M. McGirr Sons Co. v. Babbitt

61 Misc. 291, 113 N.Y.S. 753
CourtAppellate Terms of the Supreme Court of New York
DecidedDecember 15, 1908
StatusPublished
Cited by2 cases

This text of 61 Misc. 291 (M. McGirr Sons Co. v. Babbitt) is published on Counsel Stack Legal Research, covering Appellate Terms of the Supreme Court of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. McGirr Sons Co. v. Babbitt, 61 Misc. 291, 113 N.Y.S. 753 (N.Y. Ct. App. 1908).

Opinion

Giegericii, J.

The action is to recover the price of a scow load of filling material consisting of ashes, which the plaintiff claimed to have delivered by scow upon the lands of the defendant at'Babbitt, H. J., in the course of the performance of a contract for filling in around its buildings, and for the value of certain work, done in grading such lands after they were filled in, and claimed to have been performed after and in addition to the grading called for by the contract, and for which the plaintiff claims the defendant promised and agreed to pay.

Both claims were disputed, the defendant asserting that it refused to accept the contents of said scow, because it [292]*292was not filling material “ clean and free from rubbish and garbage,” as required by the contract, and that it had, therefore, been rejected, and denying that it promised to pay for such grading, and claiming, furthermore, that it was not extra work, for the reason that the contract provided the plaintiff should “ grade and fill from said buildings in accordance with the grade stakes set by you” (defendant).

It appears from the evidence that, on August 31, 1906, the scow in question landed at the defendant’s dock at Babbitt, IST. J., but there was a sharp conflict of evidence upon the trial as to what its contents were. According to the testimony adduced for the plaintiff, such scow contained 653 cubic yards of ashes, and on top of it there was firewood, consisting of barrels and boxes; while the defendant’s witnesses, on the other hand, gave testimony to the effect that the scow was piled up with all kinds of old furniture, barrels, rubbish, old mattresses, old bedsteads — “ all kinds of stuff ” —'with nothing else except dust, on such rubbish, which, it is claimed, extended down to the deck of the scow, and that there was no filling whatever of any kind in the load.

In support of the ground taken by the plaintiff, as above stated, it called witnesses who testified that the capacity of scows varied; that the one in question held a thousand cubic yards, while some held four hundred and others held twelve or thirteen hundred cubic yards, and that there were 653 cubic yards of ashes upon the scow in question by actual measurement; that no objection was made to the material on the scow except that dust was in it; that no permission was asked of the defendant by the plaintiff’s employees to land the material from the scow, and that the defendant’s employees never refused to let the plaintiff’s men unload the scow, but merely asked what they were going to do with the wood;” furthermore, that the contents of the scow were dumped along the railroad track to put a shoulder on one side of the railroad.”

The evidence adduced on the part of the defendant, on the other hand, tended to show that the scow was piled up with nothing but the sundry wooden material referred to, which reached down to the deck of the scow, which deck [293]*293formed the surface on which the load rested; that there was not any dirt visible; that there was no filling, cinders or ashes of any kind, as called for by the contract, all of which, it is claimed, clearly appears from a photograph which was taken before the scow was unloaded, and was admitted in evidence, and was testified to as being a correct representation of the scow and its contents at the time referred to.

There was further testimony given for the defendant to the effect that the defendant’s engineer told the plaintiff’s superintendent that he would not, under any conditions, accept the contents of the scow, because it contained nothing but rubbish; that he did not measure the contents of the scow, because he would not accept it on account of its not conforming to the requirements of the contract; that, after being told that it was more expensive to tow the scow back to New York than to unload it, he finally permitted the plaintiff to unload its contents along the railroad track, not on the parts of the defendant’s ground specified in the contract, but at least one thousand feet from any of the defendant’s buildings.

The defendant’s engineer in charge of the work testified that there was no rubbish along the railroad track in the way of boxes, bedsteads and furniture, before they unloaded the scow; that he saw the material lying on the ground afterward, and that certain photographs offered in evidence were correct representations of the ground with the material lying on it; that the premises had not changed in appearance since the material referred to had been placed there, except the change of time, rain and weather; that the photographs so offered were a correct representation of the appearance of the premises immediately after said material was removed from such scow in September, 190 6; that the witness was there nearly every day as an engineer in charge; that he knew everything that was- put on the premises, knew of his own knowledge that the pictures were a correct representation of the condition as existing in the month of September, 1906.

The photographs were excluded, upon the plaintiff’s objection, on the grounds, firstly, that it did not appear when they were taken; secondly, that it did not appear that it was [294]*294all material from the scow in suit, and, thirdly, the witness said that he did not take the photographs.

It is conceded by the plaintiff’s counsel that the first objection was met by testimony that the photographs were taken a month or two before the trial; but it is -still urged that the second objection has never been met and that it does not appear anywhere in the testimony that the material and stuff that the defendant photographed was the material and stuff taken from the scow, and that the nearest approach is in answer to the question “ And did you see the material after it was unloaded from the scow and placed along the track? A. I saw the scow when it was partly unloaded,” and in answer to the further question “ Did you see the material lying on the ground ? A. Yes, sir, I did.”

But a reading of the stenographer’s minutes shows that the plaintiff’s counsel is in error, there being, as already' noted above, other testimony of the engineer to which he has failed to call attention. Moreover, the testimony of the engineer is corroborated by that of the defendant’s night watchman, who testified that he saw the scow unloaded; that the material taken from it was old furniture, barrels and boxes, and that it was put on both sides of the railroad track; that he stood there from two o’clock in the afternoon until six o’clock on one day, and again, on the following day, from four until six o’clock; and on cross-examination he testified: They began to unload in the morning and throwed it on both sides of the track. Q. All of it ? A. All of it.” He further testified that on the next day he saw them unload from four o’clock until six o’clock, and that he saw the scow empty.

The third ground of objection was not discussed in the briefs nor urged upon this appeal by the defendant; but, even if it had been, such objection would not have been well taken. Nies v. Broadhead, 75 Hun, 255.

From what has been stated, it is evident that the photographs so excluded should have been admitted, although they were not taken until within a month or two of. the trial (People v. Buddenseick, 103 N. Y. 487-500), because they had a very important bearing upon the question arising [295]*295as" to the contents of the scow, in regard to which, as seen, there was a sharp conflict of evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bane v. Atlantic Coast Line Railroad
88 S.E. 477 (Supreme Court of North Carolina, 1916)
Hughes v. State
126 Tenn. 40 (Tennessee Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
61 Misc. 291, 113 N.Y.S. 753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-mcgirr-sons-co-v-babbitt-nyappterm-1908.