Luntz Corp. v. Pub. Util. Comm.

1997 Ohio 342, 79 Ohio St. 3d 509
CourtOhio Supreme Court
DecidedOctober 1, 1997
Docket1996-0962
StatusPublished
Cited by1 cases

This text of 1997 Ohio 342 (Luntz Corp. v. Pub. Util. Comm.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luntz Corp. v. Pub. Util. Comm., 1997 Ohio 342, 79 Ohio St. 3d 509 (Ohio 1997).

Opinion

[This opinion has been published in Ohio Official Reports at 79 Ohio St.3d 509.]

LUNTZ CORPORATION, APPELLANT, v. PUBLIC UTILITIES COMMISSION OF OHIO ET AL., APPELLEES. [Cite as Luntz Corp. v. Pub. Util. Comm., 1997-Ohio-342.] Public Utilities Commission—Electric utility has no affirmative duty or obligation to conduct an ongoing review of every customer’s usage and load-demand levels to ensure that every customer is being served under the most economical tariff possible—“Distribution line” in R.C. 4933.81, construed. (No. 96-962—Submitted June 11, 1997—Decided October 1, 1997.) APPEAL from the Public Utilities Commission of Ohio, No. 94-1783-EL-CSS. __________________ {¶ 1} This appeal involves an order by the Public Utilities Commission of Ohio in a complaint case brought by Luntz Corporation (“Luntz”) against Ohio Edison Company for failing to disclose possible alternate rates under which Luntz might have been served from 1980 through 1991. {¶ 2} Luntz is a family-run business that buys, processes and brokers scrap metal and sells it to steel mills and foundries. Luntz has facilities located in several Ohio cities, including Warren. Ohio Edison has provided electric service to Luntz’s Warren facility under a number of different tariffs since the mid-1970s. {¶ 3} In 1981, Luntz contacted Ohio Edison about securing an adequate electric supply for a new hydraulic shear. The shear used hydraulic pistons to power a guillotine-like blade to cut metal that did not fit into Luntz’s automobile shredder. Ohio Edison analyzed the electric demands and determined that the most economical way both to provide the necessary electric capacity to Luntz for the new shear and to avoid electrical interference to other customers near Luntz’s facility was for Luntz to construct a new substation and take service at the 23 kV transmission voltage. After Luntz installed the substation and began taking service SUPREME COURT OF OHIO

at 23 kV, the flicker problem at a nearby restaurant was virtually eliminated (a voltage fluctuation was detectable with an ammeter, but no flicker could be visually observed). {¶ 4} In 1991, Luntz hired a consultant to audit Luntz’s electric bills and to help Luntz reduce its power costs. Shortly thereafter, Luntz contacted Ohio Edison with questions regarding Luntz’s electric-load demand. Ohio Edison met with Luntz, provided Luntz with billing and usage information and power factor information, and ultimately reinstalled a magnetic tape meter at Luntz’s request in mid-1991. {¶ 5} On November 4, 1994, pursuant to R.C. 4905.26, Luntz filed a complaint with the commission against Ohio Edison alleging that Ohio Edison had (1) erroneously and negligently advised Luntz that it was required to construct a substation and to enter into a new contract for electric service at Luntz’s Warren facility in order to increase the capacity at that facility and (2) concealed and misrepresented, from February 1980 to September 1991, the availability of tariffs that were less costly than the tariff under which Luntz was actually being served. Luntz raised no tariff-related issues regarding Ohio Edison’s service before 1980 or after 1991. {¶ 6} Luntz also alleged that Ohio Edison had wrongfully removed the magnetic tape meter from Luntz’s facility in 1986, which prevented Luntz from monitoring its power factor and on-peak/off-peak electrical demands, and prevented Luntz from receiving an off-peak discount. {¶ 7} Ohio Edison filed an answer to the complaint, denying the substance of the complaint, setting forth various affirmative defenses, and asking that the complaint be dismissed. An attorney examiner found that the complaint stated a claim cognizable under R.C. 4905.26, and scheduled the matter for a hearing. The case went to hearing in June 1995. Rebuttal testimony was heard in August 1995.

