Lord v. Fairway Electric Corp.

223 F. Supp. 2d 1270, 54 Fed. R. Serv. 3d 548, 2002 U.S. Dist. LEXIS 17114, 2002 WL 31039755
CourtDistrict Court, M.D. Florida
DecidedJuly 1, 2002
Docket600CV842ORL28KRS
StatusPublished
Cited by23 cases

This text of 223 F. Supp. 2d 1270 (Lord v. Fairway Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lord v. Fairway Electric Corp., 223 F. Supp. 2d 1270, 54 Fed. R. Serv. 3d 548, 2002 U.S. Dist. LEXIS 17114, 2002 WL 31039755 (M.D. Fla. 2002).

Opinion

ORDER

ANTOON, District Judge.

On April 1, 1996, Plaintiff, Raymond Lord, a master electrician, was installing a breaker switch and load center for a customer. A “load center,” sometimes called a panel box, is a metal panel box consisting, in part, of three copper electrical conductor “buses” individually referred to as “phases.” The main circuit providing electricity to a building passes through the load center, to which “breaker switches” *1273 are installed. Each phase has a “tab” narrower than the rest of the bus phases located at the top. Lugs are placed over the tabs into which worm screws are inserted to secure electrical wire in place. Another feature of the phases are “stabs” which are finger-like structures extending horizontally from the phases onto which the breaker switches are attached. The breaker switches, once attached to the stabs, allow branch circuits to be run from the main circuit. Both the breaker switch and load center were manufactured by Defendant Siemens Energy & Automation, Inc. (Siemens). As Plaintiff affixed the breaker switch to the stabs of the load center, an electrical arc struck him and he was seriously burned. Thereafter, Plaintiff filed this lawsuit alleging Siemens 1 was responsible for Plaintiffs injury.

The court has for consideration two motions — Plaintiffs Motion for Leave to File Second Amended Complaint to Conform to the Evidence (Doc. 58, filed March 12, 2002) and Siemens’s Motion to Exclude Expert Opinion Evidence of Helmut Brosz (Doe. 67, filed April 22, 2002). For the reasons set forth below, Plaintiffs motion must be denied and Siemens’s motion must be granted.

I. Procedural and Factual Background

On March 31, 2000, Plaintiff filed suit in Florida state court alleging that a defect in the Siemens circuit breaker caused the electrical arc that injured Plaintiff. After Siemens answered the original complaint, the case was removed to this court. In August 2000 Plaintiff filed his First Amended Complaint (Doc. 18) containing the same allegations of a defective breaker switch! Pursuant to the court’s Amended Case Management and Scheduling Order (Doc. 28, filed October 11, 2000), which was based on dates submitted by the parties in .their Case Management Report (Doc. 20), all amendments to pleadings were required to be filed no later than November 20, 2000. The Amended Case Management and Scheduling Order also required disclosure of expert witness reports no later than November 5, 2001 for Plaintiff and January 7, 2002 for Defendant. In orders addressing Joint Motions for Enlargement of Time to File Expert Reports (Docs. 42 & 45, filed September 27, 2001 and December 6, 2001, respectively), the court extended the deadlines for disclosure of expert reports to February 28, 2002 for Plaintiff and to March 18, 2002 for Defendant. (Doc. 43, filed October 1, 2001 & Doc. 46, filed December 10, 2001).

The work of Plaintiffs expert, Mr. Hel-mut Brosz, is the focus of both motions pending before this court. Mr. Brosz is a professional (electrical) engineer who operates a forensic engineering firm in Markham, Ontario, Canada. Most of Mr. Brosz’s professional work involves assisting parties engaged in litigation. In furtherance of his business Mr. Brosz actively pursues clients through personal contact. According to Mr. Brosz, he learned of Plaintiffs pending lawsuit claiming the Siemens breaker was defective through his “proprietary marketing source,” although at his deposition he refused to disclose to opposing counsel the nature of this source. Upon receiving information regarding Plaintiffs lawsuit, Mr. Brosz telephoned Plaintiffs counsel on January 2, 2001 and offered his services as an expert witness. On January 29, 2001, after the deadline for *1274 amendment of pleadings had passed, Plaintiffs counsel retained Mr. Brosz to work on this case.

On February 6, 2001, the week after he was retained, Mr. Brosz traveled to Florida to inspect the load center and circuit breaker. After inspecting the equipment, Mr. Brosz concluded that the theory of causation alleged in the Amended Complaint was invalid because the damage he observed was not caused by a defect in the circuit breaker. Despite making this discovery early on in his work, it is unclear from the record before this court whether Mr. Brosz ever advised Plaintiffs counsel that the circuit breaker was not defective prior to submission of his expert report over a year later.

On February 20, 2002, just eight days prior to the deadline for filing expert reports, Mr. Brosz conducted destructive disassembly insulation and function testing of the Siemens breaker switch. Pursuant to agreement of the parties, these destructive disassembly tests were conducted in the presence of Siemens’s expert and other Siemens representatives. These tests conclusively established that the breaker switch was not defective. After the testing conducted in the presence of Siemens representatives, Mr. Brosz conducted additional disassembly tests in private.

On February 26, 2002, Plaintiff filed Mr. Brosz’s expert report, for the first time suggesting that Plaintiffs injury was caused by a defective load center and not by the circuit breaker. In that report and in his subsequent deposition, Mr. Brosz provided his opinion regarding causation. The report revealed that upon his inspection of the tab of the A-phase bus of the load center, Mr. Brosz noticed a gouge on the edge of the tab which he believed had been created during the manufacturing process eight years prior to the accident. He opined that a sliver of copper had been created by the gouging and had remained lodged somewhere in the load center since manufacture. It is Mr. Brosz’s opinion that, as Plaintiff was placing the circuit breaker in the load center, the sliver became dislodged and fell until it came to rest in contact with both the A- and Ceop-per phases of the load center. According to Mr. Brosz, once the phases were bridged by the sliver, the electrical current from the short circuit created ionized gases and, ultimately, the arcing which injured Plaintiff.

After the submission of Mr. Brosz’s expert report, Plaintiff moved to file a Second Amended Complaint to allege that the defective load center rather then the circuit breaker was the proximate cause of Plaintiffs injuries. Siemens has objected to the proposed amendment and, under Rule 702, Federal Rules of Evidence and Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579, 587, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993), has moved to exclude Brosz’s expert opinion testimony as unreliable.

II. Discussion

A. Plaintiffs Motion for Leave to File Second, Amended Complaint to Conform to the Evidence (Doc. 58)

Approximately two weeks after Mr. Brosz submitted his expert report, Plaintiff filed his “Motion For Leave to File a Second Amended .Complaint to Conform to the Evidence.” In support of his motion to amend, Plaintiff relies primarily on Federal Rule of Civil Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
223 F. Supp. 2d 1270, 54 Fed. R. Serv. 3d 548, 2002 U.S. Dist. LEXIS 17114, 2002 WL 31039755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lord-v-fairway-electric-corp-flmd-2002.