Luco Land Development, Inc. v. William Ryan Homes, Inc.

2020 IL App (2d) 190156-U
Appellate Court of Illinois·Decided February 6, 2020·No. 2-19-0156·Unpublished

Opinion

No. 2-19-0156

Order filed February 6, 2020

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

LUCO LAND DEVELOPMENT, INC., ) Appeal from the Circuit Court ) of McHenry County.

Plaintiff-Appellant, )

)

v. ) No. 15-MR-39 )

WILLIAM RYAN HOMES, INC., ) Honorable ) Thomas A. Meyer,

Defendant-Appellee. ) Judge, Presiding.

JUSTICE JORGENSEN delivered the judgment of the court.

Justices Hudson and Bridges concurred in the judgment.

ORDER

¶1 Held: The trial court properly entered judgment in defendant’s favor. Affirmed.

¶2 Plaintiff, Luco Land Development, Inc. (Luco), an excavation contractor, sued defendant, William Ryan Homes, Inc. (WRH), a home builder, seeking a declaratory judgment that the parties’ master subcontractor agreement was invalid and unenforceable and alleging, in the alternative, breach of contract and quantum meruit. After a bench trial, the trial court ruled in defendant’s favor and denied Luco’s motion to reconsider. It subsequently entered a finding under Illinois Supreme Court Rule 304(a) (eff. Mar. 8, 2016). Luco appeals, arguing that the trial court erred in: (1) making certain findings on Luco’s breach-of-contract claim; (2) admitting evidence

concerning WRH’s provision of insurance coverage; (3) considering unadmitted evidence and (4) finding that a contractual addendum was renewed. We affirm.

¶3 I. BACKGROUND

¶4 On January 16, 2015, Luco sued WRH. In a second amended complaint, filed on August 27, 2015, Luco: (1) sought a declaratory judgment finding that the parties’ master subcontractor agreement, executed on May 14, 2011, was invalid and unenforceable, because it was missing exhibits referenced in the agreement and, thus, there was no meeting of the minds (count I); (2) sought a declaratory judgment striking the arbitration and limitations provisions of the master subcontractor agreement (count II); (3) alleged breach of contract based on WRH’s alleged issuance of duplicate reversals of payment, failure to make certain payments, improper issuance of charge-backs, and improper deduction of 2.6% of payments to Luco for its insurance program (count III); and (4) sought recovery for quantum meruit, alleging that, if the contract was invalid, Luco was entitled to payment based on the same theories as breach of contract.

¶5 In its answer, WRH denied the allegations and alleged affirmative defenses based on contractual limitations, set-off, unclean hands, breach of contract, and waiver.

¶6 A. Contracts

¶7 On December 9, 2009, the parties executed a master subcontractor agreement and an “OCIP Addendum to the Master Subcontractor Agreement; General Liability Owner Consolidated Insurance Program” (OCIP addendum). Under the OCIP addendum, the parties agreed that WRH would obtain commercial general liability insurance for Luco in exchange for a 2.6% deduction from its payments to Luco.

¶8 On May 14, 2011, the parties executed an updated master subcontractor agreement. The 2011 agreement did not expressly incorporate the OCIP addendum. However, WRH’s payments to Luco continued to incorporate a 2.6% deduction for insurance coverage.

¶9 The parties terminated their relationship in 2014.

¶ 10 B. Luco’s Complaint

¶ 11 In count I, Luco sought a declaratory judgment (735 ILCS 5/2-701 (West 2018)) that the 2011 master subcontractor agreement was void and unenforceable because several exhibits, which were, it alleged, essential elements of the parties’ agreement, were omitted such that there was no meeting of the minds. In count II, Luco sought, as an alternative to count I, a declaratory judgment that the master subcontractor agreement’s arbitration clause was unconscionable and unenforceable, where it required Luco to commence an action within six months of a certificate of occupancy and required that each purchase order (PO) be deemed a separate contract. In count III, Luco alleged that, if the parties’ 2011 contract was valid and enforceable, WRH breached the contract, where: (1) WRH issued duplicate reversals of payment, thereby shorting Luco $2,625; (2) failed to pay Luco $5,406.46 for work for which lien waivers had been provided and copies of checks issued; (3) issued improper chargebacks to Luco totaling $2,625; (4) failed to pay Luco invoices totaling $22,446.83; and (5) improperly deducted amounts for 2.6% (in excess of $75,000) for contribution for insurance, where no agreement existed between the parties authorizing such withholding. Finally, in count IV, Luco sought, if the contract was invalid and unenforceable, recovery under a quantum meruit theory for improper chargebacks, invoices, etc.

