MAPLE SHADE EQUITIES, LLC VS. NEW JERSEY DEPARTMENT OF TRANSPORTATION (NEW JERSEY DEPARTMENT OF TRANSPORTATION)

New Jersey Superior Court Appellate Division·Decided November 17, 2021·No. A-3709-19·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3709-19

MAPLE SHADE EQUITIES, LLC, Appellant,

v.

NEW JERSEY DEPARTMENT OF TRANSPORTATION,

Respondent.

Argued October 18, 2021 – Decided November 17, 2021 Before Judges Messano, Accurso and Rose.

On appeal from the New Jersey Department of Transportation.

Keith A. Davis argued the cause for appellant (Nehmad Perillo Davis & Goldstein, PC, attorneys; Keith A.

Davis and Michael J. Lario, Jr., on the briefs).

Brian Ashnault, Deputy Attorney General, argued the cause for respondent (Andrew J. Bruck, Acting Attorney General, attorney; Melissa H. Raksa, Assistant Attorney General, of counsel; David M.

Kahler, Deputy Attorney General, on the brief).

PER CURIAM Plaintiff Maple Shade Equities, LLC (Maple Shade or developer), challenges a final agency decision of the New Jersey Department of Transportation (DOT or agency), deeming untimely Maple Shade's appeal of certain major access permit conditions, and finding no grounds for relaxation of the time requirements under section 4.32(b)(1) of the State Highway Access Management Code, N.J.A.C. 16:47-1.1 to 16:47-14.1 (Access Code). 1 The Director of the DOT's Division of Right of Way and Access Management issued the agency's final decision after affording Maple Shade an informal hearing on the merits of its application. We affirm.

We summarize the relevant facts and procedural history from the record evidence. Maple Shade purchased commercial property located at the intersection of Route 38 and Lenola Road in Maple Shade Township. By all accounts, the intersection was marked by high volume traffic during commuter hours; the DOT rated the intersection as "F," for the lowest level of service.

At the time of the purchase, the property consisted of a car wash, and a gas station with a convenience store. Four existing driveways were located

1 On July 16, 2018, after Maple Shade submitted its application, the Access Code was revised and renumbered. We cite the Access Code provisions in effect at the time of Maple Shade's April 10, 2016 application.

A-3709-19

along the sides of the property: one provided open access along Lenola Road; three fronted Route 38. Of the Route 38 driveways: the eastern-most permitted ingress only; the center allowed open access; and the western-most permitted egress only by right turns onto the highway.

Maple Shade planned to redevelop the property by constructing a drive -

through bank and drive-through coffee and donut shop. Pertinent to this appeal, on August 10, 2016, Maple Shade submitted to the DOT a major access permit application, seeking to revise the property's direct access to Route 38. The developer proposed closing the eastern and center driveways along Route 38 and expanding the western driveway to allow open access.

In February 2017, after consulting with the agency's various experts, the DOT notified Maple Shade of several concerns. Citing the existing volume of traffic at the intersection during morning and evening peak hours, the DOT "strongly recommend[ed]" that Maple Shade add an auxiliary "100[-]f[oo]t right turn lane" to address the agency's concerns. The developer countered that its existing third lane was an auxiliary lane, which was designed to serve the property's gas station and adjacent shopping center. Accordingly, Maple Shade argued an additional auxiliary lane increased the danger to drivers by requiring merger across two lanes.

A-3709-19

In June 2017, the DOT revised its position, "strongly recommend[ing] that [Maple Shade] provide at least a [ten-foot-]wide shoulder along the Route 38 site frontage" instead of adding a fourth lane. The DOT also noted it was in the process of proposing a plan for the intersection that would reduce congestion. Accordingly, a widened shoulder would reduce delays caused by the Maple Shade development, while serving as an effective interim mitigation device until the DOT's future Route 38 project was completed.

