Brown-Randolph Co. v. Gude

106 S.E. 161, 151 Ga. 281, 1921 Ga. LEXIS 221
CourtSupreme Court of Georgia
DecidedJanuary 13, 1921
DocketNo. 2032
StatusPublished
Cited by9 cases

This text of 106 S.E. 161 (Brown-Randolph Co. v. Gude) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown-Randolph Co. v. Gude, 106 S.E. 161, 151 Ga. 281, 1921 Ga. LEXIS 221 (Ga. 1921).

Opinions

Hill, J.

(After stating the foregoing facts.) Brown-Bandolph Company owned a city lot on the southwest corner of Marietta and [288]*288Forsyth Streets in the City of Atlanta, on which it decided to construct a building. Before the written contract for the construction was entered into, Gude & Company addressed the following letter: “Atlanta, Ga., June 28th, 1917. Mr. A. Ten Eyck Brown, Architect, Forsyth Building City. Dear Sir: — In-regard to the building you propose to have erected on the southwest corner of Forsyth and Marietta Streets, this city. We have made a careful estimate of the cost from your plans and outlined specifications, and we find that the building will cost completed, including all mechanical equipment, elevators, electric fixtures, etc., $375,000 including our commission, but not including the architect’s commission. Very truly yours, Gude & Company.” On July 30, 1917, a contract was entered into between Gude & Company and Brown-Randolpli Company, the material portions of which are given in the foregoing statement of facts. In this contract no express reference is made to the letter from Gude & Company to A. Ten Eyck Brown, just set out. The present equitable petition was filed by Brown-Randolph Company against A. V. Gude as surviving partner of Gude & Company, the Trust Company of Georgia as executor of A. V. Gude Sr., and A. Ten- Eyck Brown, praying for an accounting; for cancellation of the alleged claim of lien and all notes in the hands of the defendants, given by the plaintiff, which represented any sum in excess of the amount that might be found to be due by plaintiff tó Gude & Company; and for injunction against assigning or transferring as security any of the notes, given by plaintiff, in the possession, custody, or control of defendants, and against interfering with the plaintiff’s possession of the property, or asserting against plaintiff any claim in any proceeding other than the present cause. The petition was demurred to on general and special grounds. The court sustained the general demurrer and dismissed the petition, and the plaintiff excepted. The court held that the plaintiff had a complete remedy at law, and that a court of equity had no jurisdiction of a case like the present.

In the view we take of this case, regardless of whether a court of equity or a court of law has jurisdiction, the controlling question is whether the petition sets out a cause of action against the defendant. It will be observed that the letter written by Gude & Company to A. Ten Eyck Brown was not addressed to the plaintiff in this case, and it nowhere expressly appears -that A. Ten Eyck [289]*289Brown was the agent of the plaintiff. In order for the plaintiff to recover on the basis of the letter being made a part of the contract, it must appear that A. Ten Eyck Brown was the duly constituted agent of the plaintiff, and that the letter was a part of the contract. As stated above, the letter is not referred to in the contract expressly or by necessary implication; and therefore the letter cannot be said to be a part of the written contract of July 30, 1917. It will be seen from the terms of the written contract itself that the contractors, “ for the consideration of actual cost plus a commission of ten per cent., will furnish all labor and material and all necessary estimates of cost, and will construct the owner’s proposed building,” etc. It was also agreed and understood that “ the building will be constructed and completed according to the plans and specifications and under the directions of A. Ten Eyck Brown, architect. In all cases of doubt or dispute as to the meaning of the plans and specifications, the architect’s decision shall be final. Also, “ that the estimates of the contractors made in writing from completed drawings and specifications and full information will be correct to the extent that the cost will not exceed the estimate more than 5 per cent.” It is contended by the plaintiff that the contractor, Gude & Company, guaranteed to construct the building at a total cost of $375,000, as stated in the letter of June .28, 1917. But it will be observed that when this letter was written there was no written contract between Brown-Bandolph Company and Gude & Company, and, so far as appears in the record, there were at that time no " completed drawings and specifications and full information.” It is true that in the amendment to the petition it is alleged that the letter of June 28 was a part of the contract of July 30; but such allegation must be construed as a mere conclusion of the pleader, or as an effort to vary the terms of the written contract, as there is nothing in the contract itself to justify this allegation and conclusion. The contract itself shows that the letter was not made a part of the contract, nor is there in the petition or either amendment' any allegation that when the estimate was made by Gude & Company on June 28 they had in their possession completed plans and specifications and full information. It is alleged that Gude “ had in his hands and possession all the information fromi the architect which said Gude & Company thought would be needed,” but no such plans and specifications are attached to [290]*290the petition., nor is their substance therein set out. The estimates that were to'be binding were those made after completed plans and specifications and full information had been given to Gude & Company. The question, therefore, is whether the completed plans and specifications and full information as contemplated by the contract . were in the hands of the contractor on the date that the contract of July 30 was entered into and exeerited. Even if the letter of June 28 could be construed as a part of the written contract, it does, not show on its face that it was made from " completed plans and specifications and full information,” but that it was simply from “ outlined specifications.” We think that the facts alleged in the petition do not show that the letter of June 28 was a part of the contract (except as a conclusion of the pleader), and that the estimate of $375,000 made on that date was not the estimate provided for in the subsequently executed written contract of July 30, which is plain and unambiguous. If any previous negotiations between Gude & Company and the plaintiff were had, and they were consistent with the written contract, they will be construed as being merged into the contract; and if, on the other hand, any preliminary negotiations were had between the parties which were inconsistent with the written contract, they would be eliminated by the contract itself. But surely no preliminary estimates between Gude & Company and A. Ten Eyck Brown, before the execution of the written contract, could bind Gude & Company relatively to the plaintiff, in the absence of an allegation to the effect that the architect was the agent and acted for the plaintiff; and there is no such allegation in the petition. We cannot, therefore, look to the letter from Gude & Company to the architect as a basis for the suit, but must look to the words of the contract itself; and those words provide that It is .mutually agreed and understood that the contractors will complete the building within ten (10) months after they are given possession of the property and are furnished with complete plans and specifications and all other necessary information.” And under the contract of July 30 with Gude & Company the plaintiff was to pay actual cost of the construction of the building, plus a commission to the contractor's of ten per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pickens v. Cunningham
22 Pa. D. & C.3d 40 (Mercer County Court of Common Pleas, 1981)
Berry v. DISCOUNT LUMBER & SUPPLY COMPANY
219 S.E.2d 434 (Supreme Court of Georgia, 1975)
Mahoney, Inc. v. Galokee Corporation
522 P.2d 428 (Supreme Court of Kansas, 1974)
Williams v. Bell
190 S.E.2d 818 (Court of Appeals of Georgia, 1972)
Peachtree Medical Building, Inc. v. Keel
130 S.E.2d 530 (Court of Appeals of Georgia, 1963)
Gaines v. Edwards
71 S.E.2d 214 (Supreme Court of Georgia, 1952)
Great American Indemnity Co. v. Horkan
57 S.E.2d 487 (Supreme Court of Georgia, 1950)
Aero Construction Co. v. Grizzard
46 S.E.2d 767 (Court of Appeals of Georgia, 1948)
Parks v. Harper
158 S.E. 454 (Court of Appeals of Georgia, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
106 S.E. 161, 151 Ga. 281, 1921 Ga. LEXIS 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-randolph-co-v-gude-ga-1921.