Lyman v. Title Guaranty & Surety Co.

158 P. 423, 48 Utah 230, 1916 Utah LEXIS 21
CourtUtah Supreme Court
DecidedFebruary 11, 1916
DocketNo. 2811
StatusPublished
Cited by5 cases

This text of 158 P. 423 (Lyman v. Title Guaranty & Surety Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyman v. Title Guaranty & Surety Co., 158 P. 423, 48 Utah 230, 1916 Utah LEXIS 21 (Utah 1916).

Opinion

STRAUP, C. J.

This is an action to recover on a surety bond.

The plaintiffs and O’Toole Bros., on the 15th day of September, 1913, entered into a written contract by the terms of which 0 ’Toole Bros, agreed to dig and back-fill all trenches to construct a waterworks system at Cokeville, Wyo., in accordance with certain specifications. The plaintiffs agreed to pay therefor eleven cents per linear foot. O’Toole Bros, agreed to do the work not later than the 25th of November,: 1913, and to pay ten dollars a day for each day thereafter the work remained unfinished. Each causing delays agreed to pay the other’s “force account.’’’ O’Toole Bros, agreed “to dig the trench at the rate of at least one thousand feet (1,000) per day after” the 25th day of September, and “to furnish” the plaintiff “a surety bond in the sum of fifteen hundred dollars ($1,500) satisfactory to” them, guaranteeing the performance of the contract on the part of O’Toole Bros.; the plaintiffs to furnish O’Toole Bros, a surety bond satisfactory to them, in the sum of $1,500, guaranteeing “the payment of the contract price for all trenches dug and back-filled by” O’Toole Bros.

The suit was on the surety bond given by the defendant, guaranteeing the faithful performance by O’Toole Bros, of their contract. In that bond it is recited:

“Whereas, said principal (O’Toole Bros.) has entered into a certain written contract bearing date the 15th day of September, 1913, with said Lyman & Samuels of Salt Lake City for the work in .connection with digging and back-filling all trenches required to complete -the waterworks system at Coke-ville, Wyo., to furnish all of the labor, material, and other things contemplated by said contract, which contract, together with all its terms, covenants, conditions, and stipulations, is incorporated herein and made to form a part hereof as fully as if said contract was recited at length herein; subject nevertheless to' the conditions of this bond:

[234]*234“Now, therefore, the conditions of the foregoing obligation is such that, if the said principal shall well and truly indemnify and save harmless the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants, and conditions of the said contract on the part of the said principal to be performed, then this obligation shall be void; otherwise to remain in full force and effect in law: Provided, however, that this bond is issued subject to the following conditions and provisions:

“First. That no liability shall attach to the surety hereunder unless, in the event of any default on the part of the principal -in the performance of any of the terms, covenants, or conditions of the said contract, the obligee shall promptly and immediately upon knowledge thereof, and in any event not later than 30 days after the occurrence of such default, deliver to the surety at its office in the City of Scranton, Pa., written notice thereof with a statement of the principal facts showing such default and the date thereof; nor unless the said obligee shall deliver written notice to the surety at its office aforesaid, before making to the principal the final payment provided for under the contract herein referred to.
“Second. That, in case of such default on the part of the principal, the surety shall have the right, if it so desires, to assume and complete or procure the completion of said contract and, in case of such default, the surety shall be sub-rogated and entitled to all.the rights and properties of the principal arising out of the said contract and otherwise, including all securities and indemnities theretofore received by the obligee and all deferred payments, retained percentages, and credits due to the principal at the time of such default, or to become due thereafter by the terms and stipulations of the contract.
“Third. That in no event shall the surety be liable for a greater sum than the penalty of this bond, or subject to any suit, action, or other proceedings thereon that is instituted later than six months from the date stipulated in said contract for its completion.
“Fourth. That the said-obligee shall retain the last payment and reserve due said principal until the complete per[235]*235formance by said principal of all the terms, covenants, conditions, and stipulations of the contract on said principal’s part to be performed and until the expiration of the time within which liens or notice of liens may be filed, by reason of anything done in or towards the performance of said contract, and until the cancellation and discharge of such liens if any.”

In the complaint it is alleged that, in pursuance of the contract entered into between the plaintiffs and O’Toole Bros., the latter entered upon the performance of the work and continued with the same until about two-thirds of the work had been completed when they, without cause, and against the consent of the plaintiffs, abandoned the work and refused to continue with it; and that the defendant, with notice thereof, refused to complete the work, whereupon the plaintiffs themselves completed it. The suit is to recover the reasonable cost for such completion.

The defendant, answering, admitted the execution of the contract and the bond, but alleged that the plaintiffs had failed to give the surety bond to O’Toole Bros, called for by their contract, by reason of which it is alleged that contract and the bond became inoperative-, that the plaintiffs, without the knowledge or consent of the defendant, extended the time ten days to complete the work; that the defendant was not notified of any default on behalf of O’Toole Bros., until the 6th of January,' 1914, and that, if any default occurred, it was more than thirty days prior to the giving of any notice to the defendant; that the plaintiffs, without notice to the defendant, and in violation of the terms of the bond “made final payment of said contract to” O’Toole Bros.; and that the plaintiffs did not, as provided by the bond, bring their action within six months of the default.

The case was tried to the court who found:

“That soon after the execution of said contract (between plaintiffs and O’Toole Bros.) said O’Toole Bros, entered upon the performance thereof and performed a portion of the work agreed to be done by them, and on the 9th day of December, 1913, without just cause or excuse, without the consent and against the will of the plaintiffs, the said 0 ’Toole [236]*236Bros, quit work and failed, neglected and refused to do further work under said contract.
“That on December 30, 1913, the plaintiffs gave written notice to the defendant company of the fact that said 0 ’Toole Bros, had quit work under said contract and had refused to proceed with the work according to the terms thereof, and had abandoned said contract. That the plaintiffs in said notice and as a part thereof requested the defendant company to proceed to complete the said trench-digging and back-filling remaining unperformed by the said 0 ’Toole Bros, and then uncompleted by reason of .the default of the said 0 ’Toole Bros.; but the said defendant company, after the receipt of said notice, and on the 5th day of January, 1914, refused and still refuses to complete said work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utah State Building Board v. Walsh Plumbing Company
399 P.2d 141 (Utah Supreme Court, 1965)
Maule Industries, Inc. v. Gaines Construction Co.
157 So. 2d 835 (District Court of Appeal of Florida, 1963)
United States Plywood Corp. v. Continental Casualty Co.
157 A.2d 286 (District of Columbia Court of Appeals, 1960)
Shaw v. New Amsterdam Casualty Co.
164 A. 916 (Supreme Court of Pennsylvania, 1932)
Andes Co-Operative Dairy Co. v. Commercial Casualty Insurance
207 A.D. 102 (Appellate Division of the Supreme Court of New York, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
158 P. 423, 48 Utah 230, 1916 Utah LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyman-v-title-guaranty-surety-co-utah-1916.