Following a series of exchanges between the parties, in December 2017, Maple Shade submitted revised plans that included the ten-foot-wide shoulder. According to the plans, a six-foot portion of the shoulder was located on property owned by the DOT, and Maple Shade would convey the remaining four-foot, 785 square-foot strip to the agency. On March 19, 2018, the DOT issued the permit, which included the ten-foot-wide shoulder among fifty-five conditions. Maple Shade completed the project in accordance with the agency's conditions.

After completing the project, and nearly four months beyond the Access Code's thirty-day deadline for appeals, Maple Shade filed its appeal with the DOT on August 1, 2018. Seeking compensation for the costs of construction, and "fair market value of the land it was required to dedicate," the developer

A-3709-19

claimed the agency exceeded its powers by requiring conditions that were not mandated by the Access Code. Initially denying Maple Shade's request as untimely, the agency afforded Maple Shade an informal hearing to address the developer's "assertions of unsafe conditions on the site," and "improper acts" allegedly committed by DOT staff.

On the March 6, 2019 return date, the parties requested an adjournment to continue negotiations. After failing to reach an agreement, the DOT moved to dismiss Maple Shade's appeal as untimely. The Director conducted a plenary hearing over two days in November 2019 and February 2020. Joshua Idowu, the DOT's project manager for Maple Shade's application, testified on behalf of the agency. Maple Shade presented the testimony of three witnesses: Clifton Quay, a licensed professional engineer, who served as a civil consulting engineer on the project; Adam Catherine, a professional traffic operations engineer; and Kenneth Lowther, an equity partner of Maple Shade.

In essence, Idowu testified about the agency's safety concerns regarding the projected increase in traffic flow anticipated by Maple Shade's proposed development plan, and the need for an expanded shoulder to address those concerns. In view of the DOT's anticipated future project at the location, the agency granted a waiver under the Code, without which Maple Shade's plan

A-3709-19

would have been rejected. See N.J.A.C. 16:47-4.24(a)(1)(ii) (prohibiting deterioration in the level of service at the proposed site plan); see also N.J.S.A. 7-90(c), (e), and (g).

Conversely, Catherine stated he opposed widening the shoulder, which he opined would cause confusion for drivers accessing the Maple Shade property and the adjacent restaurant. Notably, however, Catherine acknowledged that the DOT's request was "reasonable."

Quay testified he had argued against expanding the shoulder but believed the DOT would not approve the permit unless Maple Shade included the shoulder expansion in its design plans. Quay was concerned Maple Shade would be unable to meet contractual deadlines with its lessees if the developer continued to oppose the shoulder expansion.

Lowther confirmed the permit process delayed the commencement of those leases. He acknowledged Maple Shade intended to file an appeal soon after executing the permit. According to Lowther, the developer claimed $174,500 for costs of construction, loss of income, and the value of the property dedicated for the expanded shoulder.

Following summations, the Director reserved decision. On April 23, 2020, the Director issued a cogent written decision, again concluding Maple

A-3709-19

Shade's appeal was untimely. Because the conditions imposed were "proper exercises of the state agency's police power," the Director found no grounds for relaxation of the then-existing time requirements. According to the Director:

Free access — add to your briefcase to read the full text and ask questions with AI

MAPLE SHADE EQUITIES, LLC VS. NEW JERSEY DEPARTMENT OF TRANSPORTATION (NEW JERSEY DEPARTMENT OF TRANSPORTATION), (N.J. Ct. App. 2021).

MAPLE SHADE EQUITIES, LLC VS. NEW JERSEY DEPARTMENT OF TRANSPORTATION (NEW JERSEY DEPARTMENT OF TRANSPORTATION) (MAPLE SHADE EQUITIES, LLC VS. NEW JERSEY DEPARTMENT OF TRANSPORTATION (NEW JERSEY DEPARTMENT OF TRANSPORTATION)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON
944 A.2d 1 (Supreme Court of New Jersey, 2008)
In Re I/M/O Route 206 New Amwell Rd.
731 A.2d 56 (New Jersey Superior Court App Division, 1999)
Mazza v. Board of Trustees
667 A.2d 1052 (Supreme Court of New Jersey, 1995)
In re Stallworth
26 A.3d 1059 (Supreme Court of New Jersey, 2011)