2 January Term, 1997

{¶ 8} The commission found that Luntz had failed to meet its burden of proof. Luntz timely sought rehearing. However, thirteen days later, Luntz filed an amended application for rehearing and a request for oral argument, raising new issues not addressed in Luntz’s original application for rehearing. The commission disregarded the amended application for rehearing because it was filed beyond the thirty-day period required in R.C. 4903.13, and denied the claims raised in the application for rehearing. {¶ 9} The cause is now before this court upon an appeal as of right. __________________ Steve J. Edwards, for appellant. Betty D. Montgomery, Attorney General, Duane W. Luckey and Johnlander Jackson-Forbes, Assistant Attorneys General, for appellee, Public Utilities Commission of Ohio. James W. Burk; Roetzel & Andress Co., L.P.A., and George W. Rooney, Jr., for intervening appellee, Ohio Edison Company. __________________ Per Curiam. {¶ 10} Appellant poses eight propositions of law, nearly all of which ask us to reweigh the evidence of record. For the reasons that follow, we decline to do so and affirm the order of the commission below.1 {¶ 11} We will not reverse a commission order unless it is against the manifest weight of the evidence. R.C. 4903.13. Nor will we reweigh evidence or substitute our judgment for that of the commission on factual questions where there is sufficient probative evidence in the record to show that the commission’s decision is not manifestly against the weight of the evidence and is not so clearly

1. Luntz incorrectly named Ohio Edison as the appellee in its notice of appeal in this case. However, an incorrect caption is not a jurisdictional defect under R.C. 4903.13. Consol. Rail Corp. v. Pub. Util. Comm. (1988), 40 Ohio St.3d 252, 533 N.E.2d 317.

3 SUPREME COURT OF OHIO

unsupported by the record as to show misapprehension, mistake, or willful disregard of duty. Time Warner AxS v. Pub. Util. Comm. (1996), 75 Ohio St.3d 229, 233, 661 N.E.2d 1097, 1101; Canton Storage & Transfer Co. v. Pub Util. Comm. (1995), 72 Ohio St.3d 1, 4, 647 N.E.2d 136, 140; Indus. Energy Consumers of Ohio Power Co. v. Pub. Util. Comm. (1994), 68 Ohio St.3d 547, 554, 629 N.E.2d 414, 420. However, we have complete and independent power of review as to all questions of law. Id.; Indus. Energy Consumers of Ohio Power Co. v. Pub. Util. Comm. (1994), 68 Ohio St.3d 559, 563, 629 N.E.2d 423, 426. {¶ 12} The instant appeal is based almost entirely upon factual arguments. The commission’s decisions on these issues are all amply supported by record evidence and are not subject to reversal on that basis. Id. {¶ 13} Luntz raises only two issues that could be considered questions of law: (1) whether Ohio Edison had a duty to inform Luntz of alternate rates and (2) whether the definition of the term “distribution line” in R.C. 4933.81 controls in the case at bar. For the reasons that follow, we affirm the commission’s decision on each of these issues. {¶ 14} The commission has considered alternate-rate arguments similar to those now posed by Luntz, and established a positive-inquiry standard regarding the availability of alternate customer rates. White Plastics Co., Inc. v. Columbus & S. Ohio Elec. Co. (Sept. 25, 1984), Pub. Util. Comm. No. 83-650-EL-CSS, unreported. Under White Plastics and its progeny a utility has a duty “upon inquiry, to inform the customer about the existence and availability of an alternate rate. However, it is not a requirement that a utility itself initiate regular reviews of a customer’s bills in order to determine if an alternate rate is more advantageous. It is upon the inquiry of the customer that a company has a duty to disclose the availability of alternate rate schedules.” (Emphasis added.) N. Hill Marble v. Ohio Edison Co. (Feb. 5, 1985), Pub. Util. Comm. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FirstEnergy Corp. v. Pub. Util. Comm.
2002 Ohio 2430 (Ohio Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Ohio 342, 79 Ohio St. 3d 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luntz-corp-v-pub-util-comm-ohio-1997.