Louisiana Plumbing & Heating, Inc. v. Miranne & Harris, Inc.

181 So. 2d 261, 1965 La. App. LEXIS 3902
CourtLouisiana Court of Appeal
DecidedDecember 6, 1965
DocketNo. 1969
StatusPublished
Cited by3 cases

This text of 181 So. 2d 261 (Louisiana Plumbing & Heating, Inc. v. Miranne & Harris, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Plumbing & Heating, Inc. v. Miranne & Harris, Inc., 181 So. 2d 261, 1965 La. App. LEXIS 3902 (La. Ct. App. 1965).

Opinion

McBRIDE, Judge.

Plaintiff, a subcontractor for the plumbing work, recovered judgment against the principal contractor for $6829.83 due on the subcontract. However, plaintiff has appealed from that part of the judgment which dismissed its personal right of action against the owner for the amount of its claim and disallowed its asserted lien and privilege on the property on which the work was done.

Shortly after acquiring 1415 Esplanade Avenue, New Orleans, in February, 1962, Miranne and Harris, Inc., as owner, entered into a verbal and, of course, unrecorded contract with defendant, E. M. Gibbens, Inc., contractor, 'for the renovation of said building and its conversion into ten apartments. The contract price was $25,-000. Plans and specifications were prepared by an officer of Miranne and Harris, Inc. Work commenced at once.

About March 1, 1962, E. M. Gibbens, Inc., the contractor, entered into a verbal subcontract with plaintiff whereunder plaintiff, as subcontractor, undertook to perform all plumbing work for $6602 as per its written proposal. Plaintiff was to furnish the necessary labor and materials. To be furnished and installed were two 65-gallon, glass-lined water heaters and vents. Plaintiff’s proposal provided:

“All work shall be in accordance with the rules and regulations of the Sewerage and Water Board and inspected by same, also the Department of Regulatory Inspection for gas.”

The contractor was paid by the owner in full for the job, the last installment of $9000 being paid August 2, 1962. E. M. Gibbens, Inc., fully completed its work in December, 1962, and, by mutual agreement with the owner, left the job. The owner was satisfied with the result and took possession of the premises immediately. The contractor failed to pay plaintiff. The lien plaintiff asserts against the building was filed in the mortgage office May 31, 1963. This suit ensued.

The defense of the owner is that whatever rights plaintiff may have had to a lien on the property and a personal claim against it, was lost by the failure to seasonably record the lien.

Plaintiff contends that it performed its last work on April 11, 1963, when it installed vents on the two gas water heaters as per the terms of the subcontract. The heáters were vented by the connection of metal flues to the tops thereof and by the running of the flues through holes to the outside of the building so as to permit the escape of gases and fumes generated by the heaters into the air. Plaintiff argues that its lien was filed timely, i. e. within sixty days of the last performance of all services or labor upon the property.

R.S. 9:4812 provides in part as follows :

“When the owner, * * * undertakes the work of construction, improvement, repair, * * * for which no contract has been entered into, * * * then any person furnishing service or material or performing any labor * * * may record * * * [263]*263a copy of his estimate or an affidavit of his claim * * * which recordation, if done within sixty days after the date of the last delivery of all material upon the said property or the last performance of all services or labor upon the same, by the said furnisher of material or the said laborer, shall create a privilege upon the building * * *. Any person furnishing service or material or performing any labor on the said building * * for a contractor or sub-contractor, when a contract, oral or written has been entered into, but no contract has been timely recorded, shall have a personal right of action against the owner for the amount of his claim for a period of one year from the filing of his claim, * *

During January, 1963, some water pipes were damaged by a freeze and required replacement, the work being performed by another plumber at the owner’s expense. During February, March and April, 1963, air conditioning was installed, and the premises were equipped with carpets, draperies, appliances, furniture, etc., none of which items were included in the contract between the owner and E. M. Gibbens, Inc., or in the subcontract between Gibbens and plaintiff. All apartments had electrical service by March 28, 1963. The initial apartment occupancy took place about mid-May, 1963.

At the time the contractor left the job and the owner accepted the job in December, 1962, plaintiff had, to all appearances, completed its undertakings under the subcontract. All plumbing had been installed in accordance with the agreement, and the two water heaters were in place and connected with the respective water and gas pipes. Plaintiff’s workmen did nothing in the premises until the heaters were vented on April 11, 1963. In other words, a period of four months elapsed during which time no one representing plaintiff as much as entered the premises. The contractor and the owner believed that all plumbing work under the subcontract had been fully performed. All that remained was the subcontractor’s duty to furnish the permit from the Department of Regulatory Inspections authorizing occupancy of the building.

As aforesaid, plaintiff had agreed to perform its subcontract work in accordance with the rules and regulations of the Sewerage & Water Board and the Department of Regulatory Inspections. In December, 1962, plaintiff made applications to said municipal departments for inspections of both the water and gas installations ; the water installations were inspected December 19, 1962, and approved and the water was turned on. The gas installations were inspected January 2, 1963, by the Department of Regulatory Inspections but failed to merit approval. Plaintiff was notified thereof by the Department and undoubtedly had cognizance that approval had been withheld for the reason vents had not been installed on the two 65-gallon water heaters. Plaintiff made no mention of these facts to the owner of the building or to the contractor, who had no knowledge thereof.

The owner was at all times led to believe by plaintiff that it had obtained approval of the plumbing work and that it had secured the occupancy permit. It might be mentioned in passing that up to the date of the trial, the owner had not received such permit from plaintiff.

Mr. Miranne, president of Miranne and Plarris, Inc., testified:

“Q. Did you go to the premises at all during the course of the renovation ?
“A. Yes, I did, and I went to the premises during the renovation the last time I recall going to the premises when Mr. Gibbens said that his work was completed under his contract. That was about the middle of December ’62.
[264]*264“Q. Did you inspect the premises at that time ?
“A. Yes, I did.
“Q. Did Mr. Gibbens or anybody from E. M. Gibbens, Inc. appear at the property 1415 Esplanade thereafter ? I’m talking- about after mid December of ’62 for any repairs, renovations?
“A. To my knowledge, no, because Mr. Gibbens’ work was completed.
“Q. Did you ever have any telephone or other discussions, did you ever discuss this matter with Louisiana Plumbing and Heating, Mr. Flynn, or any representative?
“A. Yes, I did. I think on three separate occasions, if this is Mr. Flynn here.
“(By Mr. Flynn) : Yes.
“A. I didn’t know Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southmark Corp. v. Ellis Millwork, Inc.
535 So. 2d 507 (Louisiana Court of Appeal, 1988)
Jeffer's Trust v. Justice
253 So. 2d 234 (Louisiana Court of Appeal, 1971)
Tabet Lumber Company v. Baughman
439 P.2d 706 (New Mexico Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
181 So. 2d 261, 1965 La. App. LEXIS 3902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-plumbing-heating-inc-v-miranne-harris-inc-lactapp-1965.