Marine Office of America Corp. v. M/V VULCAN

891 F. Supp. 278, 1995 U.S. Dist. LEXIS 8840, 1995 WL 375905
CourtDistrict Court, E.D. Louisiana
DecidedJune 13, 1995
Docket92-456, 92-3241 and 94-2196
StatusPublished
Cited by6 cases

This text of 891 F. Supp. 278 (Marine Office of America Corp. v. M/V VULCAN) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marine Office of America Corp. v. M/V VULCAN, 891 F. Supp. 278, 1995 U.S. Dist. LEXIS 8840, 1995 WL 375905 (E.D. La. 1995).

Opinion

ORDER AND REASONS

JONES, District Judge.

The evening of February 26, 1991 was disrupted by the crash of the moving vessel MTV VULCAN into the HISPAMAR, a vessel moored at the Perry Street Wharf in New Orleans. The VULCAN, owned by Rondel Shipping Ltd., (“Rondel”), also damaged Barge MPR-104.

The VULCAN’s owners admitted fault, yet the crash gave rise to numerous claims by several parties. Most of the claims were settled or otherwise resolved prior to trial. The issues remaining were tried in a bench trial which centered on damages, specifically, whether the owners of the HISPAMAR, As-land Cement Corporation (“ACC”), properly mitigated damages during the repair process, and whether ACC is entitled to compensation for missing an opportunity to fulfill a contract in Spain. The matter of punitive damages was severed from the trial.

For reasons more fully stated below, the Court finds that the plaintiff mitigated its damages and is entitled to recover reasonable repair costs, but the plaintiff has failed to show that loss of use damages are due.

This decision constitutes the findings of fact and conclusions of law required under Rule 52 of the Federal Rules of Civil Procedure.

FINDINGS OF FACT

I. Repairs

In an effort to show that the plaintiff failed to mitigate damages, Rondel questioned the propriety of taking the bid of River Construction (“River”), and the expedience and competence of repairs.

A Bidding

A preliminary field survey of damages was completed on February 27, 1991 by Ben Haveman of Technical Maritime Associates, who was certified at trial by ACC as an expert in marine survey and repair. A report was issued on February 28, 1991. (Plaintiffs Exh. 17).

On March 4, the results of Haveman’s preliminary survey were sent to repair companies in order to solicit bids for the repair of the HISPAMAR. Repair companies responded with bids the next day, on March 5.

On March 6, the bid responses were taken to Joaquin Targhetta, president of ACC. The lowest bidders were River, at $3.75/ pound of steel and American Marine Corporation, (“American Marine”), at $3.41/pound. The price per pound included the cost of steel plus the cost of removing and installing the steel. (Plaintiffs Exh. 20).

Haveman testified that the preliminary survey, on which bids were based, was limited to a damage/cost assessment because at the time of the survey, he was working for underwriters. The bidders were not told that time was of the essence since underwriters are interested in cost alone, whereas owners of vessels generally have an additional interest — the time that has to be expended making the repairs.

*281 By March 6, Haveman was working for Targhetta. Targhetta asked Haveman to obtain time estimates from the bidders.

The River bid estimated 24 days for repair — the shortest repair time of any bidder. River’s bid included a 24-hour work day, anchor removal and scaffolding. American Marine did not initially include an estimated time for repairs in its bid.

Acceptance of the American Marine bid would require the HISPAMAR to be moved to American Marine’s repair lot through a 74.5-foot-wide lock. The HISPAMAR, normally 71.5-feet wide, was wider than usual because the vessel was given a Jé to 2 degree list to prevent water from entering a tear that was caused by the crash. Even without the list, the vessel would barely fit the one-foot-minimum allowable clearance through the locks. The owners of the HISPAMAR were also concerned that moving the HISPA-MAR several miles would subject its tear to waves created by passing vessels. River Construction could work on the vessel at Perry Street, thereby reducing risks to the HISPAMAR. Despite the concern for the safety of the vessel in transit, bidders were not informed that the vessel had to stay at the Perry Street Wharf. A subsequent discovery of underwater damage indicates that the choice to stay at Perry was wise.

On cross-examination, Haveman testified that he did not understand certain statements in River’s bid. These statements included “previously quoted Cost Plus Rates.” (Plaintiff’s Exh. 20e). William Weidner, president of River Construction, explained that clarifications were subsequently provided to Haveman. River often left terms open to initiate negotiations. Additionally, some matters such as cargo cleaning could not be quantified until damage was examined thoroughly and defined.

On March 11, the River bid was accepted. (Plaintiffs Exh. 20j). Bidders were informed that the River bid was chosen because of the 24-day repair-time estimate and a concern about losing a berth at Perry Street. Perry Street had an office for the HISPAMAR at the wharf, security, and employees.

Bidders were also informed that insurance was a concern. A $25,000 insurance deductible would apply if, during the movement to another wharf, there was an accident. On cross-examination, Haveman admitted that no inquiry was made about the premium for insurance and that another berth rate would actually be approximately $200, not $1,100 as Haveman had estimated. (Plaintiffs Exh. 20j).

Haveman indicated that throughout his career, he witnessed numerous incidents of bids being sent within the same day of an accident. James Matthew, who was certified as an expert in marine survey by Rondel, considered the bidding time to be excessive. Other testimony revealed that the six-day lag between bid receipt and acceptance occurred because the owners took the bids under advisement.

All of River’s repairs subsequent to the preliminary survey were charged separately.

Haveman testified that an owner has the prerogative, based on all considerations, to pick a reasonable bid, not necessarily the lowest bid. The defendant’s witness, Matthew, acknowledged that in his career, he endorsed bids that were not the lowest.

B. Damage During the Repair Process

Weather was a factor in the repair process. River conducted repairs outside. Rain fell hard enough to stop work on approximately 24 to 28 days during the period the vessel was under repair. From March 13, 1991 to May 13, 1991, 22.14 inches of rain fell. The normal rainfall for that period is 9.64 inches.

When it rained excessively, welding had to be suspended outside, and work was delayed. While conflicting testimony was offered, the Court finds that welding in the rain is not safe.

On April 14, a rain storm brought high winds and thunderstorms to the New Orleans area. A meteorologist for River Construction testified that thunderstorms nearly always create wind gusts that are extremely non-uniform. On the 14th, winds in the Perry Street area could have been as high as 50 nautical miles per horn*. The protective tarps that covered the hole in the HISPA-MAR’s side blew off in the storm, exposing cargo and equipment. The tear in the HIS-PAMAR had been widened by River to effectuate repairs.

*282

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Lakes Business Trust v. M/T Orange Sun
855 F. Supp. 2d 131 (S.D. New York, 2012)
Crowley American Transport, Inc. v. Double Eagle Marine, Inc.
208 F. Supp. 2d 1250 (S.D. Alabama, 2002)
Tidewater Marine, Inc. v. Sanco International, Inc.
113 F. Supp. 2d 987 (E.D. Louisiana, 2000)
National Shipping Co. of Saudi Arabia v. United States
95 F. Supp. 2d 482 (E.D. Virginia, 2000)
Marine Office of America Corp. v. M/v Vulcan
101 F.3d 698 (Fifth Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
891 F. Supp. 278, 1995 U.S. Dist. LEXIS 8840, 1995 WL 375905, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-office-of-america-corp-v-mv-vulcan-laed-1995.