¶ 12 C. Trial

¶ 13 A bench trial occurred on May 22, 23, and 28, 2018. Luco’s witnesses were: (1) Jamie Amelse, Luco’s bookkeeper and Luke Amelse’s wife; (2) David Bruski, a Luco employee; and (3)

Luke Amelse, Luco’s president. WRH’s witnesses were: (1) Debbie Beaver, a WRH area manager between 2009 and 2012 and vice president of operations between 2012 and 2015; and (2) Jeffrey Meyer, a WRH superintendent between 2005 and 2013 and a construction manager between 2013 and 2017.

¶ 14 1. Jamie Amelse

¶ 15 Jamie Amelse, whom the trial court found not credible or consistent and whose testimony it gave little weight, testified that she performed clerical work for Luco, including invoices, estimates, billing, and communications from vendors and contractors. Addressing Luco’s group exhibit No. 4, Jamie testified that exhibit consisted of invoices due and owing from WRH. The invoices included an invoice number, location of work performed, lot number of the home, and WRH’s PO number. After Luco filed its complaint, it received payment for some, but not all, of the invoices. She identified a check from WRH for $14,428.98 that Luco received after the suit was filed. She cross-referenced WRH’s PO numbers with Luco’s invoice numbers to determine which invoices were paid and which were not paid. Jamie identified invoices paid and those still due and owing.

¶ 16 In a September 25, 2014, email from Beaver of WRH to Luco’s attorney, Beaver stated that Luco’s past 12 months of receivables were $470,727 and WRH was holding $47,072 as warranty escrow. According to Jamie, WRH would get Luco and Luco Construction, a separate entity, mixed up, as reflected in accounts payable printouts. Jamie identified an exhibit of WRH’s POs that showed deductions for work Luco improperly performed. WRH deducted $2,250 for improper grading and an invoice to Classic Landscaping showed that it was paid the same amount to re-grade and re-sod the property. Jamie testified that Luco was not paid for that work but was charged back.

¶ 17 Jamie addressed another exhibit, which consisted of a document she prepared listing the checks issued by WRH from May 2, 2011, to May 2015 and that included the check number, amount, and the deduction taken by WRH. Jamie testified that WRH took 2.6% of every check during this time.

¶ 18 Jamie later conceded that some of the invoices in Luco’s group exhibit No. 4 were paid and that it was possible that some of the invoices in that exhibit were paid even before WRH’s check for $14,428.98 was tendered to Luco. As of the date of her testimony, Jamie believed Luco was owed about $32,000 due to the 2.6% deduction, $6,100 in chargebacks, and about $9,500 in unpaid invoices. Jamie could not recall Beaver telling her to stop sending invoices to WRH and stated that Beaver would tell her which invoices were being sent to be paid and which ones were not. Jamie denied that Beaver met with her to go through invoices and did not know whether Beaver met with anyone else at Luco.

Free access — add to your briefcase to read the full text and ask questions with AI

Luco Land Development, Inc. v. William Ryan Homes, Inc., 2020 IL App (2d) 190156-U (Ill. Ct. App. 2020).

2020 IL App (2d) 190156-U (Luco Land Development, Inc. v. William Ryan Homes, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Webb v. Mount Sinai Hospital & Medical Center of Chicago, Inc.
807 N.E.2d 1026 (Appellate Court of Illinois, 2004)
Landmark Properties, Inc. v. Architects International-Chicago
526 N.E.2d 603 (Appellate Court of Illinois, 1988)
Gill v. Foster
626 N.E.2d 190 (Illinois Supreme Court, 1993)
Northern Illinois Construction Co. v. Zale
483 N.E.2d 1013 (Appellate Court of Illinois, 1985)
Burmac Metal Finishing Co. v. West Bend Mutual Insurance
825 N.E.2d 1246 (Appellate Court of Illinois, 2005)
Chicago Investment Corp. v. Dolins
481 N.E.2d 712 (Illinois Supreme Court, 1985)
Smith v. Silver Cross Hospital
790 N.E.2d 77 (Appellate Court of Illinois, 2003)
John Crane, Inc. v. Admiral Ins. Co.
910 N.E.2d 1168 (Appellate Court of Illinois, 2009)
McHale v. W.D. Trucking, Inc.
2015 IL App (1st) 132625 (Appellate Court of Illinois, 2015)
Martinez v. River Park Place, LLC
2012 IL App (1st) 111478 (Appellate Court of Illinois, 2012)