Mahaiwe, LLC SP & CU - Decision in On-The-Record Appeal

CourtVermont Superior Court
DecidedMay 10, 2018
Docket121-10-16 Vtec
StatusPublished

This text of Mahaiwe, LLC SP & CU - Decision in On-The-Record Appeal (Mahaiwe, LLC SP & CU - Decision in On-The-Record Appeal) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mahaiwe, LLC SP & CU - Decision in On-The-Record Appeal, (Vt. Ct. App. 2018).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 121-10-16 Vtec

Mahaiwe, LLC Site Plan & Conditional Use Approval

Decision in On-The-Record Appeal This on-the-record appeal presents an unusual case. Mahaiwe, LLC (“Mahaiwe”) proposed specific lighting and fencing as part of a conditional use and site plan review application. The City of Vergennes Development Review Board (“the DRB”) included the fencing proposal as a condition in its September 12, 2016 approval of the application. Mahaiwe now appeals the fencing condition, and challenges whether the lighting that it proposed is part of the approval. Mahaiwe is represented by Colin R. Hagan, Esq. and David J. Shlansky, Esq., and the City of Vergennes (“the City”) is represented by James H. Ouimette, Esq.

On-The-Record Scope and Standard of Review This is an on-the-record appeal. See 24 V.S.A. § 4471(b). As such, we review the decision below, the record made before the municipal panel, and the briefs submitted by the parties. In re Saman ROW Approval, No. 176-10-10 Vtec, slip op. at 1–3 (Vt. Super. Ct. Envtl. Div. Sept. 2, 2011) (Durkin, J.). Our review is further limited to the issues raised in the Statement of Questions. V.R.E.C.P. 5(f). We are directed to affirm the DRB findings if they are “supported by substantial evidence,” but should “review the DRB’s legal conclusions without deference where such conclusions are outside the DRB's area of expertise.” In re Stowe Highlands Resort PUD to PRD Application, 2009 VT 76, ¶ 7, 186 Vt. 568 (citation omitted).

1 Background The background and procedural history of this matter is set out at some length in an April 28, 2017 decision. Mahaiwe, LLC SP & CU, No. 121-10-16 Vtec, slip op. at 7 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2017) (Durkin, J.). We briefly recount some of the more salient issues here. Mahaiwe filed its application for site plan approval and a conditional use permit to convert two buildings. Part of the property is on the waterfront, with a substantial drop to the water. Some of the existing fencing at the waterfront is post and chain, and some post and lattice, and there are some gaps in the fencing. The initial application details the type of exterior lighting to be used on the project. Over a series of communications between Mahaiwe and the City during the application process, Mahaiwe subsequently proposed two fencing options for the waterfront: to maintain the existing fence (Option I), or to replace it with vertical metal posts bolted into the ground, two top rails and one bottom rail between them, and vertical metal pickets between the bottom rail and the lower top rail (Option II). The DRB approved the application with the following condition: The Applicant shall replace and install perimeter fencing on the Norton Grist Mill property including modifications to close off any breaks in the fencing that currently exist. The fencing shall be substantially identical with the perimeter fencing . . . as proposed by the Applicant in Option II. A second condition requires Mahaiwe to obtain a certificate of occupancy confirming that the fencing is installed as called for in the first condition.

Procedural History Mahaiwe’s Statement of Questions includes 16 Questions. On Mahaiwe’s request, we addressed the merits of Questions 1, 2, 6, 7, 9, 10, and 13 and affirmed the DRB’s decision in our April 28, 2017 decision. Mahaiwe filed a motion to reconsider on May 8, 2017, asking leave to brief those Questions not addressed in the April 28, 2017 decision. We granted this request in a July 24, 2017 entry order, limited to Questions 7, 8, 11, 12, and 14–16. We directed the parties to avoid repeating arguments already made and reminded the parties that we cannot issue advisory opinions.

2 The remaining Questions are as follows: Question 7: Does the Constitution of the State of Vermont prohibit the DRB from imposing the conditions set forth in its Decision? Question 8: Does the Charter of the City of Vergennes, Vermont, fail to enable the DRB imposing [sic] the conditions set forth in its Decision? Question 11: Are the conditions set forth in the DRB Decision (such as fencing) permanently fixed such that any alteration hereafter requires DRB approval, based on the existing regulations? Question 12: If the answer to the foregoing questions is “yes,” what is the quantum of change that requires DRB approval (and what standards) in the current regulations would apply and guide such change review? Question 14: Please see Questions 1 through 12. If the answer to Question 11 is “yes,” then apply each of Question 1 through 12 to the specifications on lighting (including locations and types). Question 15: Are the landscape specifications and depictions, such as (without limitation) walkway fence posts, ramps, bushes, perennial plantings, edging, and outdoor seats, contained in Applicant’s application (only part of which was attached by the DRB to its Decision), as purportedly required by the DRB, incorporated by reference into the permit conditions and made into binding permit conditions (as alleged by the DRB)? Question 16: Please see Questions 1 through 12. If the answer to Question 15 is “yes,” then apply each of Question 1 through 12 to the specifications on lighting (including locations and types).

