Lumpkin v. DEVENTER NORTH AMERICA, INC.

672 S.E.2d 405, 295 Ga. App. 312, 2008 Fulton County D. Rep. 3932, 2008 Ga. App. LEXIS 1338
CourtCourt of Appeals of Georgia
DecidedNovember 26, 2008
DocketA08A1263
StatusPublished
Cited by11 cases

This text of 672 S.E.2d 405 (Lumpkin v. DEVENTER NORTH AMERICA, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lumpkin v. DEVENTER NORTH AMERICA, INC., 672 S.E.2d 405, 295 Ga. App. 312, 2008 Fulton County D. Rep. 3932, 2008 Ga. App. LEXIS 1338 (Ga. Ct. App. 2008).

Opinions

Phipps, Judge.

Deventer North America, Inc. (Deventer) and Julia Lumpkin entered into a contract for Lumpkin’s purchase of a house being renovated by Deventer. Before the house was finished, however, Lumpkin ordered Deventer to stop work and contracted with someone else to complete construction. Deventer later invoiced Lumpkin for work performed, but Lumpkin refused to pay.

Deventer then brought this suit charging Lumpkin with, among other things, breach of contract and fraud. Lumpkin, in turn, filed a counterclaim charging Deventer and its owner, Wesley Godwin, with breach of contract and fraud. Both Deventer and Lumpkin also sought attorney fees based on allegations of bad faith in their dealings with one another. Finding no evidence of fraud by either Lumpkin, Deventer or Godwin, the trial court directed a verdict against both Lumpkin and Deventer on their fraud claims, even though neither Deventer nor Godwin had moved for a directed verdict on Lumpkin’s claim of fraud. The jury returned a verdict awarding Deventer $170,000 on its breach of contract claim and $128,182.47 on its attorney fee claim and awarding Lumpkin nothing on her counterclaim. After the court’s entry of judgment on the verdict, Lumpkin moved for a judgment notwithstanding the verdict or for a new trial on her claim of fraud against Deventer and Godwin. Following the court’s denial of those post-trial motions, Lumpkin filed a notice of appeal from the judgment entered against her in favor of both Deventer and Godwin. For reasons that follow, we find that the trial court erred in directing a verdict in favor of Deventer and Godwin on Lumpkin’s fraud claim and, therefore, reverse.

Evidence introduced at trial showed that after Deventer had acquired the residential property and begun to renovate it, Lumpkin came to the construction site, met with Godwin, and expressed an interest in purchasing the house. Godwin told Lumpkin that the house, as renovated in accordance with existing construction drawings and specifications, would cost $1.1 million, but that any major changes or alterations would have to be “priced out,” i.e., would increase the price. Godwin and Lumpkin verbally agreed that she would disburse about $250,000 to help defray expenses for certain aspects of the renovation of the house and that she would thereby acquire an option either to buy the house or, upon sale of the house to someone else, be reimbursed for the funds she had provided. Throughout the construction process, Lumpkin dealt with Godwin or with Deventer’s project supervisor, Eric Busbee. Undisputably, Lumpkin requested a number of major changes and alterations to [313]*313the original plans.

Lumpkin testified that she disbursed monies to Deventer between July and November 2001, during which time there was a flurry of construction activity, but that afterward, through no fault of her own, construction work came to a virtual standstill. As a result, she asked Randy Lomax, a friend of hers and an attorney, to contact Godwin.

Although Lumpkin had concerns about numerous construction defects such as roof leaks that would require repairs, she and Deventer entered into a written contract dated December 31, 2001, with special stipulations for Deventer’s sale of the house to her. The contract reflected a sales price of $1,440,000, which included over $250,000 already paid by Lumpkin to contractors, about $680,000 to pay off a first mortgage on the property, and $365,849 due to Deventer upon completion. Special stipulations required Deventer to complete construction of the residence and obtain a certificate of occupancy on or before March 15, 2002. Lumpkin was also required to disburse over $100,000 to subcontractors and materialmen before construction was completed. Because of Lumpkin’s concerns about construction defects, one of the special stipulations provided for a pre-closing walk-through of the property by the parties. Lumpkin testified that she agreed to purchase the house despite her concerns because of assurances by Godwin that the defects would be cured.

