MacFarland-Breakell Building Corp. v. New York State Thruway Authority

123 Misc. 2d 307, 472 N.Y.S.2d 1004, 1984 N.Y. Misc. LEXIS 2998
CourtNew York Court of Claims
DecidedFebruary 10, 1984
DocketClaim No. 68371
StatusPublished
Cited by6 cases

This text of 123 Misc. 2d 307 (MacFarland-Breakell Building Corp. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacFarland-Breakell Building Corp. v. New York State Thruway Authority, 123 Misc. 2d 307, 472 N.Y.S.2d 1004, 1984 N.Y. Misc. LEXIS 2998 (N.Y. Super. Ct. 1984).

Opinion

OPINION OF THE COURT

Harold E. Koreman, P. J.

Claimant’s action herein is for damages arising out of the alleged breach of a public improvement contract. The defendant’s motion requests dismissal based on claimant’s failure to timely commence its claim pursuant to the requirements of section 145 of the State Finance Law. A cross motion by claimant seeks permission to file a late claim and, in the alternative, requests that its notice of intention be treated as a claim. Although the ultimate issue which must be decided herein is the applicability of section 145 of the State Finance Law to the commencement of public construction contract claims against the Thruway Authority, we must initially note that while a notice of intention and claim were filed with the court and served on the Attorney-General, neither document was served on the Thruway Authority. Said Authority “is an autonomous public corporation, with an existence separate and independent from the State”, and service on the Attorney-General is not sufficient to confer jurisdiction over the Thruway Authority as a party defendant (Cantor v State of New York, 43 AD2d 872, 873). Hence, aside from any issue concerning timeliness of filing, the subject claim against the Thruway Authority must be dismissed as jurisdiction-ally defective (see Kurtz v State of New York, 40 AD2d 917, affd 33 NY2d 828). Similarly, the notice of intention, having never been served on the Thruway, may not be treated as a claim, nunc pro tunc (see Perry v State of New York, 64 AD2d 799). Continuing, however, the Authority was served with notice of claimant’s cross motion for permission to file a late claim (see Court of Claims Act, § 10, subd 6), and the court has thereby obtained the jurisdiction necessary to address this issue as it pertains to the Authority.

By virtue of the standard specifications which are part of claimant’s contract with the Thruway Authority (see Fosco Fabricators v State of New York, 94 AD2d 667), acceptance [309]*309of final payment constitutes a release unless the contractor serves upon the Authority, within 40 days of mailing of final payment, a detailed and verified statement of claim. On February 11,1983, final payment was mailed to claimant, and on March 17,1983, within 40 days thereof, claimant sent the required statement to defendant. Hence, claimant’s acceptance of the payment did not automatically constitute a release. However, in order to commence an action against the Thruway, claimant was additionally required to serve on defendant, and file with the court, a formal claim in compliance with section 11 of the Court of Claims Act, which claimant failed to do.

Assuming, as claimant contends, that the Court of Claims Act (§ 10, subd 4) and not the State Finance Law (§ 145) provides the applicable period for claim filing, claimant nonetheless failed to commence its action within the six months provided therein. However, all of section 10 carries with it the ameliorative consequences of subdivision 6 thereof which states that “[a] claimant who fails to file a claim or notice of intention, as provided in the foregoing subdivisions, within the time limited therein for filing the claim or notice of intention, may, nevertheless, in the discretion of the court, be permitted to file such claim at any time before an action asserting a like claim against a citizen of the state would be barred under the provisions of article two of the civil practice law and rules” (Court of Claims Act, § 10, subd 6; emphasis added). Hence, claimant’s late claim motion, brought within six years of accrual (see CPLR 213, subd 2) could be properly considered by the court. If, however, section 145

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dreger v. New York State Thruway Authority
81 N.Y.2d 721 (New York Court of Appeals, 1992)
Martino v. New York State Thruway Authority
154 Misc. 2d 905 (New York State Court of Claims, 1992)
Shimmerlik v. City University of New York
142 Misc. 2d 118 (New York State Court of Claims, 1988)
Finnerty v. New York State Thruway Authority
140 A.D.2d 941 (Appellate Division of the Supreme Court of New York, 1988)
Muller v. State
108 A.D.2d 181 (Appellate Division of the Supreme Court of New York, 1985)
Krales v. City University
128 Misc. 2d 168 (New York State Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
123 Misc. 2d 307, 472 N.Y.S.2d 1004, 1984 N.Y. Misc. LEXIS 2998, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macfarland-breakell-building-corp-v-new-york-state-thruway-authority-nyclaimsct-1984.