Discussion Mahaiwe addresses the legal issues raised in its remaining Questions by presenting six legal arguments in its brief. While some of these arguments do not fit neatly under the Questions as presented, we grant that they could be construed as falling within issues that are at least intrinsic to the Statement of Questions. See In re Jolley Assocs., 2006 VT 132, ¶ 9, 181 Vt. 190. Further, some of Mahaiwe’s arguments have already been addressed by the Court, and some appear to relate to Questions that were not to be briefed pursuant to our July 24, 2017 order.

3 Nevertheless, in the interest of addressing the full scope of issues, we address Mahaiwe’s arguments in turn. Argument 1: The DRB is preempted from imposing the stated conditions in its decision. Mahaiwe argues that the regulation of public safety in and around public buildings, like the one at issue here, is granted to the Commissioner of Public Safety, and that this preempts any authority that the City may have to regulate safety. A municipal body’s “power is derivative, based upon an allocation of authority from the state. Where conflict occurs, and no resolution is statutorily prescribed, the municipality must yield.” Morse v. Vermont Div. of State Bldgs., 136 Vt. 253, 255 (1978). Our Supreme Court has cautioned that this preemption must be “carefully invoked,” and that, where possible, laws should be construed “to harmonize and give effect to each, if they can be viewed so as to operate without conflict and without compromise as to the purpose of the superior enactment.” In re Patch, 140 Vt. 158, 176–77 (1981). The City’s power to regulate safety stems from the Vermont Planning and Development Act, which authorizes municipalities to regulate land development in relation to “public health, safety, and welfare.” 24 V.S.A. § 4411(a); see also 24 V.S.A. § 4302(a). This delegated power is exercised in the City of Vergennes Zoning and Subdivision Regulations, effective December 10, 2015 (“the Regulations”), which regulate safety at §§ 102, 103, 702, 802, 803.1 Mahaiwe cites 20 V.S.A. § 2731(a) as grounds for its preemption argument. This statute gives the Commissioner of Public Safety authority to regulate “the construction of buildings, maintenance and operation of premises, and prevention of fires and removal of fire hazards, and to prescribe standards necessary to protect the public, employees, and property against harm arising out of or likely to arise out of fire.” 20 V.S.A. § 2731(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kostenblatt
640 A.2d 39 (Supreme Court of Vermont, 1994)
In Re Appeal of 232511 Investments, Ltd.
2006 VT 27 (Supreme Court of Vermont, 2006)
In Re Duncan
584 A.2d 1140 (Supreme Court of Vermont, 1990)
In Re Handy
764 A.2d 1226 (Supreme Court of Vermont, 2000)
In Re Appeal of Jackson
2003 VT 45 (Supreme Court of Vermont, 2003)
Morse v. Vermont Division of State Buildings
388 A.2d 371 (Supreme Court of Vermont, 1978)
In Re Zoning Permit Application of Clyde
437 A.2d 121 (Supreme Court of Vermont, 1981)
State v. Sanguinetti
449 A.2d 922 (Supreme Court of Vermont, 1982)
In Re Appeal of Miller
742 A.2d 1219 (Supreme Court of Vermont, 1999)
In Re Appeals of Letourneau
726 A.2d 31 (Supreme Court of Vermont, 1998)
In Re Appeal of JAM Golf, LLC
2008 VT 110 (Supreme Court of Vermont, 2008)
In Re Stowe Highlands Resort PUD to PRD Application
2009 VT 76 (Supreme Court of Vermont, 2009)
Rhodes v. Town of Georgia
688 A.2d 1309 (Supreme Court of Vermont, 1997)
Appeal of Farrell & Desautels, Inc.
383 A.2d 619 (Supreme Court of Vermont, 1978)
In re Howard CEnter Renovation Permit
2014 VT 60 (Supreme Court of Vermont, 2014)
In re Wagner & Guay Permit (Mary Bourassa, Appellant)
2016 VT 96 (Supreme Court of Vermont, 2016)
In re LaBerge NOV
2016 VT 99 (Supreme Court of Vermont, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Mahaiwe, LLC SP & CU - Decision in On-The-Record Appeal, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mahaiwe-llc-sp-cu-decision-in-on-the-record-appeal-vtsuperct-2018.