MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY

CourtDistrict Court, D. Maine
DecidedJune 19, 2020
Docket1:17-cv-00446
StatusUnknown

This text of MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY (MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY, (D. Me. 2020).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MAINE MAINE WOODS PELLET CO., LLC, ) ) Plaintiff ) ) v. ) 1:17-cv-00446-JCN ) WESTERN WORLD INSURANCE ) COMPANY, ) ) Defendant ) ORDER ON MOTION FOR RECONSIDERATION Plaintiff alleges Defendant breached an insurance contract by applying three separate deductibles, rather than a single deductible, to an insurance claim submitted as the result of mechanical difficulties with Plaintiff’s heat and power plant. On the parties’ summary judgment motions, the Court granted partial summary judgment in favor of Defendant, concluding the record established that at least two deductibles applied to Plaintiff’s losses, but a genuine factual dispute remained as to whether a third deductible applied. (Summary Judgment Order, ECF No. 38.) Plaintiff moves for reconsideration of the Court’s summary judgment order. (Motion, ECF No. 49.) Following a review of the record and after consideration of the parties’ arguments, the Court denies Plaintiff’s motion for reconsideration. FACTUAL AND PROCEDURAL BACKGROUND1 Plaintiff owns and operates a wood pellet production facility that includes a heat and power plant. The cogeneration plant is comprised of traditional components such as a

boiler, heat exchanger, turbine and condenser, but the system uses cyclopentane as the working fluid rather than water. The condenser is a shell and tube heat exchanger with cooling water flowing through 2,410 U-shaped tubes and vaporized cyclopentane flowing through the shell and around the tubes. Beginning on December 20, 2016, the cogeneration plant experienced reduced

efficiency. On January 8, 2017, Plaintiff identified water in the cyclopentane side of the system and instituted brief periodic shutdowns to remove relatively small quantities of water. On January 17, 2017, larger quantities of water entered the system and Plaintiff shut down the cogeneration plant. Plaintiff performed a bubble test, which revealed leaks from two fractured tubes. The two tubes were plugged, and no further leaks were detected. The

cogeneration plant restarted on January 30, and between January 30 and March 9, Plaintiff’s system was operational with the exception of brief daily or weekly shutdowns to remove small quantities of water. On March 9, 2017, Plaintiff again shut down the cogeneration plant after discovering large quantities of water in the cyclopentane side of the system. A bubble test and a borescope revealed that one tube was sheared off. The tube was plugged, and no

further leaks were detected. The cogeneration plant began operating on March 12, and

1 The Court’s summary judgment order contains a more complete summation of the record. (See ECF No. 38.) between March 12 and March 20, Plaintiff’s system was operational with the exception of brief daily shutdowns to remove small quantities of water. On March 20, 2017, Plaintiff again shut down the cogeneration plant for scheduled

cleaning and passivation procedures and for inspection of the cyclopentane side of the condenser to assess the cause of the difficulties. Unlike during the bubble tests, Plaintiff drained the cyclopentane side while the water side remained pressurized. Plaintiff identified a discolored tube, which leaked when it was moved. The damaged tube was plugged, and Plaintiff installed modifications designed by the manufacturer to reduce tube

vibration. The cogeneration plant restarted on March 25, 2017. After the installation of the modifications, the brief periodic shutdowns to remove water have become unnecessary, and a very small amount of water typically is removed once per year. Defendant determined that three separate losses had occurred because the tubes broke at three separate times and the plant operated between the events. Defendant paid

Plaintiff $159,711.53 after applying a $100,000 deductible for the loss involving the major shutdown that began on January 17. Defendant paid Plaintiff $67,413.62 after applying a $100,000 deductible for the loss involving the major shutdown that began on March 9. Although Defendant concluded that a covered loss occurred in the amount of $93,877.70 for the shutdown that began on March 20, Defendant did not pay Plaintiff for that loss

because the damage did not exceed the $100,000 deductible. Had Defendant applied only one deductible for the whole period, it would have paid Plaintiff an additional $193,877.70. Plaintiff filed a complaint in state court, and Defendant subsequently removed the case to federal court based on diversity of citizenship jurisdiction. (Notice of Removal, ECF No. 1.) The parties filed cross motions for summary judgment, a joint stipulated statement of material facts, and separate statements of material facts. (ECF Nos. 21, 23, 24, 25, 27, 29.) After oral argument, the Court denied Plaintiff’s motion and granted in

part and denied in part Defendant’s motion. (Summary Judgment Order, ECF No. 38.) The Court concluded that the record established that at least two deductibles applied, but a factual dispute remained as to whether two or three deductibles applied. (Id.) LEGAL STANDARD The granting of a motion for reconsideration of a final judgment is “an extraordinary

remedy which should be used sparingly.” Palmer v. Champion Mortg., 465 F.3d 24, 30 (1st Cir. 2006). To prevail on a motion for reconsideration of a final order, a party must demonstrate (1) the existence of new evidence not previously available, (2) an intervening change in controlling law, or (3) the need to correct a clear error of law or to prevent manifest injustice. Int’l Ass’n of Machinists & Aerospace Workers v. Verso Corp., 121 F.

Supp. 3d 201, 217 (D. Me. 2015). Nonfinal orders remain open pending final judgment, so the Court has wide discretion to revisit prior interlocutory rulings. Geffon v. Micrion Corp., 249 F.3d 29, 38 (1st Cir. 2001); Mumme v. U.S. Dep’t of Labor, 150 F. Supp. 2d 162, 165 (D. Me. 2001). A motion to reconsider is proper if the Court “misapprehended some material fact or point of law,” but is “not a promising vehicle” for “rearguing theories previously

advanced and rejected,” Palmer, 465 F.3d at 30, or for “advance[ing] arguments that could and should have been presented to the district court prior to its original ruling.” Villanueva v. United States, 662 F.3d 124, 128 (1st Cir. 2011). DISCUSSION In this district, a motion to reconsider an interlocutory order “shall be filed within 14 days from the date of the order unless the party seeking a reconsideration shows cause

for not filing within that time.” Dist. Me. Loc. R. 7(f). “Cause for not filing within 14 days from the date of the order includes newly available material evidence and an intervening change in the governing legal standard.” Id. Given the date the Court issued the summary judgment decision (June 27, 2019), Defendant argues the motion, filed on January 10, 2020, is untimely.

Plaintiff raised the prospect of filing the motion during a telephonic conference much earlier, on July 23, 2019, but the motion would be untimely even if filed on that date. Because Plaintiff has not established newly available material evidence,2 an intervening change in the governing legal standard, or any other reason the motion could not have been filed within the fourteen-day period, Plaintiff’s motion could be denied as untimely filed.

The Court, however, may revisit or revive at any time an issue decided in an interlocutory order, including an issue decided at summary judgment. Latin Am. Music Co. Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geffon v. Micrion Corporation
249 F.3d 29 (First Circuit, 2001)
Palmer v. Champion Mortgage
465 F.3d 24 (First Circuit, 2006)
Villanueva v. United States
662 F.3d 124 (First Circuit, 2011)
Kraul v. MAINE BONDING & CASUALTY COMPANY
559 A.2d 338 (Supreme Judicial Court of Maine, 1989)
Mumme v. United States Department of Labor
150 F. Supp. 2d 162 (D. Maine, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maine-woods-pellet-co-llc-v-western-world-insurance-company-med-2020.