Mahoney, Inc. v. Galokee Corporation

522 P.2d 428, 214 Kan. 754, 1974 Kan. LEXIS 399
CourtSupreme Court of Kansas
DecidedMay 11, 1974
Docket47,273
StatusPublished
Cited by13 cases

This text of 522 P.2d 428 (Mahoney, Inc. v. Galokee Corporation) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mahoney, Inc. v. Galokee Corporation, 522 P.2d 428, 214 Kan. 754, 1974 Kan. LEXIS 399 (kan 1974).

Opinion

The opinion of the court was delivered by

Fromme, J.:

The appellant Jim Mahoney, Inc., contracted to build a 64-bed nursing home at Galena, Kansas, under a standard form contract with the appellee, The Galokee Corporation. The contract sum for completion of the project was $179,500.00. The appellant Mid-Continent Casualty Co. furnished the performance bond for the contractor. Construction of the building was begun in February and continued to mid-November, 1969. The building was occupied by The Galokee Corporation in December, 1969, and received approval from the state of Kansas for use as a nursing home. The building has been so used continuously since that time. A dispute arose between Jim Mahoney, Inc., which we will call the contractor, and The Galokee Corporation, which we will call the owner, over failure to complete and construct the building according to the plans and specifications.

Suit was filed by the contractor to recover a balance remaining due under the contract. The owner answered and filed a cross-petition claiming the contractor had defaulted by failing to complete construction, by using inferior materials, by providing poor workmanship and by failing to comply with the plans and specifications of the contract. The case was tried to the court and the court made specific findings of fact on which a final judgment was entered after offsetting a $16,215.48 balance found due the contractor against the sum of $58,960.00, which was the amount of repairs found necessary to bring the facilities up to contract specifications. A net judgment of $42,744.52 was entered in favor of the .owner and against the contractor. From this judgment the contractor and its bonding company appeal.

The first point raised by appellants, which we need to consider, is that the court accepted and erroneously used evidence of the *756 “cost of repairs” to establish the damages. They argue that, since die trial court found the contractor did not substantially perform its contract on seven specific items, it should have used evidence of “diminution of value” instead of “cost of repairs”.

In Phillips & Easton Supply Co., Inc. v. Eleanor International, Inc., 212 Kan. 730, 512 P. 2d 379, the general rule as to measure of damages for breach of contract is stated as follows:

“. . . The measure of damages recoverable for a breach of contract is limited to such [damages] as may fairly be considered as arising in the usual course of things from the breach itself, or as may reasonably be assumed to have been within the contemplation of the parties as the probable result of such a breach. [Citations omitted.] The evidence allowed to support damages for breach of contract is the best evidence obtainable under the circumstances of the case to show the natural and ordinary consequences of the breach and which will enable the court or the jury to arrive at a reasonable estimate of the loss which resulted. [Citations omitted.]” (p. 738.)

Cases are cited by both parties in which this court has accepted evidence of “cost of repairs” to establish a proper measure of damages. (McCullough v. Hayde, 82 Kan. 734, 109 Pac. 176; McCune v. Ratcliff, 88 Kan. 653, 129 Pac. 1167; Big Chief Sales Co., Inc., v. Lowe, 178 Kan. 33, 283 P. 2d 480; Thompson Construction Co. v. Schroyer, 179 Kan. 720, 298 P. 2d 239.) A more recent case approving the use of such evidence to establish a correct measure of damages for breach of a construction contract is Steffek v. Wichers, 211 Kan. 342, 351, 507 P. 2d 274.

However, Lofsted v. Bohman, 88 Kan. 660, 129 Pac. 1168; Thomas v. Warrenburg, 92 Kan. 576, 141 Pac. 255; and most of the cases cited in the foregoing paragraph recognize that evidence of “diminution of value” may be accepted under particular circumstances where such evidence will more reasonably establish the true measure of damages set forth in Phillips & Easton Supply Co., Inc. case quoted above. It should be noted that this measure of damages is limited to those damages which may fairly be considered as arising in the usual course of things from the breach itself, or as may reasonably be assumed to have been within the contemplation of the parties as a probable result of such breach.

Under Article 25 of the present contract the parties provided for default as follows:

“If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents or fails to perform any provision of the Contract, the Owner may, after seven days’ written notice to the Contractor and without prejudice to any other remedy he may have, make good such defi *757 ciencies and may deduct the cost thereof from the payment then or thereafter due the Contractor or, at his option, may terminate the Contract and take possession of the site and of all materials, equipment, tools, and construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever method he may deem expedient, and if the unpaid balance of the Contract Sum exceeds the expense of finishing the Work, such excess shall be paid to the Contractor, but if such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner."

The record in the present case contains substantial and convincing evidence that the contract was not completed and that the contractor failed to fulfill the requirements of the specifications in seven particulars. Regardless of the finding of the trial court that the contractor had not substantially performed the contract the trial court was correct in accepting evidence on the “cost of repairs” to establish the amount of damages suffered. When a building contract has been so far performed that the building is occupied and used by the owner for the purposes contemplated by the contracting parties and where correction or completion would not involve unreasonable destruction of the work done by the contractor evidence of the cost of correcting the defects and completing the omissions will, as a general rule, be a fair measure of the damages. Not only is this rule firmly entrenched in our case law but the parties, in effect, provided for applying the rule in this case by inserting Article 25 in their contract. Where the parties to a construction contract provide drat if the contractor defaults or neglects to carry out the work in accordance with the contract the owner may terminate the contract, take possession of the site and finish the work at the expense of the contractor it may be presumed that evidence of the cost of repairs and work necessary to bring the building up to specifications was reasonably contemplated by the parties as proper to establish the damages which would arise from a breach.

The appellant-contractor next contends that, even if evidence of the “cost of repairs” was proper, there was no substantial, competent evidence to support certain specific items of damage which the trial court awarded the appellee-owner.

The pertinent findings of the court upon which the judgment was entered are as follows:

“6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells Fargo Bank Texas, N.A. v. Foulston Siefkin LLP
348 F. Supp. 2d 772 (N.D. Texas, 2004)
Butera v. Boucher
798 A.2d 340 (Supreme Court of Rhode Island, 2002)
Masterson v. Boliden-Allis, Inc.
865 P.2d 1031 (Court of Appeals of Kansas, 1993)
Tonkin v. Bob Eldridge Construction Co.
808 S.W.2d 849 (Missouri Court of Appeals, 1991)
Haag v. Dry Basement, Inc.
732 P.2d 392 (Court of Appeals of Kansas, 1987)
Hochman v. American Family Insurance
673 P.2d 1200 (Court of Appeals of Kansas, 1984)
Pickens v. Cunningham
22 Pa. D. & C.3d 40 (Mercer County Court of Common Pleas, 1981)
Sippy v. Cristich
609 P.2d 204 (Court of Appeals of Kansas, 1980)
Rhine v. Miller
583 P.2d 458 (Nevada Supreme Court, 1978)
Kansas State Bank v. Overseas Motosport, Inc.
563 P.2d 414 (Supreme Court of Kansas, 1977)
Whiteley v. O'DELL
548 P.2d 798 (Supreme Court of Kansas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
522 P.2d 428, 214 Kan. 754, 1974 Kan. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mahoney-inc-v-galokee-corporation-kan-1974.