Manuel Amador v. A/s J. Ludwig Mowinckels Rederi, the Ronda

224 F.2d 437
CourtCourt of Appeals for the Second Circuit
DecidedJuly 1, 1955
Docket313, Docket 23323
StatusPublished
Cited by17 cases

This text of 224 F.2d 437 (Manuel Amador v. A/s J. Ludwig Mowinckels Rederi, the Ronda) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manuel Amador v. A/s J. Ludwig Mowinckels Rederi, the Ronda, 224 F.2d 437 (2d Cir. 1955).

Opinion

HAND, Circuit Judge.

This is an appeal from a decree in the admiralty of Judge Clancy, dismissing a libel in rem and in personam against a motor vessel and its owner, to recover for personal injuries suffered by a longshoreman during the discharge of the vessel in New York. The owner implead-ed the stevedoring company which had employed the libellant, basing its claim upon an indemnity contract; but since the libellant’s libel was dismissed, it was unnecessary for Judge Clancy to pass upon that claim. The libellant was a member of a stevedore gang working in a lower hold of the vessel, when a heavy coil of wire was dislodged through the carelessness of other members of the gang and fell upon him, causing him severe injuries. The libel is based upon the theory that the cargo was so stowed as to make the ship unseaworthy, and that she and her owner were liable regardless of the negligence of the steve-doring gang.

The first five findings, which we quote, eliminating one erroneous statement, state in detail what happened, and they are not clearly erroneous.

“1. In March, 1951, the S. S. Ronda, owned by respondent A/S J. Ludwig Mowinckels Rederi, took aboard at Antwerp in her No. 4 hold a cargo of steel strips. The hold was fifty-six feet long and wide, the hatch opening 32.6 feet long and twenty feet wide and the strips about twenty feet long so that approximately half of their length stowed lay immediately under the hatch coaming. The steel was stowed to a height in excess of eight feet so that it was something over the top on both sides of the 8 foot high shaft tunnel. The hold itself was 22 *439 feet deep and above it, the tween-deck was 12 feet.
“2. The vessel proceeded to Havre and there put aboard in the No. 4 hold something in excess of two thousand coils of steel wire, each one of which weighed 159 pounds, the width of the wire being 6 inches and of the coil about 3 feet. They were laid on dunnage at the bottom of the hold and married, the first tier resting at an angle on a coil laid flat at the side of the hold with the tier above laid at an angle in the other direction so that each tier helped to secure the members of the tier beneath and that above. This process resulted in what was called a ‘married’ stow. Above each three tiers a layer of dunnage was laid thwartships so that there were three in all, the number of tiers being altogether about twelve. Double dunnage was laid in the wings. When the stow was completed the height of the coils was two or three feet higher than the steel and general cargo was laid on both. The top few feet of the coils was shored by vertical dunnage boards braced against the steel. General cargo, baled and bagged, was in the hold forward of the coils. It was known when the vessel was at Havre that the steel was to be delivered at New York and the wire coils afterwards at Baltimore. While the Ronda encountered generally fair weather on her voyage the sea was sometimes rough and the vessel then pitched and rolled.
“3. The Ronda arrived at New York on the 19th of March, 1951 and the next morning a gang of stevedores, employed by the Commercial Stevedoring Company, Inc., the impleaded respondent, went aboard and proceeded to discharge the cargo in the tween-deck section of No. 4 hold as well as at least some of the general cargo in the lower hold. When this was completed, the discharge of the strip steel cargo was started and proceeded during the rest of that day. The steel strips were taken out by eight men divided into two gangs of four, one of which operated on the port side and the other on the starboard. A number of the strips, approximating two and one-half tons, were taken out at a time in a sling. The sling was sent aloft on the ship’s crane by the gang working on one side while the gang on the other side was preparing the next draft for discharge. The process was to lift the end of the draft under the hatch opening to a point where it was higher than the coil cargo, whereupon the rope attached to the rear end of the draft would be tightened and the whole draft swung to a position under the hatch opening, lifted and put upon the dock. No guide line or backstop was used by either gang.
“4. It is found as a fact that from the beginning of the discharge of the steel this method of the stevedores’ operation caused frequent collisions between the ends of some of the drafts and the coiled wire. The assistant operating manager of the ship’s agent who also was general superintendent of Commercial Ste-vedoring Company authorized the boss of the stevedoring gangs working in the No. 4 hold to remove so much of the coil cargo as would at any time appear necessary to facilitate the discharge. * * * None of it was removed by the stevedores who persisted in maintaining the practice we have stated.
“5. In the early afternoon of March 21, libellant, who was a member of the stevedore gang operating in No. 4 hold, while engaged in passing a loop of rope under what was intended to be a draft of the steel strips and while his back was turned to the coil cargo, was struck by one or several of some dozen coils which were dislodged and fell from the top two tiers of the stow. He was severely injured. The dislodgment of *440 the coils was caused by successive collisions between the ends of the drafts of steel strips as the drafts were lifted and immediately by such a collision effected by the port gang whose draft was then being carelessly removed while libellant was preparing the draft to follow.”

