Lytle v. Weber (In Re Weber)

450 B.R. 595, 2011 WL 2649998
CourtUnited States Bankruptcy Court, M.D. Louisiana
DecidedJuly 6, 2011
Docket19-10247
StatusPublished

This text of 450 B.R. 595 (Lytle v. Weber (In Re Weber)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lytle v. Weber (In Re Weber), 450 B.R. 595, 2011 WL 2649998 (La. 2011).

Opinion

MEMORANDUM OPINION

DOUGLAS D. DODD, Bankruptcy Judge.

Plaintiffs Dennis and Ramona Lytle sued debtors Scott and Kimberly Weber for a declaration that the Webers’ debt to the plaintiffs, now the subject of a state court default judgment, is nondischargeable under 11 U.S.C. § 523(a)(2)(A), (a)(4) and (a)(6). This opinion explains the basis for the court’s ruling that the Lytles’ claim of $44,978 against the Webers is nondis-chargeable as to Kim Weber only.

FACTS

The plaintiffs sought to build a comfortable home at a reasonable cost on a lot in *598 the University Club Plantation subdivision in Baton Rouge after moving from Little Rock, Arkansas in late 2007. They hired Lighthouse Construction, L.L.C. (“Lighthouse”), a licensed general contractor owned by Scott Weber and his wife Kim, who is plaintiff Dennis Lytle’s sister. 1 Scott Weber supervised the work; Kim Weber maintained Lighthouse’s books. The construction project took from April 2008 until November or December 2008. The Lytles agreed to pay $379,713 for the project 2 but the price eventually exceeded $457,000. 3

Plaintiffs carefully monitored the project, making notes and photographing the work.' 4 Dennis Lytle testified that he believed Lighthouse was paying for all the work as the project advanced: he said that the debtors assured him that the job was progressing well 5 and that Lighthouse was paying its subcontractors and suppliers timely.

The Lytles paid Lighthouse $306,-770.40 6 before declining to make the final contract payment when they learned of problems that included Lighthouse’s failure to pay subcontractors and material-men. Lytle insisted he would not have made the progress payments had he known of Lighthouse’s breaches.

The evidence established that throughout the project the plaintiffs sought information about Lighthouse’s use of their money. Dennis Lytle testified that he first asked the debtors for an actual accounting, including cancelled checks, as early as May 2008 after the first progress payment. Kim Weber agreed to get the materials together and respond to him. Though Lytle anticipated that the defendants would need time to gather the information, the summer advanced without his receiving anything. In July 2008, Lytle “sternly demanded” financial information from the Webers, who repeatedly put him off. In September 2008, nearly four months after he first asked for information, Kim Weber told Lytle she had prepared a document showing the application of plaintiffs’ progress payments but claimed that Scott Weber had told her not to provide it to Lytle. Again in October 2008 Kim told Dennis that Scott Weber would not let her give the information to Lytle.

Kim Weber finally gave Dennis Lytle a listing of estimated and actual costs for the construction project on November 3, 2008, 7 explaining that Lighthouse had paid the amounts listed in the column captioned “actual.” 8 However, Kim did not furnish *599 any corroboration that Lighthouse actually had made the payments on the list. 9 When Lytle rejected the document as “unacceptable” because it comprised “only numbers” without backup, Kim agreed to provide more information. She also told him that he needed to meet with her and her. husband if he really wanted an explanation of the numbers on the breakdown. Yet when Lytle agreed to meet with the defendants Kim Weber put him off, claiming that Scott was not available at the time. In any case, Lytle testified that the plaintiffs began “to feel really shaky” once they received the November 8, 2008 cost breakdown and began to suspect that the debtors were “concealing something.”

After the home was finished in late November or early December 2008, 10 Kim Weber asked her brother for a check to pay some subcontractors to whom Lighthouse owed money. Dennis Lytle gave her a personal check for $12,145.32, noting in the check’s memorandum section the names of the creditors and the amounts paid for each. 11 Kim Weber explained to her brother that the payment would settle all amounts Lighthouse owed on the project. In fact, Lytle said that Kim told him the amount for Angelle Concrete Group, L.L.C. (“Delta/Angelle”), 12 one of the eon-tractors, actually was to reimburse Lighthouse for payments it already had made to Delta. Lytle conceded that he probably should have asked Lighthouse to obtain a lien waiver from Delta/Angelle but did not because, even though he had some concerns by then, he trusted the Webers to pay the project costs as the contract required.

Later in December 2008, Kim Weber asked Lytle for an additional $27,531.65 to pay Lighthouse’s subcontractors and mate-rialmen; she identified only Central Electric Co., L.L.C. (“Central Electric”) specifically. For a second time Kim told Dennis that the check was the last one Lighthouse needed to satisfy claims associated with the project and that it “would settle everything.” Lytle did not believe that plaintiffs still owed as much as $27, 531.65 on the job and so before he agreed to give Lighthouse the money, Lytle demanded an accounting — for at least the fourth time. Despite that, and notwithstanding (1) Ramona Lytle’s opposition to giving the Weber’s another check, (2) Lytle’s skepticism about the significant balances Weber claimed were due and (3) the defendants’ repeated failure or refusal to deliver an accounting, on December 19, 2008, Lytle gave Weber a check for $16,952.15. 13 Ly-tle never received confirmation that Light *600 house paid the subcontractors and suppliers Kim claimed the December 19 check would cover.

Despite Kim’s assurances, the December 2008 payments did not resolve all claims associated with the home building project. Plaintiffs later learned that Lighthouse had failed to pay several subcontractors and materialmen, including three whose claims the plaintiffs themselves eventually had to resolve: McConnell Brick & Block Company, Inc. (“McConnell”), Delta/An-gelle Concrete, and Central Electric. 14

McConnell Brick

Dennis Lytle called his sister after the Lytles received McConnell’s February 5, 2009 demand letter. She counseled him not to worry about the invoices because the claim was only a lien against his home 15 and that “they” would “take care of it.” However, no evidence established that the Webers or Lighthouse ever paid McConnell.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RecoverEdge L.P. v. Pentecost
44 F.3d 1284 (Fifth Circuit, 1995)
Miller v. J.D. Abrams Inc. (In Re Miller)
156 F.3d 598 (Fifth Circuit, 1998)
Rooker v. Fidelity Trust Co.
263 U.S. 413 (Supreme Court, 1924)
District of Columbia Court of Appeals v. Feldman
460 U.S. 462 (Supreme Court, 1983)
Field v. Mans
516 U.S. 59 (Supreme Court, 1995)
Kawaauhau v. Geiger
523 U.S. 57 (Supreme Court, 1998)
Lewis v. Bank of America NA
343 F.3d 540 (Fifth Circuit, 2003)
Union Planters Bank National Ass'n v. Salih
369 F.3d 457 (Fifth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
450 B.R. 595, 2011 WL 2649998, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lytle-v-weber-in-re-weber-lamb-2011.