Madero Construction, Llc, V. Fullwiler Construction, Inc.

CourtCourt of Appeals of Washington
DecidedFebruary 24, 2025
Docket86281-2
StatusUnpublished

This text of Madero Construction, Llc, V. Fullwiler Construction, Inc. (Madero Construction, Llc, V. Fullwiler Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madero Construction, Llc, V. Fullwiler Construction, Inc., (Wash. Ct. App. 2025).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

MADERO CONSTRUCTION, LLC, a No. 86281-2-I Washington limited liability company, DIVISION ONE Respondent, UNPUBLISHED OPINION v.

FULLWILER CONSTRUCTION, INC., a Washington corporation; 2217 NW 62nd ST, LLC, a Washington limited liability company; MERCHANTS BONDING COMPANY (MUTUAL), a surety; FIRST FEDERAL SAVINGS & LOAN ASSOCIATION OF PORT ANGELES, a Washington Bank Corporation; THE OHIO CASUALTY INSURANCE COMPANY, a surety,

Appellants.

FELDMAN, J. — Fullwiler Construction, Inc. (Fullwiler) appeals the trial court’s

award of damages to Madero Construction, LLC (Madero) on Madero’s breach of

contract claim and its dismissal of Fullwiler’s negligent misrepresentation

counterclaim. We affirm.

I

In June 2021, Fullwiler was the general contractor for a townhome

construction project in Ballard (the Ballard Project). Its sole shareholder, Jerry No. 86281-2-I

Fullwiler (referred to herein by his full name to avoid confusion with Fullwiler),

asked Jose Ulloa, the owner of Madero, to perform framing work on the

townhomes as a subcontractor. On July 6, Madero began working on the Ballard

Project, and Jerry Fullwiler signed a Trade Contractor Agreement (TCA)

memorializing the parties’ agreement.

The next day, Fullwiler’s office manager, Mallorie Hefley, e-mailed Ulloa the

TCA and a “starter packet” with two attached addenda regarding insurance

coverage (Addenda A and B) and asked him to complete, sign, and return the

documents to her. The TCA required Madero to maintain insurance during the

contract period for claims arising out of the work and provide Fullwiler with a

certificate of insurance. Ulloa filled out and signed the contract documents and

returned them to Hefley. Unbeknownst to Fullwiler, Madero’s insurance policy had

an exclusion for “newly built residential construction,” which applied to the Ballard

Project. Ulloa did not notify Fullwiler of this exclusion, nor did he supply a

certificate of insurance to Fullwiler.

Madero’s laborers were initially supervised by Fullwiler’s assistant

superintendent, Jacob Minzghor. In mid-July, Ulloa advised Minzghor that certain

aspects of the approved building plans were internally inconsistent. To resolve

this issue, Minzghor instructed Ulloa to construct the roofs in a manner that

deviated from the approved building plans. Madero continued constructing the

roofs per Minzghor’s instructions for several weeks. Then, on August 11, a

replacement superintendent noticed the roofs were not being constructed

according to the approved building plans. Madero’s laborers worked over a period

-2- No. 86281-2-I

of approximately two weeks, at Fullwiler’s direction, to tear down the framing and

reconstruct it according to the approved building plans.

While Madero was reconstructing the roofs, Fullwiler refused to pay invoice

#896008 (Invoice 8), in the amount of $50,172.57, submitted by Madero on August

16 for work it performed between August 2 and August 13. Madero then sent a

“notice of default” to Fullwiler on September 1 that referenced Invoice 8 and “a

second invoice, #896009 [Invoice 9], dated August 28, 2021 for $64,738.80.” On

September 2, Madero ceased working on the Ballard Project. It then generated its

final invoice, Invoice #896010 (Invoice 10), totaling $17,880.24, for work it

performed after August 28. Madero also recorded a mechanic’s lien on September

13, stating the “[p]rincipal amount for which the Lien is claimed is . . . $132,791.61,”

which is the total of the foregoing invoices ($50,172.57 + $64,738.80 +

$17,880.24).

In March 2022, Madero filed a complaint against Fullwiler alleging breach

of contract and seeking damages totaling $132,791.61. 1 In response, Fullwiler

asserted counterclaims alleging Madero breached the parties’ contract by

performing faulty and defective work and negligently misrepresented the extent of

its insurance coverage. Following a bench trial, the court found (a) Madero did not

breach the contract by performing faulty or defective work because it was

instructed by Fullwiler’s agent to deviate from the approved building plans, (b)

1 Madero’s complaint also named as defendants the property owner (2217 NW 62nd St., LLC) and

two sureties (Merchants Bonding Company (Mutual) and The Ohio Casualty Insurance Company). This opinion refers to these defendants collectively as “Fullwiler” because they filed a joint appellate brief in which they collectively refer to themselves as “Fullwiler Construction,” are represented by the same counsel, and have otherwise acted in concert throughout this litigation. A fifth defendant, First Federal Savings & Loan Association of Port Angeles, was voluntarily dismissed.