Bentsen was the assistant general superintendent of the ship’s- agent in New York, and he did not examine the stow with much care. It does not appear whether what he told the gang bosses was before they had begun to discharge the steel strips in the way they did; but, although he did not warn them before he left, Lunde, the ship’s second mate, saw the drafts hitting the coils and warned the gang bosses to be careful. Moreover, later, after he came back and saw the same thing happening, he again warned them and they agreed to be careful. The judge held that the stowage was proper; that there was no credible evidence that the coils had been disturbed except by being upset, when the drafts struck them. He held that “the stevedores’ work was grossly negligent in the failure to use a stay or guide line during the ascent of the draft at least to a stable position suspended in the hatch opening. They were negligent as well in their general conduct in so conducting the discharge operation as to cause repeated collisions between the drafts of steel strips and the coils. So gross was their negligence that not even the repeated collisions served as warnings to take measures to avoid dislodging the stow of coils. The dun-nage as it was laid served its purpose. The stow was solid and remained solid until discharged and the manner of laying the dunnage had nothing whatever to do with plaintiff’s injury.”

We do not understand that the appellee denies that a ship is responsible for proper stowage, as well as for fitness in hull and gear; at any rate that is certainly the law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe v. Zucker
N.D. New York, 2025
Ramirez v. Toko Kaiun K.K.
385 F. Supp. 644 (N.D. California, 1974)
Lucas v. " BRINKNES" SCHIFFAHRTS GES.
379 F. Supp. 759 (E.D. Pennsylvania, 1974)
Guzman v. Mowbray
288 F. Supp. 948 (S.D. New York, 1968)
Giaraffa v. Moore-McCormack Lines, Inc.
270 F. Supp. 342 (S.D. New York, 1967)
Crispin Company v. M/V Korea
251 F. Supp. 878 (S.D. Texas, 1965)
Ingravallo v. Pool Shipping Co.
247 F. Supp. 394 (E.D. New York, 1965)
Bell v. Nihonkai Kisen, K. K., Tokyo
204 F. Supp. 230 (D. Oregon, 1962)
Lowe v. The Vessel Madrid
210 F. Supp. 826 (S.D. Florida, 1962)
Doherty v. Federal Stevedoring Co.
198 F. Supp. 191 (S.D. New York, 1961)
Cavelleri v. Isthmian Lines, Inc.
190 F. Supp. 801 (S.D. New York, 1961)
Carabellese v. Naviera Aznar, S.A.
285 F.2d 355 (Second Circuit, 1960)
Reddick v. Mcallister Lighterage Line, Inc.
258 F.2d 297 (Second Circuit, 1958)
Amador v. The Ronda
146 F. Supp. 617 (S.D. New York, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
224 F.2d 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manuel-amador-v-as-j-ludwig-mowinckels-rederi-the-ronda-ca2-1955.