Louvin Realty Corp. v. City of New York

242 A.D. 181, 272 N.Y.S. 752, 1934 N.Y. App. Div. LEXIS 6023
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 29, 1934
StatusPublished
Cited by2 cases

This text of 242 A.D. 181 (Louvin Realty Corp. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louvin Realty Corp. v. City of New York, 242 A.D. 181, 272 N.Y.S. 752, 1934 N.Y. App. Div. LEXIS 6023 (N.Y. Ct. App. 1934).

Opinion

Mabtin, J.

The plaintiff seeks to recover damages in this action for the alleged wrongful cancellation by the city of New York of its contract with the Maxwell Gibbs Corporation, plaintiff’s assignor, dated November 6, 1929, for the construction of a part of the Kings County Hospital buildings in Brooklyn for the sum of $3,869,000.

The Maxwell Gibbs Corporation sublet its entire contract. The demolition work of fifteen buildings was sublet to Henry Jaffe who started wrecking the old buildings on the site on November 4, 1929, in order to prepare it for the general construction of the new hospital building, and continued through the week with between 100 and 200 men. Jaffe continued the wrecking up to about January 28, 1930, when he abandoned the job. At that time the only buildings remaining to be demolished were known and designated as the “ chronic kitchen ” and part of the dormitory for females.

On February 1, 1930, the Maxwell Gibbs Corporation entered into a contract to complete the demolition work with P. Makofsky & Son, who started work on February 2 or 3, 1930. Makofsky was on the job about a week when he stopped work. During January, 1930, the architect filed a certificate with the commissioner of hospitals in which he recommended that the contract be declared abandoned and the Maxwell Gibbs Corporation be directed to discontinue work because in his opinion certain clauses in the specifications had been violated.

On February 10, 1930, the commissioner of hospitals ordered the Maxwell Gibbs Corporation to discontinue work under the contract for the construction of the Kings County Hospital. Thereafter, and on or about April 22, 1930, the present action was commenced.

The theory of this action is that the contract was canceled without cause, fraudulently and in bad faith in furtherance of a scheme ” on the part of certain officials and agents of the city to deprive the plaintiff’s assignor, Maxwell Gibbs Corporation, of its contract.

The city contends on this appeal that the architect was the sole and final arbiter of the performance of the contract under the provisions thereof, and that plaintiff cannot recover unless it establishes that the action of the architect in terminating the contract was unreasonable, collusive, fraudulent and taken in bad faith. It also contends that the contract is void on the ground of public policy because the plaintiff admitted that it was obtained through political influence. It is argued that the promise sued on, being based in part upon an illegal consideration, cannot be enforced, either in whole or in part, and that the contract is not validated by [183]*183its assignment, if it was void in its inception. The city says that in any event the judgment must be reversed because the court adopted an erroneous measure of damages and seriously erred in its ruhngs on the evidence and its charge to the jury.

The respondent contends that it proved conclusively that there was a binding agreement between its assignor and the city which was being properly performed by the plaintiff’s assignor. It then sets out at length the methods alleged to have been used by the architect and deputy commissioner of hospitals to force the contractor to abandon the contract. The respondent says it was hampered in the demolition of the old buildings and was dictated to in the letting of subcontracts and in securing the bond. It is also contended by the respondent that the subcontractors were advised by the deputy commissioner that the general contractor was not wanted on the job and his payments would not be made, in consequence of which the plaintiff’s assignor met with serious obstacles in the performance of the contract; that everything possible was done to get the plaintiff’s assignor off the job, so that the contract could be awarded to another contractor and that the dishonest scheme was finally brought to a successful conclusion. It is further asserted that the architect charged the contractor with not proceeding fast enough with the work, although it was shown on the trial that the chronic ldtchen ” building, which stood in the center of the plot on which the hospital was to be built, was being used and this prevented the contractor from demolishing it. The plaintiff contends that it could not prepare for the foundation work until it had the plans and until the site was available for excavating purposes; that it could not do any excavating until the buildings were removed from the site and further that the building directly in the center of the plot was not turned over to the contractor until after January 28, 1930.

The city says that the plaintiff was never able to do the work and never intended to do it. On this issue the jury found for the plaintiff. It will be unnecessary to further consider that question because of errors in the admission of evidence requiring a reversal of the judgment.

Several important questions of law have been submitted on this appeal with reference to the admission of evidence. The most important question, however, is that of damages. The parties appear to have entirely disregarded the general rule of damages applicable to a case of this character. The decision of that important question makes it unnecessary to consider the other questions here involved, especially in view of the fact that they are not likely to arise on a new trial.

[184]*184It is argued now that the theory of damages was consented to by the city of New York, but the record shows that objection was made at the very outset when it was attempted to put in evidence subcontracts. A list of subcontracts and the prices at which the work was to be performed was thereafter admitted in evidence.

Subcontracts alleged to have been made with subcontractors were not only admitted in evidence, but the court in its charge finally told the jury in substance that the contractor was entitled to recover the difference between the contract price with the city and the amount that the subcontractors had agreed to accept as compensation for performance of the subcontracts. To this amount they were told to add the expense which the contractor had in partly performing the contract. Of course, this is not and never has been the rule of damages in cases of this kind. A subcontractor might agree to do the work for nothing, but that would not change the rule.

The well-known rule with reference to damages for breach of contract, where a contractor is suing for anticipated profits, has been many times ably set forth. Before considering the decisions on that subject, however, we will refer to a few which have condemned the method of proving damages by admitting in evidence subcontracts.

The Appellate Division, through Mr. Justice Miller, in Hirsh v. Press Pub. Co. (141 App. Div. 357), said: “ It is unnecessary to cite authority upon the proposition that the damages recoverable for breach of contract are such as may fairly be said to have been within the contemplation of the parties. While, of course, the certainty of proof required may vary according to the circumstances and necessities of the case, it has never been held, so far as we are aware, that a party claiming damages may have the benefit of favorable contracts, made by him with third parties after the making of the contract for breach of which damages are claimed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indiana & Michigan Electric Co. v. Terre Haute Industries, Inc.
507 N.E.2d 588 (Indiana Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
242 A.D. 181, 272 N.Y.S. 752, 1934 N.Y. App. Div. LEXIS 6023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louvin-realty-corp-v-city-of-new-york-nyappdiv-1934.