Lyons v. Otter Tail Power Co.

280 N.W. 192, 68 N.D. 403, 1938 N.D. LEXIS 124
CourtNorth Dakota Supreme Court
DecidedApril 14, 1938
DocketFile No. 6513.
StatusPublished
Cited by5 cases

This text of 280 N.W. 192 (Lyons v. Otter Tail Power Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyons v. Otter Tail Power Co., 280 N.W. 192, 68 N.D. 403, 1938 N.D. LEXIS 124 (N.D. 1938).

Opinions

Crimson, Dist. J.

In the early summer of 1926 the plaintiff constructed a public garage in the city of Jamestown. He entered into negotiations with the defendant for the extension of its steam heating mains to this new garage. This resulted in a written agreement, dated April 3, 1926, whereby the defendant agreed to extend its heating mains to plaintiff’s garage not later than August 15, 1926 and plaintiff agreed to pay the defendant, The Otter Tail Power Company $976 towards the cost of said extension. The defendant is a public utility engaged in furnishing steam heat, electric light and power, etc., and is subject to the jurisdiction of the board of railroad commissioners of the State of North Dakota, as provided by chapter 192, Session Laws, 1919, and statutes amendatory thereof. This contract, however, was .not submitted to said board and was never approved by it. The defendant proceeded to install the heat mains as provided in the contract, and on August 9, 1926 plaintiff paid defendant $976 in accordance therewith. The total cost of the installation was $4,-101.33. Of that sum another consumer paid $749. Defendants stood the balance.

*405 Thereafter steam heat was furnished by the defendant in accordance with the rates and schedules approved by the railroad commission, and payments therefor made by the plaintiff.

On May 6, 1933 the plaintiff filed a written application with the board of railroad commissioners praying for a return of the sum so paid. A hearing was had thereon June 9, 1934 before the board of railroad commissioners, at which hearing the defendant appeared, and testimony was taken. Thereafter, on December 31, 1934 said board filed its findings of fact, conclusions and order, wherein it directed the defendant to refund and pay to the plaintiff the sum of $976 with interest from August 9, 1926 at six per cent. No appeal was taken from that order, neither did the defendant comply therewith. In July 1935, the plaintiff brought this action to enforce that order. Trial to a jury was had in March 1937. Plaintiff offered in evidence the pleadings before the railroad commission, its findings, conclusions and order and rested his case entirely thereon. The defendant objected thereto, offered evidence as to the schedules, rates and regulations of the board and as a further defense attempted to show that plaintiff had not been damaged, claiming that a private heating plant would have cost him more. The jury returned a verdict for the plaintiff and from the judgment entered thereon and from the order denying a motion for judgment notwithstanding or for a new trial, this appeal is taken.

The defendant, both before the railroad commission and in district court, contended that the board of railroad commissioners had no jurisdiction to make such an order for a money award; that the contract, and payment under it, were voluntary and fully executed; that the statute of limitations had run; and that there are no provisions in our public utility laws for the enforcement of a reparation award for money hy the railroad commission. The same contentions are made on argument here, and further some errors of law at the trial are claimed.

The order of the board of railroad commissioners is based upon § 4609c44, Comp. Laws Supp. 1925, which reads as follows:

“Improper charges; Eeparation. When complaint has been made to the commissioners concerning any rate, fare, toll, rental or charge for any product or commodity furnished or service performed by any *406 public utility and tbe commissioners have found after investigation that the public utility has charged an excessive or discriminatory amount for such product, commodity or service, in excess of the schedules, rales and tariffs on file toilh the commissioners, or has discriminated under said schedules against the complainant, the commissioners may order that the public utility make due reparation to the complainant therefor, with interest from the date of collection; provided, no discrimination will result from such reparation.”

The evidence in district court showed that at the time this contract was consummated and the payments made the railroad commission had established no rules, regulations, schedules, rates, tariffs or orders applicable to the making of extensions or additions to the steam heating mains and distribution system of the defendant company in Jamestown; neither had any provisions with reference to the payment of the cost or capital investment thereof, or the making of contributions by prospective consumers towards such cost been adopted, nor had that been done at any time before the filing of the complaint. An attempt was made to show that such rules, and schedules had been adopted with regard to electric light extensions and that the same bases were to be followed with regard to steam main extensions. No rule or regulation, however, had been adopted by the board to that effect. The parties in the absence of such rules and regulations proceeded to make their own contract by which the plaintiff obtained heating service for his garage building, and in order to induce the defendant to extend its mains so as to make such service possible, he agreed to pay a portion of the cost. The contract was fully performed on both sides.

The board of railroad commissioners possesses only the authority conferred upon it by the constitution and the statutes of the state. All orders made by it must conform with the statutes to be valid. The public utility statute, chapter 192, Session Laws, 1919, and statutes amendatory thereof (Supplement 1925, §§ 4609cl-4609c56) are replete with provisions for hearings upon notice. (See § 4609c5.) Before a schedule can be adopted the interested parties must have had a hearing upon notice. State ex rel. Lemke v. Chicago & N. W. R. Co. 46 N. D. 313, 179 N. W. 378; State ex rel. Hughes v. Milhollan, 50 N. D. 184, 195 N. W. 292; Chrysler Light & P. Co. v. Belfield, 58 *407 N. D. 33, 224 N. W. 871, 63 A.L.R. 1337; State ex rel. Lemke v. Union Light, Heat & P. Co. 47 N. D. 402, 182 N. W. 539.

Since no rule had been adopted applying the regulation for electric light extensions to steam extensions the board had no o authority for such action. To allow the commission to do that without a hearing would be to allow practices condemned in State ex rel. Lemke v. Chicago & N. W. R. Co. 46 N. D. 313, 179 N. W. 378, supra. There may be a great difference in what should be required in connection with steam extensions from what may be required for electric extensions. The nature of the business is different. The consumers of steam heat are probably much less numerous. The cost of construction of an extension for steam heating may be a capital expenditure which, if forced upon the utility and included in the rate base, would be unjust to the other consumers. These are things which might properly be taken into consideration by the board in establishing rules pertaining to steam heat extensions, but in the absence of such rules the board had no jurisdiction to determine retroactively upon what conditions an extension should have been made eleven years ago, when that extension has been made pursuant to a contract between the parties entered into and performed in the absence of rules and regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yeik v. Department of Revenue & Taxation
595 P.2d 965 (Wyoming Supreme Court, 1979)
Great Northern Railway Company v. Thompson
222 F. Supp. 573 (D. North Dakota, 1963)
Williams Electric Cooperative, Inc. v. Montana-Dakota Utilities Co.
79 N.W.2d 508 (North Dakota Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
280 N.W. 192, 68 N.D. 403, 1938 N.D. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyons-v-otter-tail-power-co-nd-1938.