M. Perez Co. v. Base Camp Condominiums Ass'n No. One

3 Cal. Rptr. 3d 563, 111 Cal. App. 4th 456
CourtCalifornia Court of Appeal
DecidedAugust 19, 2003
DocketC039827
StatusPublished
Cited by38 cases

This text of 3 Cal. Rptr. 3d 563 (M. Perez Co. v. Base Camp Condominiums Ass'n No. One) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. Perez Co. v. Base Camp Condominiums Ass'n No. One, 3 Cal. Rptr. 3d 563, 111 Cal. App. 4th 456 (Cal. Ct. App. 2003).

Opinion

Opinion

HULL, J.

In this construction defects dispute, the general contractor, Kerry Meeker, doing business as Kerry Meeker Construction (Meeker), appeals from a postjudgment order denying his request for litigation expenses from the property owner, Base Camp Condominiums Association No. One (Base Camp), and a subcontractor, M. Perez Company, Inc., doing business as Henley & Company (Henley). The court concluded that Meeker failed to establish the existence of a contract containing a provision that would permit the recovery of litigation expenses. Henley also appeals from the order, contending it contains two clerical errors. We reverse the judgment, in part.

FACTS AND PROCEDURAL HISTORY

Because the parties have failed to provide this court with a full record of the proceedings below, our review of the facts is severely limited. From the allegations in the pleadings, it appears that Meeker entered into an agreement with Base Camp to remodel the facade of a condominium complex owned by Base Camp, and Meeker entered into a subcontract with Henley to do the *460 stucco portion of the work. A dispute arose regarding performance by the parties under the agreements and liability for defects in the finished product.

On March 3, 1998, Henley sued Meeker and Base Camp. (Case No. 1599.) Henley alleged an April 23, 1997, agreement with Meeker, requiring Meeker to pay Henley $145,896 for labor and materials. Henley further alleged that Meeker breached the agreement by failing to pay $50,000 of the amount due. Henley sought damages in the amount of $50,000, plus attorney fees. The complaint also contained claims for quantum meruit and indebitatus assumpsit, again seeking damages of $50,000. Henley’s fourth cause of action sought to foreclose on its mechanics lien. A copy of the alleged agreement was not attached to, or incorporated into, the complaint.

On April 14, 1998, Meeker sued Base Camp. (Case No. 1603.) Meeker alleged that he entered into a written agreement with Base Camp “on or about March 1997.” A copy of the agreement was attached to and incorporated into the complaint. Meeker alleged that Base Camp breached the agreement, resulting in damages of $44,791.61. Meeker also alleged quantum meruit, seeking damages of $127,740.39. Meeker sought attorney fees “to the extent available by either contract, statute or bond.”

On July 15, 1998, Base Camp filed a complaint against Meeker and Henley. (Case No. 1610.) Base Camp alleged an April 21, 1997, agreement with Meeker, whereby Meeker would be paid $348,941 for the construction of improvements at the condominium complex. A copy of the agreement was attached to and incorporated into the complaint. It is the same agreement as that attached to Meeker’s complaint against Base Camp. Base Camp further alleged that Meeker entered into a written or oral agreement with Henley, to which Base Camp was a third party beneficiary.

Base Camp alleged five causes of action against Meeker and Henley: (1) breach of implied warranty; (2) negligence; (3) breach of contract; (4) breach of the covenant of good faith; and (5) breach of express warranty. On each cause of action, Base Camp sought compensatory damages of $500,000. It also sought attorney fees “as provided under the contract.”

Base Camp’s answers to the complaints of Meeker and Henley contained general denials and asserted a right to litigation expenses. Meeker’s answer to Base Camp’s complaint likewise contained a general denial. It also contained an affirmative defense asserting a right to indemnity from those “whose negligence and/or fault proximately contributed to [the] damages ...” and sought an award of attorney fees. Henley’s answer to Base Camp’s complaint asserted a general denial and an affirmative defense that the complaint failed to state a claim sufficient to allow Base Camp to recover attorney fees. Henley sought an award of attorney fees.