On February 5, 2002, however, Godwin wrote Lomax a letter declaring the contractually-agreed completion date, that had been extended from March 15 until March 19 due to inclement weather, invalidated by Deventer’s inability to obtain a certificate of occupancy due to Lumpkin’s failure to respond, communicate, or make necessary decisions. At or about that time, Godwin also sent Lomax a list of outstanding balances totaling about $176,000 owed by Lumpkin to Deventer on various accounts of subcontractors, suppliers, and employees.

Lumpkin testified that shortly thereafter, she went to the house during a heavy rain and observed water gushing into the kitchen and damaging sheet rock. According to Lumpkin, Busbee met her at the house and informed her that they were not going to make any repairs. At that point, she decided to have another contractor, Phillip Carter, inspect the house. Therefore, on February 13, Lomax instructed Godwin to stop work temporarily. By faxes, Godwin responded to Lomax that, as a result of the stop-work order, Deventer would not be able to fulfill financial obligations to laborers, suppliers, and subcontractors; that additional, resultant costs would be charged to Lumpkin; and that the building permit that had been issued to him should be reissued to Lumpkin because laborers and subcontractors hired by her were assuming control of the project. On [314]*314February 22, Godwin sent Lomax an invoice for $196,500 for work completed as of that date.

Carter, who Lumpkin hired to inspect the house, testified that “we didn’t know what all we were going to find [until] we tore things out.” A roofing contractor who inspected the roof at Carter’s request testified to numerous construction defects requiring removal and replacement of the roof. A structural engineer testified that reinforcement of the top floor was required to avert a possible extreme catastrophic failure of the floor. Another contractor testified that due to various inadequacies, the entire heating and air conditioning systems had to be replaced. Other contractors testified to other construction defects requiring numerous repairs. Lumpkin claims that she spent about $650,000 to complete construction, which included about $350,000 to repair defects.

1. Lumpkin contends that the trial court erred in sua sponte directing a verdict in favor of Deventer and Godwin on her claim of fraud.

To support her claim of fraud, Lumpkin was generally required to show: “(1) a false representation or concealment of material fact; (2) scienter; (3) intent to induce the allegedly defrauded party to act or refrain from acting; (4) justifiable reliance; and (5) damages.”1

The general rule is that actionable fraud cannot be predicated upon promises to perform some act in the future. Nor does actionable fraud result from a mere failure to perform promises made. Otherwise, any breach of a contract would amount to fraud. An exception to the general rule exists where a promise as to future events is made with a present intent not to perform or where the promisor knows that the future event will not take place.2

“A promise made without a present intent to perform is a misrepresentation of a material fact and is sufficient to support a cause of action for fraud.”3

Moreover,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bigsby v. Barclays Capital Real Estate, Inc.
298 F. Supp. 3d 708 (S.D. Illinois, 2018)
Michael Dolan v. Air Mechanix, LLC
803 S.E.2d 104 (Court of Appeals of Georgia, 2017)
Dean Prainito v. Michael Smith
Court of Appeals of Georgia, 2012
Prainito v. Smith
728 S.E.2d 309 (Court of Appeals of Georgia, 2012)
Strader v. Palladian Enterprises, LLC
719 S.E.2d 541 (Court of Appeals of Georgia, 2011)
Esprit Log & Timber Frame Homes, Inc. v. Wilcox
691 S.E.2d 344 (Court of Appeals of Georgia, 2010)
Lumpkin v. DEVENTER NORTH AMERICA, INC.
672 S.E.2d 405 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
672 S.E.2d 405, 295 Ga. App. 312, 2008 Fulton County D. Rep. 3932, 2008 Ga. App. LEXIS 1338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lumpkin-v-deventer-north-america-inc-gactapp-2008.