Peelle, Ch. J.,

delivered the opinion of the court:

The question now arises on the defendants’ motion for a new trial on the ground of (1) error of fact, (2) error of law, and (3) newly discovered evidence, the latter resting on records in an executive department. While we overrule the [365]*365defendants’ motion for a new trial, the former findings are withdrawn and the judgment vacated because of new findings and revised opinion this day filed. We allow most all of the amendments to the findings asked for by the defendants, including those based on the new or record evidence, though we adhere to our ruling on the law of the case, and will restate our reasons.

As the findings disclose, the claimant on July 24, 1905, entered into a contract with the Government, through the Acting Secretary of the Interior, for the erection of certain structures required in connection with the Huntley (Mont.) reclamation project, in accordance with the advertisement, proposal, and specifications made part of the contract set forth in the petition, excepting in so far as the specifications might thereafter be amended or modified by the terms of the contract, as set forth in article 1 thereof.

The contention is that the words “ actual necessary cost ” contained in paragraph 24 of the specifications include liability insurance, depreciation of plant, expenses of superintendents, and loss on account of boarding men.

Paragraph 24 of the specifications provides:

Changes and extra worlc. — The Secretary of the Interior reserves the right to make such changes in the specifications of work or material at any time as may be deemed advisable, without notice to the surety or sureties on the bond given to secure compliance with the contract, by adding thereto or deducting therefrom, at the unit prices of the contract, or at such allowances for changes of materials as shall be deemed just and reasonable by the engineer, whose decision shall be binding on both parties. The right to make material changes in the quantities listed in the proposal is an essential part of the contract, and bidders must make their estimates accordingly. Should any change be made in a particular piece of work after it has been commenced, so that the contractor is put to extra expense, the engineer shall make reasonable allowance therefor, which action shall be binding on both parties. Extra work or work not provided for in the specifications, if ordered in writing by the engineer, will be paid for at actual necessary cost, as determined by the engineer, plus 15 per cent. Demand for such extra payment must be accompanied by the certificate of the engineer that such work has been satisfactorily performed or the material furnished, and stating the amount [366]*366to be allowed therefor. Such demand must be made before the time of the payment following the completion of said extra work, or the furnishing of the material.”

Paragraph 36 of the specifications provides that “the payments due shall be made to the contractor upon the presentation of proper accounts, prepared by the engineer and approved by the chief engineer, in accordance with the provisions made therefor and pertaining to the contract,” while paragraph 96 provides that the work shall be completed to the “ entire satisfaction of the chief engineer.”

Subsequent to the execution of the contract and after the claimant had entered upon the performance thereof he was, on May 2, 1906, directed through the supervising engineer to build, under said paragraph 24, certain structures listed on force account under the provisions of said paragraph. That is to say, at “ actual necessary cost,” to be determined by the engineer, plus 15 per cent.

Various other changes were from time to time ordered in the work for which claimant was paid at unit prices, as provided in said paragraph, but no payments were made for the items now claimed for. The engineer, under date of June 2, 1906, as set forth in his letter, directed the claimant to assemble the necessary plant and equipment to- enable him tc complete the work on force account as well as other work under the “ structures ” contract, for which work, as therein provided, he was assured that in making up the final estimate proper and equitable consideration would be given, and an allowance recommended to cover the liability insurance of laborers, the unloading and storage of construction materials, and the depreciation of machinery.

On May 31, 1907, when the “ structures ” work and extra work so ordered were completed to that date, the claimant forwarded his statement of account for the value of labor and material furnished, adding thereto 15 per cent as provided in said paragraph 24, which he certified was correct and which, after certification by the engineer of the Kecla-mation Service, was paid. No mention was made in said account of the items for which payment is now claimed; but upon completion of the work and before payment of the retained percentages under paragraph 96 of the specifica[367]*367tions, the claimant did make claim for expenses of the class referred to, and by reason thereof a board of engineers of the Reclamation Service was assembled by authority of Mr. Savage, supervising engineer, and after conferring with the claimant they “recommended for settlement, subject to the regulations of the department,” the claim for liability insurance, depreciation of the plant, and storage warehouses upon the basis or ratio of the force work to the other work performed, and also the total loss in the boarding of men on force account; in all, $3,387.48. Thereupon the claim so recommended and certified was presented to the Auditor of the Treasury, who disallowed the claim on the ground that “ all of the extra work under this contract appears to have been performed prior to June 1,1907, and the cost thereof to the contractor, plus the 15 per cent provided for in paragraph 24, itemized and determined by the engineer, approved by the director, and paid for in full upon settlements heretofore made in this office. The Government’s obligation for this extra work, under the terms of this contract, has thus been discharged.”

From the decision thus rendered an appeal was taken to the Comptroller of the Treasury for the reasons stated by the Secretary of the Interior in his letter set forth in Finding VI; but the decision of the auditor was affirmed by the assistant comptroller (14 Comp. Dec., 297) on the ground that the items for which claim is here made were not a part of the “ actual necessary cost ” of .such extra work within the meaning of paragraph 24 of the specifications, holding that as the claimant at the end of each month during the progress of the work had made his demand for extra payment based on the cost of work and material, which he certified to be correct, as did the engineer in charge, and settlement was made therefor upon that basis, he was “ estopped from demanding an extra allowance as a part of the cost of the extra work”; that the Government was not “ responsible for the course of business of the contractor and the performance of the whole contract ”; that if it were, it “ would virtually create a partnership between the contractor and the Government as to losses only”; that if there had been a profit on the boarding of [368]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sweeney v. United States
109 U.S. 618 (Supreme Court, 1884)
Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)
Hoffeld v. United States
36 Ct. Cl. 230 (Court of Claims, 1901)
McIntyre v. United States
44 Ct. Cl. 448 (Court of Claims, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 361, 1912 U.S. Ct. Cl. LEXIS 77, 1911 WL 1367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lovell-v-united-states-cc-1912.