*461 Meeker’s answer to Henley’s complaint is not in the record. However, the record does contain a cross-complaint filed by Meeker against Henley on October 23, 1998. In it, Meeker alleged breach of the April 23, 1997, agreement between Meeker and Henley and a right to indemnity with respect to the Base Camp action. Meeker later filed a first amended cross-complaint, naming two additional cross-defendants not parties to this appeal. Meeker asserted a right to indemnity from the cross-defendants for any judgment that might be entered against him on the complaints filed by Base Camp and Henley. Meeker also claimed a right to attorney fees.

Meeker filed a first amended complaint against Base Camp. For breach of contract, Meeker sought “undisputed” damages of $44,000, plus a penalty of 24 percent per year. Meeker also claimed approximately $166,405.93 for extra work on the project and $100,000 in consequential damages. On his quantum meruit claim, Meeker sought damages of $190,000. Meeker later filed a second amended complaint, alleging consequential damages of $180,000.

Prior to trial, Base Camp offered Meeker $115,000 in settlement pursuant to Code of Civil Procedure section 998. (Further undesignated section references are to the Code of Civil Procedure.) Henley made a section 998 offer to Base Camp to accept $17,500 in settlement.

The three cases were consolidated and tried to a jury. In case No. 1599, the jury returned a general verdict in favor of Henley and against Meeker. The jury awarded damages of $36,676 on the breach of contract claim and $26,654 on the quantum meruit claim. In the other two actions, the jury returned a special verdict. The jury concluded that Meeker was entitled to $44,665 on its contract with Base Camp. The jury also concluded that Meeker was entitled to reimbursement for various additional costs incurred by Meeker on the project, totaling $77,251.

On Base Camp’s claims against the other parties, the jury concluded there was no breach of express or implied warranty or breach of contract regarding the “stucco system.” However, the jury concluded there had been negligence by both Henley and Base Camp. The jury found Henley 10 percent and Base Camp 90 percent at fault, and found $7,500 in total damages for negligence in connection with the stucco. The jury found no breach of warranty, breach of contract or negligence with respect to the other aspects of the construction project.

The trial court entered judgment as follows: (1) Meeker to recover from Base Camp $98,531, plus interest from November 6, 2000; (2) Base Camp to recover nothing from Meeker; (3) Henley to recover from Meeker $36,676; and (4) Base Camp to recover from Henley $750.

*462 Meeker filed a motion for indemnity and an award of prevailing party attorney fees. Meeker claimed a right to express and implied indemnity from Henley and a right to prevailing party fees from both Henley and Base Camp. Henley and Base Camp filed opposition. Henley also filed its own motion for prevailing party status.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newborn v. City of L.A. CA2/7
California Court of Appeal, 2026
Volpe Co. v. Sausal Corp. CA1/5
California Court of Appeal, 2026
Kaur v. Pabla CA5
California Court of Appeal, 2024
Mascaro v. Brown CA2/6
California Court of Appeal, 2023
Blackburn v. County of San Diego CA4/1
California Court of Appeal, 2022
Otay Land Co. v. UE Limited CA4/1
California Court of Appeal, 2021
Hart v. Clear Recon Corp.
California Court of Appeal, 2018
Hart v. Clear Recon Corp.
237 Cal. Rptr. 3d 907 (California Court of Appeals, 5th District, 2018)
SER Gabrielle M. v. Hon. David R. Janes, Judge
West Virginia Supreme Court, 2016
Stein v. Dept. of Fish and Wildlife CA3
California Court of Appeal, 2016
Cruz v. City of Culver City
2 Cal. App. 5th 239 (California Court of Appeal, 2016)
Dorsey v. Superior Court
241 Cal. App. 4th 583 (California Court of Appeal, 2015)
Smith v. Calbert Ca1/1
California Court of Appeal, 2015
Son v. Lee CA4/1
California Court of Appeal, 2014
Tutor-Saliba-Perini J v. v. LA Co. MTA CA2/7
California Court of Appeal, 2014
Ponce v. Philco Construction CA4/3
California Court of Appeal, 2014

Cite This Page — Counsel Stack

Bluebook (online)
3 Cal. Rptr. 3d 563, 111 Cal. App. 4th 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-perez-co-v-base-camp-condominiums-assn-no-one-calctapp-2003.