Magee v. BEA Construction Corp.

797 F.3d 88, 92 Fed. R. Serv. 3d 605, 2015 U.S. App. LEXIS 13690, 2015 WL 4639239
Court of Appeals for the First Circuit·Decided August 5, 2015·No. 14-1541·Published·Cited by 3 cases

Opinion

SELYA, Circuit Judge.

This diversity case involves an old-fashioned contract dispute between property owners and a construction firm. Defendant-appellant BEA Construction Corp. (BEA) failed to dissuade a jury from finding that it was on the wrong side of the dispute and now challenges the sufficiency of the evidence. Since this challenge comes too late and offers too little in the way of substance, we affirm.

We highlight the pertinent events, re-„ solving any factual conflicts in favor of the jury verdict. See La Amiga del Pueblo, Inc. v. Robles, 937 F.2d 689, 690 (1st Cir.1991). The plaintiffs, Robert Magee and his wife Zoraida, are citizens of New Jersey. Having retired, they wished to build a vacation home in Vieques, Puerto Rico. To that end, they entered into an oral contract with BEA in December of 2008 for the assembly of a prefabricated house on a lot that they owned. The plaintiffs gave BEA an $80,000 down payment on the understanding that the project would be completed within 16 months. Work commenced shortly thereafter.

Roughly a year later, the parties’ relationship began to sour. At that time, the plaintiffs requested that the project be put on hold to accommodate Mr. Magee’s failing health. BEA agreed to stop work and to reimburse the unspent portion ($74,406) of the down payment. But words are not always matched by deeds, and the plaintiffs received only $1000.

The parties subsequently entered into a second oral agreement for the assembly of a smaller and cheaper home. This new project was to be completed within four months and the plaintiffs were to receive credit against the contract price for any monies owed to them with respect to the original project. BEA began receiving materials in May of 2011 but — by July of 2012 — it had managed to do nothing more than dig a square hole and place rebar columns in the ground.

The plaintiffs were disgruntled and, on September 7, 2012, repaired to the federal district court. Citing diversity of citizenship and the existence of a controversy in the requisite amount, see 28 U.S.C. § 1332(a), they alleged that BEA had breached sundry contractual obligations while failing to complete construction of their home as agreed. In addition to their principal claim, the plaintiffs also asserted breach of contract claims against two BEA officials (C. William Dey and Abigail Gon-zález). BEA counterclaimed, contending that it was the plaintiffs who had defaulted on the contractual arrangements.

Following extensive pretrial skirmishing (none of which is relevant here), the case went to trial in April of 2014. 1 After the plaintiffs rested, the individual defendants (but not BEA) moved for the entry of judgment as a matter of law. See Fed. R.Civ.P. 50(a). The court granted the individual defendants’ motions, accepting their arguments that the evidence afforded no basis either for piercing the corporate veil or for otherwise holding them personally liable. The trial proceeded against BEA alone. On April 11, the jury returned a verdict wholly favorable to the plaintiffs: it found BEA to have defaulted on its contractual obligations, awarded $150,000 in damages, and rejected the *90 counterclaim. BEA did not file any post-trial motions, but it did file a timely notice of appeal.

Though BEA’s appellate brief is not a model of clarity, we construe it liberally and tease from its heated rhetoric three lines of argument. These lines of argument can be summarized as follows: that the jury (i) erroneously found BEA in breach of its contractual obligations; (ii) compounded this error by incorrectly finding that the plaintiffs were not in breach; and'(hi) arbitrarily failed to credit pivotal testimony. A common thread links the three components of this asseverational array: whether viewed singly or in the ensemble, all of BEA’s arguments boil down to an attack on the sufficiency of the evidence.

That attack stumbles at the threshold. It is an elementary principle that a party who wishes to challenge the sufficiency of the evidence on appeal must first have sought appropriate relief in the trial court. See, e.g., Hammond v. T.J. Litle & Co., 82 F.3d 1166, 1171 (1st Cir.1996); La Amiga del Pueblo, 937 F.2d at 691. Here, however, BEA flouted this elementary principle&emdash;and there is a price to pay.

We need not tarry. BEA could have moved for the entry of judgment as a matter of law at various points during and after the trial, see Fed.R.Civ.P. 50(a)-(b), but it never deigned to file such a motion at the close of the plaintiffs’ case, at the close of all the evidence, or even after the verdict. By the same token, BEA could have moved for a new trial following the verdict, see Fed.R.Civ.P. 59, but it did not deign to do so. BEA’s decision to forgo any and all of these anodynes precludes it from challenging the legal sufficiency of the evidence for the first time on appeal. See, e.g., Cone v. W. Va. Pulp & Paper Co., 330 U.S. 212, 217-18, 67 S.Ct. 752, 91 L.Ed. 849 (1947); Hammond, 82 F.3d at 1171; La Amiga del Pueblo, 937 F.2d at 691; Jusino v. Zayas, 875 F.2d 986, 991 (1st Cir.1989); LaForest v. Autoridad de Las Fuentes Fluviales de P.R., 536 F.2d 443, 445 (1st Cir.1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Magee v. BEA Construction Corp., 797 F.3d 88, 92 Fed. R. Serv. 3d 605, 2015 U.S. App. LEXIS 13690, 2015 WL 4639239 (1st Cir. 2015).

797 F.3d 88 (Magee v. BEA Construction Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sonya Leclair v. Donovan Spring Co., Inc.
2018 DNH 241 (D. New Hampshire, 2018)
United States v. Rodriguez-Milian
820 F.3d 26 (First Circuit, 2016)