MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY

CourtDistrict Court, D. Maine
DecidedMarch 31, 2021
Docket1:17-cv-00446
StatusUnknown

This text of MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY (MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY, (D. Me. 2021).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MAINE MAINE WOODS PELLET CO., LLC, ) ) Plaintiff ) ) v. ) 1:17-cv-00446-JCN ) WESTERN WORLD INSURANCE ) COMPANY, ) ) Defendant ) DECISION AND JUDGMENT ON MOTIONS FOR JUDGMENT ON A STIPULATED RECORD Plaintiff alleges Defendant breached an insurance contract by applying three separate deductibles, rather than a single deductible, to an insurance claim submitted as the result of mechanical difficulties with Plaintiff’s heat and power plant. On the parties’ summary judgment motions, the Court granted partial summary judgment in favor of Defendant, concluding the record established that at least two deductibles applied to Plaintiff’s losses, but a genuine factual dispute remained as to whether a third deductible applied. (Summary Judgment Order, ECF No. 38.) The parties filed cross motions for judgment on a stipulated record. (Def.’s Motion, ECF No. 78; Pl.’s Motion, ECF No. 79.) The remaining issue is whether the third breakdown was caused by the second breakdown and therefore subject to a single deductible under the policy. Following a review of the record and after consideration of the parties’ arguments, the Court concludes that two deductibles apply to Plaintiff’s losses. The Court, therefore, grants Plaintiff’s motion for judgment and denies Defendant’s motion.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY1 A. The Mechanical Difficulties Plaintiff owns and operates a wood pellet production facility that includes a heat and power plant. The cogeneration plant is comprised of traditional components such as a boiler, heat exchanger, turbine and condenser, but the system uses cyclopentane as the working fluid rather than water. The condenser is a shell and tube heat exchanger with

cooling water flowing through 2,410 U-shaped tubes and vaporized cyclopentane flowing through the shell and around the tubes. Beginning on December 20, 2016, the cogeneration plant experienced reduced efficiency. On January 8, 2017, Plaintiff identified water in the cyclopentane side of the system and instituted brief periodic shutdowns to remove relatively small quantities of

water. On January 17, 2017, larger quantities of water entered the system and Plaintiff shut down the cogeneration plant. Plaintiff performed a bubble test, which revealed leaks from two fractured tubes (hereinafter “Tube 1” and “Tube 2”). The two tubes were plugged, and no further leaks were detected. The cogeneration plant restarted on January 30, and between January 30 and March 9, Plaintiff’s system was operational, except for brief daily

or weekly shutdowns to remove small quantities of water.

1 The Court’s summary judgment order contains additional details concerning the undisputed facts and the legal issues the Court has resolved. (Summary Judgment Order, ECF No. 38.) On March 9, 2017, Plaintiff again shut down the cogeneration plant after discovering large quantities of water in the cyclopentane side of the system. A bubble test and a borescope revealed that one tube was sheared off (hereinafter “Tube 3”). The tube

was plugged, and no further leaks were detected. The cogeneration plant began operating on March 12, and between March 12 and March 20, Plaintiff’s system was operational, except for brief daily shutdowns to remove small quantities of water. On March 20, 2017, Plaintiff again shut down the cogeneration plant for scheduled cleaning and passivation procedures and for inspection of the cyclopentane side of the

condenser to assess the cause of the difficulties. Unlike during the bubble tests, Plaintiff drained the cyclopentane side while the water side remained pressurized. Plaintiff identified a discolored tube, which leaked when it was moved (hereinafter “Tube 4”). The damaged tube was plugged, and Plaintiff installed modifications designed by the manufacturer to reduce tube vibration. The cogeneration plant restarted on March 25,

2017. After the installation of the modifications, the brief periodic shutdowns to remove water became unnecessary, and a very small amount of water typically is removed once per year. B. The Insurance Policy The commercial property insurance policy covers several risks but also contains exclusions for, among other things, design defects and mechanical breakdowns. Plaintiff,

however, also purchased optional coverage for equipment breakdowns. The additional coverage modified the exclusions in the base policy to provide for coverage if an excluded cause of loss results in an “accident,” defined as “a fortuitous event” that damages covered equipment. (Policy, ECF No. 21-1 at 83–85.) The “event must be” one of several listed risks; the only one of relevance here is a “mechanical breakdown.” Id. The equipment breakdown coverage also specified that for purposes of the number

of applicable deductibles, “[i]f an initial ‘accident’ causes other ‘accidents,’ all will be considered ‘one accident’” and “[a]ll ‘accidents’ that are the result of the same event will be considered ‘one accident.’” Id. at 86. C. The Dispute Concerning the Number of Deductibles Defendant determined that three separate losses had occurred because the tubes

broke at three separate times and the plant operated between the events. Defendant paid Plaintiff $159,711.53 after applying a $100,000 deductible for the loss involving the major shutdown that began on January 17. Defendant paid Plaintiff $67,413.62 after applying a $100,000 deductible for the loss involving the major shutdown that began on March 9. Although Defendant concluded that a covered loss occurred in the amount of $93,877.70

for the shutdown that began on March 20, Defendant did not pay Plaintiff for that loss because the damage did not exceed the $100,000 deductible. If Defendant had applied one deductible for the whole period, Defendant would have paid Plaintiff an additional $193,877.70. Plaintiff filed a complaint in state court, and Defendant subsequently removed the case to federal court based on diversity of citizenship jurisdiction. (Notice of Removal,

ECF No. 1.) The parties filed cross motions for summary judgment, a joint stipulated statement of material facts, and separate statements of material facts. (ECF Nos. 21, 23, 24, 25, 27, 29.) After oral argument, the Court denied Plaintiff’s motion and granted in part and denied in part Defendant’s motion. (Summary Judgment Order, ECF No. 38.) The Court concluded the summary judgment record established three separate

mechanical breakdowns for deductible purposes because the multiple tube breakages resulted in three significant shutdowns for repairs, each occurring weeks or more apart with virtually full operation of the plant between the incidents. (Id. at 18–19.) Applying the “one accident” provision to the summary judgment record, the Court concluded at least two deductibles applied because there was no basis to conclude that the fractures in Tubes

1 and 2 resulting in the first major shutdown caused the breakage in Tube 3 and the second major shutdown. (Id. 20–21.) The Court could not determine at summary judgment whether two or three deductibles applied, however, because a factual dispute remained as to whether the breakage of Tube 3 and the second major shutdown caused the leak in Tube 4 discovered during the third major shutdown. (Id.)

After the Court denied Plaintiff’s request for reconsideration and upheld the summary judgment determinations, (Order, ECF No. 62), the parties submitted supplemental stipulations of fact and sought judgment on a stipulated record. (Suppl. Stipulation, ECF No. 72; Motions, ECF Nos. 78, 79.) LEGAL STANDARD Unlike motions for summary judgment, “[i]n a case submitted for judgment on a

stipulated record, the district court resolves disputed issues of material fact.” Bhd. of Locomotive Engineers v. Springfield Terminal Ry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
MAINE WOODS PELLET CO LLC v. WESTERN WORLD INSURANCE COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maine-woods-pellet-co-llc-v-western-world-insurance-company-med-2021.