Mark Gleaves v. Messer Construction Company and PERI Formwork Systems, Inc.

77 N.E.3d 1244, 2017 WL 2544635, 2017 Ind. App. LEXIS 249
CourtIndiana Court of Appeals
DecidedJune 13, 2017
DocketCourt of Appeals Case 49A02-1609-CT-2140
StatusPublished

This text of 77 N.E.3d 1244 (Mark Gleaves v. Messer Construction Company and PERI Formwork Systems, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Gleaves v. Messer Construction Company and PERI Formwork Systems, Inc., 77 N.E.3d 1244, 2017 WL 2544635, 2017 Ind. App. LEXIS 249 (Ind. Ct. App. 2017).

Opinion

Baker, Judge.

On October 9, 2012, Mark Gleaves, a construction worker employed by Whitten-berg Construction (“Whittenberg”), was working at the construction site of the Indiana University Neuroscience Building when a sixteen-foot-long 2x4 lumber infill struck him in the head, inflicting serious injury. Whittenberg was a concrete contractor; Messer Construction Company (“Messer”) was the construction manager of the construction project; and PERI Formwork Systems, Inc. (“PERI”), was the manufacturer of the formwork Whit-tenberg was using to form the walls of the building. Gleaves sued Messer, alleging that it had assumed a duty of reasonable care for his safety on the jobsite and that it breached that duty, and PERI, alleging that it failed to provide adequate warnings and instructions to end users and that it was not an open and obvious danger that lumber infills could eject during the removal process and strike a person standing a safe distance away. The trial court granted Messer’s motion for summary *1247 judgment, finding that Messer did not owe a duty to Gleaves, and PERI’s motion for summary judgment, finding that because the hazard of this construction process is open and obvious, PERI did not have a duty to warn users about the dangers in the use of PERI forms. Gleaves now appeals. Rinding no error, we affirm.

Facts 1

The Accident

Messer contracted with Indiana University (“IU” or “Owner”) for construction management services for the construction of the Neuroscience Building in Indianapolis. Whittenberg also contracted directly with IU to perform concrete work on the building. Whittenberg has performed concrete construction work using concrete formwork at more than one hundred job-sites, and it has used PERI-brand form-work in nearly all of its jobsites over the last fifteen years.

PERI manufactures and supplies formwork systems for concrete contractors’ use in forming new concrete structures until the structures harden and become self-supporting. PERI manufactured and supplied the formwork system that Whittenberg used in this construction project. A PERI form is used to pour concrete walls; the system includes the use of infills to bridge gaps in the formwork. To set PERI forms, large panels are used first; progressively smaller sized panels are then used until the gap is small enough to fill with a lumber infill. Whittenberg supplied the lumber and materials for the infills, and Whittenberg’s carpenters made the infills on the construction site. PERI does not track the construction sites at which its forms are used; at this construction site, Whittenberg controlled the use of the PERI forms, including their location, installation, and removal.

Gleaves’s general duties at the construction site involved cleaning up after the carpenters, cleaning concrete forms, assisting with concrete pours, and retrieving discarded lumber infills used by Whit-tenberg. Gleaves had prior experience working on forming concrete walls, but he had not worked with PERI concrete forms before this construction project. When Gleaves began working on the construction project, Whittenberg had him watch a video about PERI forms. Whittenberg provided Gleaves with personal protection equipment, including a safety harness and a hard hat; it also held weekly and monthly safety meetings for its employees.

On October 9, 2012, a crane was wrecking a section of formwork away from a concrete wall. “Wrecking” is a term of art in the concrete construction industry that involves the dismantling of the form-work used to form a concrete structure after the concrete has cured. Part of the wrecking process involved Whittenberg employees pushing to the ground unsecured lumber infills before removing the PERI forms with overhead cranes and taking them to another area.

Gleaves was working in a trench at the construction site patching tie holes in the concrete walls and picking up material in the trench. As the formwork was pulled up and away by the crane, a sixteen-foot 2x4 lumber infill was ejected from the form being lifted and struck Gleaves in the head while he was in the trench. No audible warning signal was given before the crane lifted the firm that struck Gleaves. Prior to the accident, Gleaves did not see *1248 the crew above him wrecking the form .that led to the accident.

The Contracts

Under Messer’s contract with IU, Messer’s duties were owed to IU and not to any contractors or other third parties. The contract included the following provisions about safety at the construction site:

• Messer was to provide on-site administration of the construction contract.
• Messer was to use its best efforts to obtain satisfactory performance from each contractor, to recommend courses of action to IU when requirements of the construction contract were not being fulfilled, to determine that the work of each contractor was being performed according to the requirements of the construction contract, and to, notify IU .and the- contractor, of defects and deficiencies in the work.
• With respect to ' each contractor’s own work, Messer did not have control over or charge of nor was responsible for construction means, methods, techniques, or safety precautions and programs in connection with the work of each contractor because these things were solely the contractor’s responsibility under its . contract.
• Messer did not have control over or charge of acts or omissions of the , contractors or any other person performing work not directly employed by Messer.
• Messer was required to provide and maintain an effective- safety program. Each contractor was required to conform to Messer’s Safety, Health and Environmental Program and its Safety4Site Program.
• Every worker was required to attend a safety orientation before working on the site. The orientation was to take place in Messer’s trailer.
• If a contractor did not re-erect a barricade or safety device- after the completion of a work activity, Messer would perform the work.
• Upon notification of a safety deficiency, the contractor responsible was to use any and all means necessary to correct the situation immediately. Messer could remove the contractor’s employee or employees if they failed to address the situation.

Messer’s App. Vol. II p. 11, 13, 16-17, 172,

The American Institute of Architects Document 232, which governed general conditions for construction, stated that Messer was to be responsible for the oversight of the health safety programs of the contractors; each contractor was to remain the controlling employer as to its employees and was to comply with the .applicable safety laws; and Messer’s responsibility for review of safety precautions did not extend to direct cqntrol oyer or charge of the acts or omissions of the . contractors or their employees, nor did-it constitute approval of safety precautions or any , construction means, methods, or procedures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunt Construction Group, Inc. v. Garrett
964 N.E.2d 222 (Indiana Supreme Court, 2012)
Williams v. Tharp
914 N.E.2d 756 (Indiana Supreme Court, 2009)
Progressive Insurance v. General Motors Corp.
749 N.E.2d 484 (Indiana Supreme Court, 2001)
Cole v. Lantis Corp.
714 N.E.2d 194 (Indiana Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
77 N.E.3d 1244, 2017 WL 2544635, 2017 Ind. App. LEXIS 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-gleaves-v-messer-construction-company-and-peri-formwork-systems-inc-indctapp-2017.