Mar-Paul Co. v. Jim Thorpe Area Sch. Dist.

25 Pa. D. & C.5th 206
CourtPennsylvania Court of Common Pleas, Carbon County
DecidedNovember 17, 2011
DocketNo. 04-2595
StatusPublished

This text of 25 Pa. D. & C.5th 206 (Mar-Paul Co. v. Jim Thorpe Area Sch. Dist.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Carbon County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mar-Paul Co. v. Jim Thorpe Area Sch. Dist., 25 Pa. D. & C.5th 206 (Pa. Super. Ct. 2011).

Opinion

NANOVIC, P.J.,

Herein, additional defendant, Hayes Large Architects, LLP (“Hayes”), moves for summary judgment on the claims made in the joinder complaint filed against it by the Jim Thorpe Area School District (“District”), all of which have been assigned to Popple Construction, Inc. (“Popple”). [208]*208For the reasons which follow, we deny this motion to the extent it requests summary judgment in full.

PROCEDURAL AND FACTUAL BACKGROUND

In 2002, the district began constructing an elementary school in Kidder Township, Carbon County, Pennsylvania, for kindergarten through eighth grade. Mar-Paul Company, Inc. (“Mar-Paul”) was the general contractor for the project; Popple was Mar-Paul’s subcontractor for the project site work. Moisture-laden soil caused construction delays, which resulted in both Mar-Paul and Popple claiming they were owed additional payments from the district beyond the base contract rate.

On August 6, 2004, Mar-Paul filed suit against the district and Popple. Mar-Paul’s complaint included claims for monies due it directly, as well as pass through claims on behalf of Popple.

The district joined Hayes, the district’s architect on the project, as an additional defendant against which it sought indemnification and/or contribution. By agreement dated February 26, 1996, the district contracted for Hayes’ architectural services for the project. The district also claimed direct liability for any amounts Mar-Paul recovered (for itself and on behalf of Popple) against it because of Hayes’ failure to comply with Hayes’ contractual obligations to the district. The district further sought recovery against Hayes for costs to correct defective work related to the construction of a shingled roof over the media center at the project, in the event this work was necessitated by design defects attributable to Hayes.

[209]*209Hayes, in turn, joined Pathline, Inc. (“Pathline”), the district’s clerk-of-the-works for the project, as an additional defendant. A separate agreement entered in 1999 between the district and Pathline provides for Pathline to furnish these services. In its joinder complaint, Hayes likewise sought indemnification and/or contribution from Pathline for any monies Hayes may be required to pay the district. Additionally, Hayes claimed Pathline was negligent in the information it supplied regarding the suitability of soil conditions at the project site, which was intended to be relied upon and was in fact relied upon by Hayes to its detriment.

In late 2009, Mar-Paul, the district and Popple reduced to writing the terms of settlement of their respective claims against one another. All parties executed a mutual release, assignment of claims and settlement agreement (“agreement”) reflecting the agreed upon terms. Pursuantto this agreement, the district is to pay certain monies to Mar-Paul (i.e., $285,422.00) andPopple (i.e., $275,000.00), and to assign all of its right, title and interest in those claims asserted in its joinder complaint against Hayes to Popple. The agreement further provides that the first $25,000.00 of any monies recovered by Popple are to be retained by Popple, with the balance to be paid 65 percent to Popple and 35 percent to the district, less Popple’s pro rata share of attorney’s fees and costs in pursuing these claims. The agreement also recites that Popple’s claims against the district total $358,698.80.

Before us now is Hayes’ motion for summary judgment in which it asserts first that the district’s assignment to [210]*210Popple of its claims against Hayes violates public policy and is unenforceable in that it constitutes champerty, and second, that there exist no valid claims for contribution or indemnity that the district could assign to Popple.

DISCUSSION

Champerty

Champerty is:

[a] bargain by a stranger with a party to a suit, by which such third person undertakes to cany on the litigation at his own cost and risk, in consideration of receiving, if successful, a part of the proceeds or subject sought to be recovered.

