Luckie v. Max Wright, Inc.

82 S.E.2d 660, 90 Ga. App. 243, 1954 Ga. App. LEXIS 674
CourtCourt of Appeals of Georgia
DecidedMay 13, 1954
Docket35165
StatusPublished
Cited by10 cases

This text of 82 S.E.2d 660 (Luckie v. Max Wright, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luckie v. Max Wright, Inc., 82 S.E.2d 660, 90 Ga. App. 243, 1954 Ga. App. LEXIS 674 (Ga. Ct. App. 1954).

Opinion

Townsend, J.

Special ground 4 contends that the court erred in charging the jury as follows: “Where an oral contract to furnish labor and material for the improvement of real estate is entered into by two parties and a contract price is agreed upon but the time of payment of said contract price is not agreed upon, it is implied as a term of the contract that payment of the contract price be made upon the completion of the contract by the party furnishing the labor and the materials for the improvement of the real estate.” In connection with this portion of the charge, the court also charged that the jury was to determine whether or not a valid oral contract existed between the plaintiff and the defendant on November 30, 1950, and, if not, a verdict for the defendant should be returned; and the court also charged that, before a contract can result, “it is necessary that there be a mutual assent or meeting of the minds of the parties about the same thing in the same sense, including the terms of the contract, and amount and time of payment and the method and manner and time of performance of the conditions of the contract.” Construing the charge as a whole, the excerpt complained of could not have been construed by the jury as an opinion of the court that a contract had been entered into, nor could it have confused them as a contradictory statement that the time of payment, where no time was explicitly agreed upon, is impliedly upon the completion of the contract, and also that there must be mutual assent as to all the terms of the contract including time of payment thereof. The reason for the implication arising that payment on a contract is due when the contract is completed is inherent in the proposition that it is usual and natural in the ordinary course of things to pay for things when they are received, since one party, having fulfilled his obligation, is entitled to like performance by the opposite party on a contract, and since, if this course is not intended by both, it will be otherwise stipulated. As to goods sold, the presumption, in the absence of proof of a contract or custom to the contrary, is that payment is due on delivery. Northwest At *246 lanta Bank v. Willingham, 69 Ga. App. 258 (25 S. E. 2d 154). Liens of laborers arise upon the completion of their contract of labor. Code § 67-1803. It follows, therefore, that where a contract involving goods and services is involved, and no stipulation to the contrary is included therein, and no custom to the contrary proved in evidence, payment will be presumed due when the contract is completed. Accordingly, there was no error in so charging. This ground is without merit.

In special ground 5 it is contended that the court erred in charging in effect that, should the jury find that an oral contract was entered into on November 30, 1950, it would be immaterial that the defendant refused to sign a written contract subsequently to that date, and it would also be immaterial that the tendered written contract contained material variations from the oral contract previously agreed upon.. In Lott-Lewis Co. v. Bingham-Hewett Grain Co., 28 Ga. App. 728 (113 S. E. 222), it is held as follows: “A valid and binding contract having been made, the defendant’s subsequent refusal tp sign a formal written contract tendered by the plaintiff was immaterial; and it was immaterial whether this tendered contract contained material variations from the previous contract.” See also Herbener & Sons v. Cuero Cotton Oil & Mfg. Co., 25 Ga. App. 440 (103 S. E. 828.) This ground is without merit.

In special ground 6 error is assigned on the following excerpt from the charge, on the ground that it is an expression of opinion and an instruction on the wrong measure of damages: “Where one employs another to furnish the labor and material and to do the work necessary for the improvement of real estate but renounces the contract prior to the time when the contractor has incurred any expense toward the performance thereof, the recovery for the breach of the contract is the difference between the contract price and what it would have cost the contractor in labor and materials to have performed the contract.” In special ground 7, error is assigned on an excerpt from the charge as follows, on the ground that it allowed the jury to base their verdict upon their own experience and disregard the evidence in the case: “If you find the plaintiff is entitled to recover, the form of your verdict would be, ‘We, the jury, find for the plaintiff the sum of $________________’ which is stated in the petition *247 as $4,089.22—it may not exceed that and it may be any amount less than that that the jury determines that the plaintiff is entitled to if it is entitled to recover.” These grounds will be considered in connection with one of the contentions under the general grounds, to the effect that, the contract price being alleged as $16,537.50 and the cost of performance alleged as $12,448.28, there was no evidence to support a verdict in the sum of $3,112.50.

The excerpt complained of in special ground 6 is taken from the headnote in Campbell & Co. v. Mion Bros., 6 Ga. App. 134 (3) (64 S. E. 571), and is a correct statement of the law. As hereinabove pointed out, the court made it clear that the jury was to determine whether or not a contract was in existence, and this excerpt is not an expression of opinion that the contract did in fact exist. The defendant contends that the court should have stated the measure of damages as “the difference between the contract price and what it would have reasonably cost to have performed the contract.”

The rule is as stated by the trial judge in his charge. However, in proving what it would cost the contractor to have completed the job, the evidence is necessarily restricted to its reasonable cost to him. There was evidence here as to the items of material and the labor of installing them, which evidence was based on testimony as to estimates from which the contract price was determined. In some instances the cost of the material itself could be arrived at with a fair degree of accuracy, thus eliminating the element of estimation (as where the plaintiff actually ordered certain equipment at a certain price), but the labor for installation must necessarily depend upon the estimation of such cost by the witnesses. It follows, therefore, that in cases such as these the proof of the cost to the contractor must be restricted to amounts that are reasonable, and the testimony of any witness is subject to attack by cross-examination and by contradictory testimony by other witnesses tending to show the cost sought to be established to be unreasonable in amount. The nature of the testimony seeking to show the cost of the labor and material to complete the contract is therefore opinionative and is subject to the rule of evidence that the question of the value of an article is peculiarly for the jury, which is not abso *248 lutely bound by the opinions or estimates of witnesses on the subject. Minchew v. Nahunta Lumber Co., 5 Ga. App. 154 (62 S. E. 716).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crankshaw v. Stanley Homes, Inc.
207 S.E.2d 241 (Court of Appeals of Georgia, 1974)
Redman Development Corp. v. Piedmont Heating & Air Conditioning, Inc.
197 S.E.2d 167 (Court of Appeals of Georgia, 1973)
Stubbs v. Forrest Hills Baptist Church
193 S.E.2d 53 (Court of Appeals of Georgia, 1972)
Paradies & Co. v. Southeastern Personnel, Inc.
186 S.E.2d 304 (Court of Appeals of Georgia, 1971)
Southern Land, Timber & Pulp Corp. v. Davis & Floyd Engineers, Inc.
135 S.E.2d 454 (Court of Appeals of Georgia, 1964)
Peachtree Medical Building, Inc. v. Keel
130 S.E.2d 530 (Court of Appeals of Georgia, 1963)
Marsh v. State Highway Department
114 S.E.2d 411 (Supreme Court of Georgia, 1960)
Jones v. Ely
96 S.E.2d 536 (Court of Appeals of Georgia, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
82 S.E.2d 660, 90 Ga. App. 243, 1954 Ga. App. LEXIS 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luckie-v-max-wright-inc-gactapp-1954.