Cain v. Central Plumbing and Heating Company

85 So. 2d 376
CourtLouisiana Court of Appeal
DecidedFebruary 3, 1956
Docket4131
StatusPublished
Cited by12 cases

This text of 85 So. 2d 376 (Cain v. Central Plumbing and Heating Company) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cain v. Central Plumbing and Heating Company, 85 So. 2d 376 (La. Ct. App. 1956).

Opinion

85 So.2d 376 (1956)

J. H. CAIN et al., Plaintiff in Rule-Appellee,
v.
CENTRAL PLUMBING AND HEATING COMPANY, Defendant in Rule-Appellant.

No. 4131.

Court of Appeal of Louisiana, First Circuit.

February 3, 1956.

Lecompte, Hall & Coltharp, DeRidder, for appellant.

Kay & Kay, DeRidder, for appellee.

TATE, Judge.

The Central Plumbing and Heating Company, a partnership, appeals from judgment rejecting its claim for payment for certain plumbing supplies and services, and ordering cancellation of its lien therefor, recorded against certain property foreclosed under a mortgage held by plaintiffs, Mr. and Mrs. J. H. Cain. Subsequent to the sheriff's sale of said property, the aforesaid appellant partnership (hereinafter referred to as "Central") was made defendant in a rule to show cause why its lien in the principal sum of $900 should not be cancelled and erased, and praying for the court to determine any right of the lienholder to any part of the proceeds of the sale.

The sole question for our determination is whether Central's labor and materialman's lien was timely recorded to preserve its lien and privilege under LSA-R.S. 9:4801 et seq. as a furnisher of plumbing supplies *377 and services in construction of the building on the property seized and sold herein. More precisely, both parties admitting that in the case of a completed building the lien must be recorded within 90 days after the last work is done or material furnished, the question herein in this case of a building never completed according to specifications by the original owners is by what date, if any, is a materialman required to file his lien in order to protect his claim against the property?

To summarize the facts, as to which there is no conflict for appellate purposes: A carpenters' local union purchased some land and commenced the construction of a building thereupon as owner, which lot and building are the property seized and sold by the plaintiffs-creditors herein. Construction commenced in September of 1952. Afterwards, the $20,000 mortgage held by plaintiffs and foreclosed upon herein was executed and recorded on February 13, 1953. The process of construction was somewhat leisurely, because although the materials were purchased from union funds and from the proceeds of the loan, the bulk of the labor was contributed by the members of the local union from their spare time. Becoming financially embarrassed, the union was unable to complete and finish the upstairs of the building and the stairs leading thereto, according to the original specifications, although the remainder of the building was so completed. The incompleted work, estimated to cost $2,000, was chiefly finishing, such as a celotex ceiling, a finished floor above the secondstory sub-floor, permanent treads on the stairs, etc. The last actual work done upon the building was done not later than April of 1954, when the downstairs was painted and trimmed for purposes of renting it to a commercial user, which subsequently was done. All of Central's work had been performed prior to that time, although Central did not execute its lien for the remaining balance due of $900 until December 20, 1954, which was filed the following day in the mortgage records.

The following is the pertinent part of the statute, LSA-R.S. 9:4812, under which the lien and privilege as a furnisher of labor and supplies is claimed:

"When the owner * * * undertakes the work of construction * * * for which no contract has been entered into * * * then any person furnishing service or material or performing any * * * may record * * * a copy of his estimate or an affidavit of his claim * * * which recordation, if done within sixty days after the date of the last delivery of all material upon the said property or the last performance of all services or labor upon the same, by the said furnisher of material or the said laborer, shall create a privilege upon the building * * *." (Italics ours.)

Astutely, and with considerable logic, counsel for appellant urges that the language requiring recordation of the privilege within sixty days after the "last delivery of all material" or the "last performance of all services or labor" clearly means within sixty days of the date of final completion of work. Alternatively, it is urged that this date could be not later than the date the owner abandons his intention of completing the work. Thus, it is argued, Central's lien was timely recorded and primes plaintiffs' mortgage, which was not recorded until after the construction had commenced, since: (a) the building was never finally completed according to its original specifications; (b) allegedly, the owner had not abandoned his intention of finally completing said building when Central's lien was recorded on December 21, 1954.