Black’s Law Dictionary 209 (5th ed. 1979). At its essence champerty seeks to bar a party from speculating and profiting in litigation in which he has no legitimate interest. Fleetwood Area School District v. Berks County Board of Assessment Appeals, 821 A.2d 1268, 1274 (Pa.Cmwlth. 2003). To invalidate an assignee’s litigation of an assigned claim, three elements must exist:

1) The assignee must have no legitimate interest in the suit;
2) He must expend his own money in prosecuting the suit; and
3) He must be entitled by the bargain to share in the proceeds of the suit.

Belfonte v. Miller, 243 A.2d 150, 152 (Pa. Super. 1968). [211]*211“A champertous agreement is one in which a person having otherwise no interest in the subject matter of an action undertakes to carry on the suit at his own expense in consideration of receiving a share of what is recovered.” Id. (quoting Richette v. Pennsylvania R.R., 187 A.2d 910 (Pa. 1963)).

In this case, the second and third elements of champerty have been met because Popple, pursuant to the agreement, will expend its own monies in prosecuting the district’s claims against Hayes and it is entitled to share in the proceeds of any recovery. In dispute is the first element: whether Popple has any legitimate interest in the instant suit independent of the agreement. For the following reasons, we find Popple’s interest to be legitimate: (1) Popple was involved in this litigation from the outset, before any agreement was reached, and does not come to this litigation as an outsider; (2) the subject matter of the agreement is the very litigation in which Popple was an original defendant; (3) the amount of damages claimed by Popple in the underlying litigation exceeds the amount paid to it by the district; and (4) the public policy of this Commonwealth favors settlement and allows for the assignment of non-personal injury claims. Popple is no stranger to the litigation and, as such, is not barred by champerty from pursuing the claims against Hayes which have been assigned to it by the District.

Viability of the District’s Claims Assigned to Popple

To the extent that the district’s joinder complaint against Hayes asserts a claim for contribution, Hayes is correct [212]*212in stating that such a claim cannot exist. The underlying claims brought by Mar-Paul and Popple against the district are in contract. At the most basic level, Mar-Paul and Popple claim that the district’s actions were a breach of the parties’ contract and caused damages. There are no tort claims. Accordingly, since the principle of contribution refers to the allocation of the payment of damages by and between two or more joint tortfeasors, and there being no claim that the district was a tortfeasor, its request for contribution against Hayes must fail. See 42 Pa.C.S.A. § 8324(a) (providing for contribution only between joint tortfeasors); Carson v. Driscoll, 2006 WL 2009047 *6 (CCP Phil.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bilt-Rite Contractors, Inc. v. Architectural Studio
866 A.2d 270 (Supreme Court of Pennsylvania, 2005)
Vattimo v. Lower Bucks Hospital, Inc.
465 A.2d 1231 (Supreme Court of Pennsylvania, 1983)
Szymanski-Gallagher v. Chestnut Realty Co.
597 A.2d 1225 (Superior Court of Pennsylvania, 1991)
Davis v. Miller
123 A.2d 422 (Supreme Court of Pennsylvania, 1956)
Fleetwood Area School District v. Berks County Board of Assessment Appeals
821 A.2d 1268 (Commonwealth Court of Pennsylvania, 2003)
Kemper National P & C Companies v. Smith
615 A.2d 372 (Superior Court of Pennsylvania, 1992)
Belfonte v. Miller
243 A.2d 150 (Superior Court of Pennsylvania, 1968)
City of Wilkes-Barre v. KAMINSKI BROTHERS
804 A.2d 89 (Commonwealth Court of Pennsylvania, 2002)
Buttermore v. Aliquippa Hospital
561 A.2d 733 (Supreme Court of Pennsylvania, 1989)
National Liberty Life Insurance v. Kling Partnership
504 A.2d 1273 (Supreme Court of Pennsylvania, 1986)
Potts v. Dow Chemical Co.
415 A.2d 1220 (Superior Court of Pennsylvania, 1979)
Mirizio v. Joseph
4 A.3d 1073 (Superior Court of Pennsylvania, 2010)
Richette v. Pennsylvania Railroad
187 A.2d 910 (Supreme Court of Pennsylvania, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
25 Pa. D. & C.5th 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mar-paul-co-v-jim-thorpe-area-sch-dist-pactcomplcarbon-2011.