-3- No. 86281-2-I

Fullwiler breached the contract by failing to pay Madero for all the work it performed

on the Ballard Project through September 2, 2021, and (c) Fullwiler had failed to

establish its negligent misrepresentation claim. Turning to the amount of Madero’s

damages, the trial court found Madero “did sufficiently demonstrate (albeit by a

thin reed) that Madero was deprived of a total of $132,791.61 ($50,172.57 +

$64,738.80 + $17,880.24) due to Fullwiler Construction’s refusal to pay the

invoices.” Fullwiler appeals.

II

A

Fullwiler argues Madero “never offered evidence or testimony” regarding

Invoices 9 and 10 and therefore “failed to prove with substantial evidence

$82,619.04 of $132,791.61 of its claimed damages (62 percent), that were

wrongfully awarded by the trial court.” We disagree.

“The general measure of damages for breach of contract is that the injured

party is entitled to (1) recover all damages that accrue naturally from the breach

and (2) be put into as good a pecuniary position as [the injured party] would have

had if the contract had been performed.” 224 Westlake, LLC v. Engstrom Props.,

LLC, 169 Wn. App. 700, 729, 281 P.3d 693 (2012). While damages must be

proved with reasonable certainty, this certainty requirement “‘is concerned more

with the fact of damage than with the extent or amount of damage.’” Lewis River

Golf, Inc. v. O.M. Scott & Sons, 120 Wn.2d 712, 717, 845 P.2d 987 (1993) (quoting

Gaasland Co., Inc. v. Hyak Lumber & Millwork, Inc., 42 Wn.2d 705, 712-13, 257

P.2d 784 (1953)). As to the amount of damage, “‘Evidence of damage is sufficient

-4- No. 86281-2-I

if it affords a reasonable basis for estimating loss and does not subject the trier of

fact to mere speculation or conjecture.’” Clayton v. Wilson, 168 Wn.2d 57, 72, 227

P.3d 278 (2010) (quoting State v. Mark, 36 Wn. App. 428, 434, 675 P.2d 1250

(1984)).

Where a trial court has weighed the evidence and entered findings of fact,

as the trial court did in this case, “we review the trial court’s factual findings for

substantial evidence to support them.” Norcon Builders, LLC v. GMP Homes VG,

LLC, 161 Wn. App. 474, 497, 254 P.3d 835 (2011). “‘Substantial evidence is

evidence in sufficient quantum to persuade a fair-minded person of the truth of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Lord
822 P.2d 177 (Washington Supreme Court, 1992)
ESCA Corp. v. KPMG Peat Marwick
959 P.2d 651 (Washington Supreme Court, 1998)
Lewis River Golf, Inc. v. O.M. Scott & Sons
845 P.2d 987 (Washington Supreme Court, 1993)
Hardcastle v. Greenwood Savings & Loan Ass'n
516 P.2d 228 (Court of Appeals of Washington, 1973)
Gaasland Co. v. Hyak Lumber & Millwork, Inc.
257 P.2d 784 (Washington Supreme Court, 1953)
Skagit State Bank v. Rasmussen
745 P.2d 37 (Washington Supreme Court, 1987)
State v. Mark
675 P.2d 1250 (Court of Appeals of Washington, 1984)
Owens v. City of Seattle
299 P.2d 560 (Washington Supreme Court, 1956)
Clayton v. Wilson
227 P.3d 278 (Washington Supreme Court, 2010)
Ross v. Kirner
172 P.3d 701 (Washington Supreme Court, 2007)
Lawyers Title Ins. Corp. v. Baik
55 P.3d 619 (Washington Supreme Court, 2002)
Brin v. Stutzman
951 P.2d 291 (Court of Appeals of Washington, 1998)
ESCA Corp. v. KPMG Peat Marwick
135 Wash. 2d 820 (Washington Supreme Court, 1998)
Lawyers Title Insurance v. Baik
147 Wash. 2d 536 (Washington Supreme Court, 2002)
Ross v. Kirner
162 Wash. 2d 493 (Washington Supreme Court, 2007)
Clayton v. Wilson
168 Wash. 2d 57 (Washington Supreme Court, 2010)
Aiken v. Aiken
387 P.3d 680 (Washington Supreme Court, 2017)
Norcon Builders, LLC v. GMP Homes VG, LLC
254 P.3d 835 (Court of Appeals of Washington, 2011)
224 Westlake, LLC v. Engstrom Properties, LLC
281 P.3d 693 (Court of Appeals of Washington, 2012)
Mutual of Enumclaw Insurance v. Gregg Roofing, Inc.
315 P.3d 1143 (Court of Appeals of Washington, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Madero Construction, Llc, V. Fullwiler Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/madero-construction-llc-v-fullwiler-construction-inc-washctapp-2025.