Appellant relies upon National Homestead Association v. Graham, 176 La. 1062, 147 So. 348; Rathborne Lumber & Supply Co. v. Falgout, 222 La. 345, 62 So.2d 507; and Singer Lumber Co., Inc. v. King, La. App., 45 So.2d 567. Although the former two Supreme Court cases refer to the provision as meaning requiring the recordation of the lien within sixty days after "the final completion of the structure", the Supreme Court explained this phrase by stating in the Graham case at 147 So. 352: "The work is completed when the last material *378 is furnished and the last labor is performed."

In the Graham case for instance, the apartment house was never finally completed as originally planned due to financial difficulty of the owner, much the same as in the present case. In sustaining the lien filed on November 5, 1930, the Supreme Court pointed out that labor was performed on the building at least up through October 1. If the Supreme Court had intended to hold that the lienors had 60 days within which to record their privilege after work was "finally" completed in the sense contended by appellant, it appears that it was unnecessary to find that labor had been performed up through October 1, since the Graham building was never finally completed as planned any more than was the building in the present case. (The Falgout case simply quoted from the holding in the Graham case, but did not involve construction of the clause in question.)

Considerable support is given to appellant's position by the Orleans Court of Appeal decision reported at Singer Lumber Co., Inc. v. King, above cited. Perhaps, as appellee urges, this case can be distinguished, since the appellate and district court found that well within the period of sixty days before the lien was filed, the owners had not abandoned the project and were hoping to have the contractor recommence operations; whereas it is otherwise in the instant case for all practical purposes after April, 1954, when the downstairs was finished and for rent, and the upstairs was in use by the owner as a meeting room, and also rented for such purposes to two or three other unions. The Orleans Court, like ourselves, found it difficult that the time within which the lien must be filed should start running by an act evidenced by "the mere mental determination of the owner that the work is abandoned". We feel that the objective manifestation of the completion, namely, when the last work was actually done on the contract, is a more reliable indicia of completion of the work, i. e., the rule of the Graham case.

But further, our Supreme Court has rejected roughly similar arguments made on behalf of the lienholder in Trouard v. Calcasieu Building Materials, 222 La.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clegg Concrete, Inc. v. Kel-Bar, Inc.
393 So. 2d 178 (Louisiana Court of Appeal, 1980)
Daigrepont v. Welch
358 So. 2d 1302 (Louisiana Court of Appeal, 1978)
Albert K. Newlin, Inc. v. Weingarten's Markets Realty Co.
253 So. 2d 594 (Louisiana Court of Appeal, 1971)
Jeffer's Trust v. Justice
253 So. 2d 234 (Louisiana Court of Appeal, 1971)
McCulley v. Dublin Construction Co.
234 So. 2d 257 (Louisiana Court of Appeal, 1970)
Louisiana Plumbing & Heating, Inc. v. Miranne & Harris, Inc.
181 So. 2d 261 (Louisiana Court of Appeal, 1965)
Clark v. Richardson
157 So. 2d 325 (Louisiana Court of Appeal, 1963)
Romero & Sons Lumber Company v. Babineaux
151 So. 2d 714 (Louisiana Court of Appeal, 1963)
Munson v. Risinger
114 So. 2d 59 (Louisiana Court of Appeal, 1959)
Sawyer v. Sawyer
335 P.2d 794 (Wyoming Supreme Court, 1959)
RF Mestayer Lumber Company v. Tessner
101 So. 2d 238 (Louisiana Court of Appeal, 1958)
Taylor Seidenbach, Inc. v. Healy
90 So. 2d 158 (Louisiana Court of Appeal, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
85 So. 2d 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cain-v-central-plumbing-and-heating-company-lactapp-1956.