MacKnight Flintic Stone Co. v. City of New York

79 N.Y.S. 523

This text of 79 N.Y.S. 523 (MacKnight Flintic Stone Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacKnight Flintic Stone Co. v. City of New York, 79 N.Y.S. 523 (N.Y. Ct. App. 1903).

Opinion

LAUGHLIN, J.

This is an action to foreclose a mechanic’s lien filed pursuant to the provisions of chapter 315 of the Laws of 1878 against the moneys due or to grow due under a contract made between one Peter J. Brennan and the city of New York, for the construction of Public School No. 109. The evidence in this case is the same as that in the case of MacKnight Flintic Stone Co. v. City of New York (decided herewith) 79 N. Y. Supp. 521, and upon the main issues the opinion in that case is controlling in this. A further question is, however, presented here. At the time the plaintiff abandoned the work on Public School No. 109, it had some material upon the ground, ready for use in the performance of its contract, which Brennan refused to permit it to remove, and a part of which he subsequently [524]*524used in the performance of his contract work with the city for the construction of the school. The appellant now contends that, in any event, it is entitled to a lien for the value of this material; that the material, although delivered on the premises for use in the performance of its contract with Brennan, belonged to it; that the use thereof by Brennan was wrongful, but that it was at liberty, notwithstanding, to waive the tort, and recover the value of the material on an implied contract to pay therefor. Whether the plaintiff could sustain a lien on this theory need not be determined. A sufficient answer to this contention on its part is that the only contract pleaded in the complaint as a basis for this lien is the contract, which was entire, and which the court, upon conflicting evidence, has determined that it failed to perform.

It follows, therefore, that the judgment should be affirmed, with costs.

VAN BRUNT, P. J„ and INGRAHAM and HATCH, JJ., concur. PATTERSON, J., dissents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacKnight Flintic Stone Co. v. City of New York
79 N.Y.S. 521 (Appellate Division of the Supreme Court of New York, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
79 N.Y.S. 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macknight-flintic-stone-co-v-city-of-new-york-nyappdiv-1903.