Luebke v. City of Watertown

284 N.W. 519, 230 Wis. 512, 1939 Wisc. LEXIS 100
CourtWisconsin Supreme Court
DecidedMarch 7, 1939
StatusPublished
Cited by7 cases

This text of 284 N.W. 519 (Luebke v. City of Watertown) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luebke v. City of Watertown, 284 N.W. 519, 230 Wis. 512, 1939 Wisc. LEXIS 100 (Wis. 1939).

Opinion

Fowler, J.

Upon the complaint and an affidavit of the plaintiff, the plaintiff procured from a court commissioner an order requiring the defendants to1 show cause before the circuit judge why they “should not be permanently restrained and enjoined from entering into the contract referred to in said complaint,” and restraining them from “entering into a contract with the Oliver Construction Company, or any other person, for the construction of the sewers referred to in the complaint” until the further order of the court. No answer was made to the complaint. No demurrer to it was interposed. At the time set for the hearing the city clerk filed an affidavit at the end of which he prayed for an order permitting the defendants to enter into- a contract for the construction of the sewers. A hearing on these motions was had, and without the introduction of any evidence, findings of fact were made by the court, and judgment was entered thereon dismissing the complaint upon the merits and dissolving the restraining order issued by the court commissioner. The plaintiff has appealed from the judgment.

The practice above stated is entirely without precedent. Findings are only made upon the issues made by the com[515]*515plaint and answer upon the evidence produced upon trial to the court. Judgments on the merits are only entered upon findings so made, upon rulings on demurrer when pleading over is not served, upon a motion for judgment on the pleadings, upon an agreed case pursuant tO' sec. 269.01, Stats., or upon the consent of the party against whom the judgment runs. Why the court did not follow one of these courses in the instant case we do not know. Doubtless we might properly reverse the judgment upon the record made. But as the plaintiff asked for a “permanent injunction” on the showing made on return to the order to show cause and the defendants made no- objection to that course, but asked that they be permitted to- proceed with the construction of the sewer, we conclude to treat this as an agreement by the parties to submit the case for final decision upon the facts appearing from the complaint and the affidavits presented on the return to the order to show cause, which are entirely without dispute.

The plaintiff in asking for a “permanent injunction” asked for a final judgment. This cannot be treated as a request for a final judgment if the court should decide in his favor, but not as for such judgment if the court should decide against him. It must be considered as a motion for a final judgment in the case, whether for or against the plaintiff. As the plaintiff asked for a final judgment on the complaint and the showing that should be made pursuant to the order to show cause, and the defendants asked that they might be permitted to proceed with the construction of the sewer upon the complaint and their showing, we conclude to treat this as an agreement by the parties to submit the case upon the facts appearing from the complaint and the affidavits presented on the return to- the order to show cause. This makes in effect an agreed case finder the statute cited, which provides that even without any complaint the parties [516]*516“to a controversy which might be the subject of a civil action, may agree upon a verified case containing the facts upon which the controversy depends and submit the same to any court which would have jurisdiction if an action were brought,” and judgment may be entered thereon.

The complaint states that the city authorities in due form took the preliminary steps for constructing certain sewers and properly advertised for bids for constructing them, and that the lowest .bidder was the “Oliver Construction Company.” The only ground laid for enjoining the letting of the contract was that the Oliver Construction Company did not accompany its bid with a contract and bond as required by sec. 62.15, Stats. Sub. (2) of that statute requires that “when work is required . . . to be let to the lowest responsible bidder . . . (the board of public works) shall prepare ... a form of contract and bond with sureties as required.” Sub. (3) requires “no bid shall be received unless accompanied by a contract and bond with sureties, as prescribed by the form furnished, completed with the exception of the signatures on the part of the city.”

To the affidavits submitted on the return day are attached copies of the proceedings precedent to the opening of the bids which show that the statutory proceedings were literally complied with in every respect except that instead of a form of “contract and bond” as provided in sub. (2) above stated, no bond was prepared by the board of public works, and no bond accompanied the bid of the Oliver Construction Company, but instead the form of contract prepared by the board provided for the bondsman signing the contract itself as a party thereto. The bid of the Oliver Construction Company was accompanied by a contract in form as prepared by the board of public works signed by “M. Oliver,” and by the Central Indemnity Company as surety. It further appears from the affidavits presented by the defendants that Michael Oliver is a sole trader engaged in general construction work [517]*517doing business under the name of Oliver Construction Company; that the city authorities knew of this fact; that he signed his business contracts as “Oliver Construction Co.,” “M. Oliver,” “Mike Oliver,” or “Michael Oliver.” That the bid was signed “Oliver Construction Co.;” that the name “Mike Oliver” appears at the commencement of the signed contract submitted with his bid, and that the city authorities all knew that “M. Oliver,” “Mike Oliver,” and the “Oliver Construction Co.” designated the same person.

The plaintiff urges that the proceeding did not authorize the letting of the contract because there is no such entity as the Oliver Construction Company, and the signature to the bid was therefore ineffectual. Also that the variances in the contract between “Mike Oliver” at the head and the signature “M. Oliver” voids the contract. A person may bind himself to a contract by any name which he may wish to adopt providing he uses it as a substitute for his own name. Jewett v. Whalen, 11 Wis. *124; First State Bank v. Cox, 192 Wis. 566, 213 N. W. 290. A person may bind himself by using his trade name. Sec. 116.22, Stats.; 19 R. C. L. p. 1333, § 11.

That the board of public works in preparing the instruments which the bidder was to sign combined the obligations of the contractor and his surety in a single instrument instead of two is immaterial. Fidelity & D. Co. v. Milwaukee-Western F. Co. 191 Wis. 499, 503, 210 N. W. 713. So far as we can discover all obligations of the surety that under the letter of the statute should have been incorporated in a separate bond obligating him as surety for performance of the contract, were assumed by him in signing the contract as a party thereto. This was a substantial compliance with sec. 62.15, Stats.

It is contended that by not giving a separate bond sec. 289.16, Stats., was evaded and the right to contract voided. That section provides that contracts for public work shall [518]*518require the contractor to pay all claims for labor performed and material furnished upon and in the work, and that a bond shall be given, with penalty equal to the contract price, obligating the surety to make such payment. But the contract signed by both the contractor and the surety contains a provision that the party of the first part shall pay and that the party of the second part is surety for the payment of all claims “as required by sec. 289.16,” Stats.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrews Construction, Inc. v. Town of Levis
2006 WI App 180 (Court of Appeals of Wisconsin, 2006)
Doyle v. Jorgensen
414 P.2d 707 (Nevada Supreme Court, 1966)
Mueller v. American Indemnity Co.
120 N.W.2d 89 (Wisconsin Supreme Court, 1963)
Fidelity and Deposit Co. of Maryland v. Bodenstedt
104 N.W.2d 292 (Nebraska Supreme Court, 1960)
Nielsen v. City of St. Paul
88 N.W.2d 853 (Supreme Court of Minnesota, 1958)
In Re Davis Bros. Stone Co.
14 N.W.2d 870 (Wisconsin Supreme Court, 1944)
Angers v. Sabatinelli
1 N.W.2d 765 (Wisconsin Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
284 N.W. 519, 230 Wis. 512, 1939 Wisc. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luebke-v-city-of-watertown-wis-1939.