Marion Steam Shovel Co. v. Aukamp

20 P.2d 851, 172 Wash. 455, 1933 Wash. LEXIS 563
CourtWashington Supreme Court
DecidedApril 4, 1933
DocketNo. 24354. Department One.
StatusPublished
Cited by4 cases

This text of 20 P.2d 851 (Marion Steam Shovel Co. v. Aukamp) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marion Steam Shovel Co. v. Aukamp, 20 P.2d 851, 172 Wash. 455, 1933 Wash. LEXIS 563 (Wash. 1933).

Opinions

Holcomb, J.

Respondent is a dealer in new and used power shovels at Portland, Oregon, H. J. Balzer and his wife being the owners of the agency, the Machinery Company being simply a trade name. Balzer was the agent of respondent in Portland. Appellant is a contractor residing and doing business in Yakima. In the spring of 1930, he had a road building contract with the state for the grading and surfacing on a state highway near Lowden in the vicinity of Walla Walla, which required the movement of about 72,000 yards of material, all of which material was sand or sandy loam with no rock or other hard material.

Although appellant had the contract in his own name, it was, in fact, to be performed by a partnership consisting of himself and one Smith. In performing the work, Smith was to furnish the rock crushing equipment wherever necessary and appellant to furnish the grading machinery and equipment, including trucks. They found it necessary to procure a steam shovel, which shovel appellant was to furnish.

*457 On about March 26, 1930, appellant and Smith went to the office of Balzer in Portland to purchase a shovel. Balzer had a used shovel known as a Type 7, gas friction shovel, made by the Marion Steam Shovel Company. In order to induce appellant to make the purchase, Balzer represented to him that this shovel had been completely disassembled and rebuilt, thoroughly overhauled, and that it would work just as well as a new shovel. He also represented that all of the worn parts had been replaced by new ones, and that it would handle one thousand cubic yards a day of such material as appellant had to move: During the course of negotiations, appellant advised Balzer of the nature of his contract, the time within which it had to be completed and the amount and character of material to be excavated.

In addition to the oral representations, the machine, which was in a somewhat dark shed, was shown to appellant and Smith. It had been newly painted all over, including the working parts, and gave the appearance of a new shovel and of having been entirely taken down and rebuilt. A power shovel is a large and complicated machine, and little can be ascertained as to its condition by an examination of what may be seen from the outside. Balzer was advised that the purchaser could not tell much as to the condition of the machine without running it, upon which he assured appellant that it had been thoroughly overhauled by the Marion Steam Shovel Company, and that when it overhauled a piece of machinery it did it right.

Appellant relied upon representations of Balzer, believed them to be true, and made an executory contract for the purchase of the machine. A cash payment of seven hundred dollars was then made. The machine was to have been shipped so as to arrive at Lowden on March 31, but due to some further necessary re *458 pair it did not arrive until April 7, 1930. Previously, on April 1, 1930, Balzer wrote to appellant, saying:

“We regret it necessary to delay shipment of the shovel. As we advised you, the shovel had been completely disassembled and rebuilt, and all parts showing excessive wear were replaced. In tuning up the shovel, it was naturally necessary to make various adjustments, and we, felt from your conversation you had rather have us make them before shipment, rather than have them made on the job. We want you to have a smooth running shovel from the start, and trust the delay has not seriously inconvenienced you.”

At about the time the machine arrived, appellant signed the executory contract of sale and ten promissory notes for $630 each, which were all dated as of March 26, 1930.

Inasmuch as appellant was unfamiliar with the operation of such a machine, an operator was sent along with the machine from Portland, whose name was Johnson. It developed that Johnson had previously operated the same machine for a contractor near Portland, and the machine was then in a bad condition of repair. This operator had difficulty with the shovel from the start. During the week that he was there, he was unable to make it dig more than about two hours a day. It was continually breaking down, or getting out of adjustment.

When they had attempted to operate it without success for about nine days, it was dragged off the work and respondent was notified, through Balzer. Balzer then sent one Cheatham, a service man in the employ of respondent, to examine and recondition the machine. Cheatham apparently did all within his power to make it run, but was unable to do so. Appellant was about to turn the machine back, but Cheatham induced him to try it a while longer, which he did. Later, one' Cox, who was in the employ of respondent, in *459 duced appellant to try the shovel a while longer, claiming it could be adjusted. On June 24, however, it broke down, and Johnson, the operator, left.

Appellant, then being thoroughly satisfied that it was not merely a matter of adjustment, placed it at the station at Lowden where he had received it, notified respondent that it was at its disposal and that he would pay nothing further on it. On September 6, 1930, he notified respondent, in writing, at its Portland office, to the same effect. It also appeared in evidence that only fifteen of this type of shovel were ever built by respondent, that they proved unsatisfactory, and that this machine wherever sold had to be taken back by respondent, it never having worked properly on any job.

Although the executory contract between respondent and appellant had no affidavit of good faith and was not acknowledged as a chattel mortgage, counsel for respondent conceived that it was a chattel mortgage, at least as between the parties thereto, and had it foreclosed as a chattel mortgage in Walla Walla county, where it had been left by appellant, by sheriff’s notice and sale. No notice thereof was given appellant, other than by posting of notices of chattel mortgage sale by the sheriff of Walla Walla county upon the machine and in three places in the city of Walla Walla. Under that proceeding, the shovel was sold by the sheriff for one thousand dollars.

This action was brought on the notes for the balance remaining due, after the purported sheriff’s sale and for attorney’s fees, as provided in the notes. Appellant answered, setting up the fraudulent representations as outlined herein as a pure defense to the notes, and also alleged that the sale had been rescinded, and asked for special damages sufficient to put appellant in status quo. During the trial of the case the trial *460 court required appellant to elect between the defense of fraudulent representations and that of breach of warranty. Appellant elected to rely on fraud and misrepresentation, both as a matter of pure defense and as a foundation for damages upon the rescission of the contract. The jury returned a verdict in favor of appellant in the sum of $1,264.35.

Respondent moved for a judgment notwithstanding the verdict, and in the alternative for a new trial. The trial court granted judgment notwithstanding the verdict, and further ordered that, in case the judgment n. o. v. was reversed, then a new trial should be had. Judgment was thereupon entered in favor of respondent as prayed in its complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Getty v. Jett Ross Mines, Inc.
159 P.2d 379 (Washington Supreme Court, 1945)
W. T. Rawleigh Co. v. Graham
103 P.2d 1076 (Washington Supreme Court, 1940)
Peoples Bank & Trust Co. v. L. Romano Engineering Corp.
62 P.2d 445 (Washington Supreme Court, 1936)
Webster v. L. Romano Engineering Corp.
34 P.2d 428 (Washington Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
20 P.2d 851, 172 Wash. 455, 1933 Wash. LEXIS 563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marion-steam-shovel-co-v-aukamp-wash-1933.