Malley v. Sierra Manufacturing Co.

258 P.2d 522, 118 Cal. App. 2d 643
CourtCalifornia Court of Appeal
DecidedJune 23, 1953
DocketCiv. No. 19159
StatusPublished
Cited by2 cases

This text of 258 P.2d 522 (Malley v. Sierra Manufacturing Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Malley v. Sierra Manufacturing Co., 258 P.2d 522, 118 Cal. App. 2d 643 (Cal. Ct. App. 1953).

Opinion

WOOD (Parker), J.

Action for damages for alleged breach of contract. Defendant Sierra Manufacturing Company, a limited partnership, answered the first amended complaint and also filed a cross-complaint. The judgment was that plaintiff take nothing on said complaint, and that the cross-complainant recover from cross-defendant on the cross-complaint the sum of $3,000. Plaintiff appeals from the judgment.

In 1945, plaintiff was engaged in the business of manufacturing and selling an electric broiler, referred to at the [644]*644trial as the Mall ey Kitchen Master. On November 13, 1945, plaintiff and Sierra Manufacturing Company, hereinafter referred to as defendant, entered into a written agreement which provided that defendant would perform certain work consisting of metal spinning, polishing, punching holes and riveting specified parts (used in the manufacture of the broiler), which parts were to be spun from 12, 16 and 17 inch aluminum blanks (“circles” of aluminum sheet) of specified weights. The agreement provided further that defendant would do the work for a flat price of $1.35 a set; plaintiff would “supply all the material used to manufacture” the said items, and would supply chucks, three foot presses and dies for punching holes; plaintiff would “give” to the Sierra Manufacturing Company, and defendant would complete, a minimum of work amounting to $15,000 annually, and defendant agreed to complete such contracts as given to it in excess of $15,000 and up to $50,000 per annum. It was provided further therein that neither party would be liable in damages occasioned by a shortage of materials, labor difficulties, or causes beyond the reasonable control of the respective parties. A copy of said agreement was. made a part of the amended complaint.

It was alleged in the amended complaint that, as required by said contract, plaintiff supplied to defendants the chucks, three foot presses and dies, all of which were in the possession of defendants prior to signing the agreement and ever since have been in their possession. It was alleged in paragraph IX of said complaint that, in furtherance of said contract, on January 10, 1946, plaintiff in writing, ordered defendants to make 15,000 sets at $1.35 per set, at the rate of, ‘ ‘ as stated in said written order, ‘up to 1,000 sets weekly’ ”; said order was accepted by defendants; when said order was given, it was agreed and understood that defendants would make up sets so that they would be ready for pick-up by plaintiff at the rate of 1,000 sets a week commencing January 17, 1946, and that defendants were to complete said sets so that on or before April 25, 1946, all of said completed sets would have been picked up by plaintiff. It was alleged in paragraph XI of said complaint that up to and including April 30, 1946, defendants failed to perform the contract and the January 10, 1946 order, by failing to complete the 15,000 sets for pick-up by plaintiff in the manner described in paragraph IX of said complaint, and defendants completed for delivery only various parts of sets (setting forth therein the parts which [645]*645were completed). It was alleged further in said complaint, in part, as follows: at the time said order was given, defendants were in possession of approximately 10,000 pounds of aluminum sheets theretofore supplied by plaintiff; in addition thereto plaintiff caused to be delivered to defendants materials far in excess of the amount required, and plaintiff continuously kept defendants supplied with all materials, and performed everything required to be done by plaintiff under the said contract to enable defendants to compete and have said sets ready for pick-up by plaintiff in the manner described in paragraph IX of said complaint; in April, 1946, plaintiff and defendants conferred about the failure of defendants to perforin the contract, and at that time plaintiff told defendants he was about to go on a trip to promote the sale of housewares which he manufactured, and he stated it would be pointless to make the trip unless defendants assured him of delivery of “at least 5,000 sets during the months of May and June, 1946,” and thereafter 500 sets a week, all within the limitations of the original contract; defendants assured plaintiff they would do so, whereupon plaintiff ordered defendants to make 5,000 sets for May and June, 1946, and thereafter 500 sets a week; in furtherance of said further order, plaintiff caused to be delivered to defendants materials far in excess of that required, and plaintiff performed everything required to be done by him under the contract to enable defendants to fill the order given in April, 1946; upon the assurance of defendants that they would make up the order given in April, 1946, plaintiff went on the trip, expended approximately $1,000 as expenses thereof, and obtained orders for the broilers amounting to approximately $70,000, to be shipped to plaintiff’s customers during July, August, and September, 1946; from May 1, 1946 to and including December, 1946, defendants completed various parts of sets, specified therein (the quantities of parts allegedly completed during each month were specifically set forth—and were less than the quantities required by the purported orders); by reason of the failure of defendants to perform everything required of them under the contract plaintiff lost large profits and many customers, and the good will of his business suffered great damage; plaintiff has been damaged in the sum of $85,000.

As a second cause of action it was alleged, in part, that in September, 1946, plaintiff and defendants entered into [646]*646an oral agreement which provided that defendants would manufacture for plaintiff 6,000 broilers for $1.86 per broiler; said broilers would be available for delivery to plaintiff not later than December 31, 1946; as part of said oral contract plaintiff was to supply defendants with necessary materials and parts, and defendants were to have the use of certain chucks, foot presses and dies, which were and ever since have been in the possession of defendants; plaintiff caused to be delivered to defendants materials and parts far in excess of the amount required and plaintiff performed everything required to be done by him under said oral contract; at the time said contract was entered into, defendants knew plaintiff would rely upon defendants for the supply of all broilers as per said contract, and that plaintiff would not manufacture or buy any other broilers in his business; by June, 1947, defendants had made only 3,626 broilers and have failed and refused to make up the balance of the broilers as required by the contract; by reason of such failure of defendants to perform the contract, plaintiff suffered damages in the sum of $12,500.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Harvey
330 P.2d 478 (California Court of Appeal, 1958)
Malley v. Sierra Manufacturing Co.
258 P.2d 526 (California Court of Appeal, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
258 P.2d 522, 118 Cal. App. 2d 643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/malley-v-sierra-manufacturing-co-calctapp-1953.