. In remanding, LUBA sustained petitioner’s objection to that condition and rejected the county’s underlying determinations: that the county’s Program to Meet the Goal (PTMG) — a legislative enactment to accomplish statewide land use goals — was ambiguous and that the county would have enacted a different PTMG had it known the headwall on the subject property would be extensively mined, as petitioner plans. For the reasons stated below, we reverse and remand LUBA’s decision.

The 80-acre property subject to this dispute is just north of Bend, approximately one mile southwest of Tumalo State Park, and 500 feet west of the Deschutes River. In 1995, the county granted the prior owner of the property, Cascade Pumice, a permit to mine pumice until 2007, when petitioners purchased the property. Petitioners sought a conditional use permit to expand the mining operation to include, among other things, mining 3.4 million cubic yards of tuff and further mining into the side of a prominent hill situated along the south side of the site.

Before we discuss the specifics of the county’s decision approving the application, we pause to give a brief overview of the county’s Goal 5 planning history, which is pertinent to the county’s decision, LUBA’s opinion, and the [546]*546parties’ arguments. Goal 5 is a statewide planning goal enacted to “protect natural resources and conserve scenic, historic, and open space resources.” Goal 5; see OAR 660-015-0000(5). As specified in OAR chapter 660, division 16, local governments must conduct three tasks to comply with Goal 5. First, local governments must inventory key resource sites. OAR 660-016-0000. Second, local governments must identify conflicts with the inventoried Goal 5 resource sites and determine the “Economic, Social, Environmental and Energy” (ESEE) consequences of allowing conflicting uses for those sites.3 OAR 660-016-0005(1). Finally, based on the determination of the ESEE consequences, the local government must develop a “program to achieve the Goal.” OAR 660-016-0010. When enacting a “program to achieve the Goal,” the local government has three options. It can completely protect the resource, allow conflicting uses fully, or allow the conflicting use but in a limited way so as to protect the resource site. OAR 660-016-0010(1) - (3).

In 1990, the county enacted a series of ordinances to comply with its Goal 5 planning obligation for mineral and aggregate resources. The county enacted Deschutes County Ordinance (DCO) 90-025, which adopted an inventory of significant mineral and aggregate sites, including petitioner’s site. The county also enacted DCO 90-029, an ordinance that adopted the “ESEE Findings and Decision” (ESEE decision) for petitioner’s site. The ESEE decision addressed each of the three steps required by OAR chapter 660, division 16: an inventory of resources on the site, an analysis of conflicting uses, and the county’s program to meet the goal.

As for resources on the site, petitioner’s predecessor, Cascade Pumice, represented to the county that less than 25 acres of the site would actually be mined. The ESEE decision for petitioner’s site identified 750,000 cubic yards of pumice and 10,000 cubic yards of sand and gravel to be mined, but did not identify tuff, a type of volcanic rock, as a resource. The ESEE decision then identified conflicting uses and discussed the ESEE consequences of the conflicting uses. At the end of the discussion, the county elected to adopt a “Program to [547]*547Meet the Goal” under OAR 660-016-0010(3) to limit both the extraction of the resource and the conflicting uses. Pertinent to this appeal is paragraph 23 of the PTMG, which provides:

“The Board finds that in order to protect both the aggregate resource and the conflicting resources and uses, the site * * * will be zoned for surface mining, subject to the following ESEE conditions:
“(a) Setbacks shall be required for potential conflicting residential and other development;
“(b) Noise and visual impacts shall be mitigated by buffering and screening, with particular attention paid to screening from Tumalo State Park or the eastern, northeastern and southeastern boundaries;
“(c) Hours of operation shall be consistent with DEQ standards and applicable county ordinances;
“(d) Wildlife restrictions set forth in [Oregon Department of Fish and Wildlifefs letter of August 10,1989, shall apply;
“(e) Excavation shall be limited to five acres with ongoing incremental reclamation (subject to [Department of Geology and Mineral Industries] review and approval);
“(f) Mining operations, including placement of processing operations and equipment and excavation and transport of material shall meet all applicable DEQ noise and dust standards.
“The Board finds that processing on site will be allowed.”

Thus, in its PTMG, the county determined that it would apply the surface mining zone to the site. That zone imposes a number of limitations or requirements on mining to reduce off-site impacts, including setbacks, screening, and noise and operational limitations. Other than limiting the excavation site to five acres, the PTMG did not restrict where petitioner could mine, and it did not mention the hillside.

With the above background in mind, we turn to the facts that led up to this judicial review. Petitioner purchased the subject property from Cascade Pumice in 2007 and submitted an application to the county to expand mining operations into the hillside. A portion of the northwestern slope of [548]*548the hill has already been mined. The application also sought to mine and export both pumice and tuff. Approval of petitioner’s application would ultimately result in a more pronounced headwall, both in height and length. The existing headwall is visible from the Tumalo State Park campground and associated trails.

In 2009, the county granted a conditional use permit that, among other things, allowed petitioner to mine further into the hillside for tuff as incidental to mining for pumice, the inventoried resource. Two of the respondents in this appeal, Eric and Ronna Hoffman, appealed to LUBA. In 2010, LUBA determined that the county did not adequately explain its reasons for allowing the mining of tuff, and remanded the county’s decision. Hoffman v. Deschutes County, 61 Or LUBA 173 (2010).

In finding that the county’s explanation of its decision that tuff was incidental to pumice mining was insufficiently clear, LUBA noted that petitioner sought to mine approximately 3.4 million cubic yards of tuff and only 700,000 cubic yards of pumice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gould v. Deschutes County
520 P.3d 433 (Court of Appeals of Oregon, 2022)
Deschutes County v. Pink Pit, LLC
475 P.3d 910 (Court of Appeals of Oregon, 2020)
Restore Oregon v. City of Portland
458 P.3d 703 (Court of Appeals of Oregon, 2020)
Michaelson v. City of Portland
437 P.3d 1215 (Court of Appeals of Oregon, 2019)
Crowley v. City of Hood River
430 P.3d 1113 (Court of Appeals of Oregon, 2018)
Nicita v. City of Oregon City
399 P.3d 1087 (Court of Appeals of Oregon, 2017)
Delta Property Co. v. Lane County
352 P.3d 86 (Court of Appeals of Oregon, 2015)
Friends of the Hood River Waterfront v. City of Hood River
326 P.3d 1229 (Court of Appeals of Oregon, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
281 P.3d 644, 250 Or. App. 543, 2012 Ore. App. LEXIS 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-latham-excavation-inc-v-deschutes-county-orctapp-2012.