Andrews Construction, Inc. v. Town of Levis

2006 WI App 180, 722 N.W.2d 389, 296 Wis. 2d 89, 2006 Wisc. App. LEXIS 694
CourtCourt of Appeals of Wisconsin
DecidedAugust 3, 2006
Docket2004AP3338
StatusPublished
Cited by2 cases

This text of 2006 WI App 180 (Andrews Construction, Inc. v. Town of Levis) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrews Construction, Inc. v. Town of Levis, 2006 WI App 180, 722 N.W.2d 389, 296 Wis. 2d 89, 2006 Wisc. App. LEXIS 694 (Wis. Ct. App. 2006).

Opinion

LUNDSTEN, P.J.

¶ 1. This case involves a bid proposal on a municipal road construction project for the Town of Levis. The issue presented is whether Andrews Construction's proposal complied with the statutory requirement that its bid proposal include a sworn statement that it "examined and carefully prepared the proposal from the plans and specifications and has checked the same in detail before submitting the proposal or bid to the municipality." 1 *91 Wis. Stat. § 66.0901(7) (2003-04). 2 Andrews argues that its bid proposal "substantially" complied with this statute because the proposed work listed in the bid proposal effectively communicates the assurances required by the statute. We disagree and, consequently, affirm the circuit court's summary judgment order dismissing Andrews' breach of contract claim against the Town of Levis.

Background

¶ 2. The Town of Levis published a bid notice for a road construction project. Andrews Construction submitted a bid proposal providing some details as to the work it would perform, but not including a sworn statement of the sort described in Wis. Stat. § 66.0901(7). The Town Board accepted Andrews' proposal.

¶ 3. About one week later, a county highway department official called Andrews Construction and informed Andrews that its bid proposal was not acceptable because the proposal did not include "bid and performance bonds." Andrews also received a letter from the Town stating that Andrews' bid proposal was not acceptable and that the Town was going to re-bid the project. After new bids were submitted, the contract was awarded to a different company.

¶ 4. Andrews Construction filed suit against the Town seeking damages for lost profits based on the Town's alleged breach of contract. The Town moved for summary judgment. The circuit court granted that motion, dismissing Andrews Construction's claim. Andrews appealed.

*92 ¶ 5. The parties' initial briefing on appeal focused on several issues, but not on whether Andrews Con struction complied with Wis. Stat. § 66.0901(7). At our direction, the parties submitted supplemental briefs addressing whether Andrews Construction's bid proposal complied with § 66.0901(7).

Discussion

¶ 6. We review summary judgment decisions de novo, applying the same method as the circuit court. Green Spring Farms v. Kersten, 136 Wis. 2d 304, 315-17, 401 N.W.2d 816 (1987). That method is well established and need not be repeated here.

¶ 7. The content of Andrews Construction's bid proposal is undisputed. It contains a brief description of the work Andrews was offering to perform and the amount Andrews would charge for that work. It is also undisputed that Andrews Construction did not submit with its bid proposal a statement of any kind containing assurances of the type required by Wis. Stat. § 66.0901(7).

¶ 8. Wisconsin Stat. § 66.0901(7) imposes a bidder's certificate requirement on bid proposals for public contracts. That statute provides that "the bidder shall incorporate and make a part of the bidder's proposal... a sworn statement by the bidder . . . that the bidder. . . has examined and carefully prepared the proposal from the [municipality's] plans and specifications and has checked the same in detail before submitting the proposal or bid to the municipality." 3

*93 ¶ 9. The parties agree that Wis. Stat. § 66.0901(7) applies to Andrews Construction's bid proposal. And Andrews does not challenge the Town's reliance on Bechthold v. City of Wauwatosa, 228 Wis. 544, 560, 280 N.W. 320 (1938) (on rehearing), for the proposition that the Town had no power to enter into a contract with Andrews unless Andrews' bid proposal complied with §66.0901(7). See Bechthold, 228 Wis. at 562 ("[A] municipality has no power to make contracts for public improvements unless it proceeds in the manner prescribed by law, and ... a contract entered into without complying with the charter provisions is void."). Thus, if Andrews' bid proposal did not comply with § 66.0901(7), the contract between the Town and Andrews is void.

¶ 10. Andrews Construction admits that it did not submit a bidder's certificate, but relies on the doctrine of substantial compliance. Andrews argues that its bid proposal substantially complied with Wis. Stat. § 66.0901(7) because the contents of its proposal show that Andrews checked the specifications and carefully prepared its proposal to match them. Andrews argues that a review of the bid notice when compared with Andrews' bid proposal "does indicate that the signed bid does reflect the project's specifications as set forth in the bid notice." We reject Andrews' argument.

¶ 11. The doctrine of substantial compliance "contemplates 'actual compliance in respect to the substance essential to every reasonable objective of the statute.'" *94 Midwest Mut. Ins. Co. v. Nicolazzi, 138 Wis. 2d 192, 200, 405 N.W.2d 732 (Ct. App. 1987) (citation omitted). Thus, the Andrews bid proposal complies with Wis. Stat. § 66.0901(7) only if it complies with the statute's objectives. It does not.

¶ 12. Andrews did not submit any statement that arguably makes the assurances required by Wis. Stat. § 66.0901(7). For example, Andrews' bid proposal included no statement regarding its "checking" of plans and specifications. Thus, there was complete noncompliance with the statutory requirement that bids be accompanied by a bidder's certificate.

¶ 13. Moreover, even if Andrews Construction's bid proposal perfectly tracked all bid specifications, the bidder's certificate statute requires more. That statute requires a statement with an assurance from an identifiable person that all "plans and specifications" were checked, and that the bid proposal was examined before the proposal was submitted. Wis. Stat. § 66.0901(7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cheryl M. Sorenson v. Richard A. Batchelder
2016 WI 34 (Wisconsin Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2006 WI App 180, 722 N.W.2d 389, 296 Wis. 2d 89, 2006 Wisc. App. LEXIS 694, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrews-construction-inc-v-town-of-levis-wisctapp-2006.