Magnum Construction Management Corp., Etc. v. City of Miami Beach

209 So. 3d 51, 2016 Fla. App. LEXIS 18359
CourtDistrict Court of Appeal of Florida
DecidedDecember 14, 2016
Docket3D15-2239
StatusPublished
Cited by2 cases

This text of 209 So. 3d 51 (Magnum Construction Management Corp., Etc. v. City of Miami Beach) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Magnum Construction Management Corp., Etc. v. City of Miami Beach, 209 So. 3d 51, 2016 Fla. App. LEXIS 18359 (Fla. Ct. App. 2016).

Opinion

ROTHENBERG, J.

Magnum Construction Management Corporation (“MCM”) and its surety, Travelers Casualty and Surety Company of America . (“Travelers”), appeal the trial court’s entry of a final judgment against them and in favor of the City of Miami Beach, Florida (“the City”), who claimed, in part, that MCM was liable for playground defects and landscaping.defects at South Pointe Park (“South Pointe Park” or “the park”). Because the City failed to provide MCM with an opportunity to cure the defects in the playground, as required by the contract between the parties, we reverse the trial court’s finding that MCM was liable for the playground defects. Additionally, because the trial court’s award of damages in connection with the landscaping defects on the project was specula *53 tive, we reverse the award and remand for a new trial on damages.

BACKGROUND

The underlying lawsuit arose out of a construction project that was intended to redesign and improve South Pointe Park. The City awarded Hargreaves Associates, Inc. (“Hargreaves”) the contract for designing the park and supervising the construction project. Thereafter, the City awarded MCM the general contract for the construction of the park. Travelers issued a performance bond for the project and named MCM as the principle and the City as the obligee.

The park was designed to include, in part, a new children’s playground and a variety of new grassy turfs and other landscaping features. Construction commenced in 2007, and on March 20, 2009, Hargreaves issued a Certificate of Substantial Completion, which according to the contract documents indicated that “all conditions and requirements of permits and regulatory agencies have been satisfied and the Work, is substantially complete in accordance with the Contract Documents, so the Project is available for beneficial occupancy by CITY,” Although Hargreaves stopped working on the park by October 2009 due to a payment dispute Hargreaves had with the City, the City did not officially terminate its contract with Hargreaves until 2011, and in the interim, the City did not hire a replacement for Hargreaves.

In the aftermath of a major flood in 2009, several aspects of the park’s landscaping began to decline, including the deterioration of the sod in certain areas of the park. Although the parties attempted to maintain the park and remediate the problems with the landscaping features, when it became obvious that these attempts were not going to solve the problem, the City hired Rosenberg Gardner Design to create a remediation plan. It was eventually determined that one of the primary causes , for the problems with the sod and other landscaping features was the over compaction of the soil, and the City ultimately awarded Superior Landscaping & Lawn Service, Inc. the construction bid to remediate the park.

In addition to the landscaping defects, it also became apparent that some of the aspects of the park’s playground were not in compliance with certain contractually required safety standards. On December 6, 2010, the City unilaterally performed an audit of the playground and initiated the underlying litigation. As the trial court correctly noted below, several of the playground defects were minor and could have been easily corrected, such as a missing slide side rail, properly sized metal cap covers, and.the relocation of a sculpture. The City did not, however, offer MCM the opportunity to repair or cure any of the defects in the playground, but instead removed, redesigned, and replaced the playground in its entirety. It is particularly noteworthy that the City’s own expert witness, Teri Hendy, never recommended that the playground be entirely removed. 1

After a bench trial, the trial court entered a verdict adjudicating the City’s claims against MCM, Travelers, and Hargreaves. The trial court found that: (1) MCM was liable for breach of contract and breach of warranty; (2) Travelers was liable for breach of performance; and (3) Hargreaves was liable for breach of contract, negligence, and negligence per se.

*54 As to MCM’s liability for the playground defects, the trial court specifically found that, although the City did not agree to work with MCM to prepare a joint audit of the playground and never provided MCM with an opportunity to cure the deficiencies in the playground, the City suffered damages because the playground did not comply with the safety standards in the contract documents. The trial court, however, found that the City’s complete removal and replacement of the playground was excessive, and therefore reduced the damages accordingly.

As to MCM’s liability for the subgrade, sod, and landscaping defects, the trial court found that the City was entitled to be reimbursed for the remediation of the defects in the park, and that MCM was partially at fault for failing to recognize that over compacting the soil would cause the grass and landscaping to fail. However, the trial court also found that the City was not entitled to a betterment, which the trial court calculated as the difference between the total amount sought by the City and the entire damage award. After the trial court entered a final judgment, MCM and Travelers timely appealed. 2

ANALYSIS

1. Liability for the playground defects

MCM argues that it cannot be held liable for the playground defects because the City never provided MCM with an opportunity to cure any of the playground defects, as required by the contract documents. Because section 25.3 of the General Conditions of the contract documents plainly provides for an opportunity to cure, we agree.

Section 25.3 provides as follows:

If, within one (1) year after the date of substantial completion or such longer period of time as may be prescribed by the terms of any applicable special warranty required by the Contract Documents, or by any specific provision of the Contract Documents, any of the Work is found to be defective or not in accordance with the Contract Documents, CONTRACTOR, after receipt of written notice from CITY, shall promptly correct such defective or nonconforming Work within the time specified by the CITY without cost to CITY, to do so.

This provision requires the City to notify MCM, the contractor, of any defects it finds in MCM’s work. Thereafter, MCM “shall” correct the defective work within the time specified by the City. It follows, therefore, that the City was required to notify MCM of any defective work and provide MCM with a period of time in which MCM must cure the identified defects.

Although section 25.3 is dispositive of this issue, we note that had the contract been performed as intended, MCM would also have been given other opportunities to cure the playground defects through the project’s “consultant,” Hargreaves. For example, section 25.1 states as follows: “CONSULTANT shall have the authority to reject or disapprove work which CONSULTANT finds to be defective. If required by CONSULTANT, CONTRACTOR shall promptly either correct all defective work or remove such defective work and replace it with nondefective work.” Similarly, the contract contains an alternative dispute resolution provision in section 12.1, which states as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moncada Alaniz v. Bay Promo, LLC
143 F.4th 18 (First Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
209 So. 3d 51, 2016 Fla. App. LEXIS 18359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/magnum-construction-management-corp-etc-v-city-of-miami-beach-fladistctapp-2016.