Lord v. City of Chicago

274 Ill. 313
Illinois Supreme Court·Decided June 22, 1916·Published·Cited by 6 cases

Opinion

Mr. Justice Dunn

delivered the opinion of the court:

The appellants began an action on the case against the city of Chicago, in the superior court of Cook county, to recover damages caused to their real estate by the elevation of the tracks of the Chicago and Western Indiana Railroad Company in accordance with the requirements of an ordinance of the city. A demurrer was sustained to the declaration. The suit was dismissed and a judgment was rendered against the plaintiffs, from which they have appealed.

The declaration contained three counts, from which it appeared that the appellants owned certain real estate adjoining the right of way and tracks of the Chicago and Western Indiana Railroad Company, on which they had erected and were maintaining an elevator and public warehouse for the reception, storage and shipping, in car-load lots, of grain.t The elevator was connected with the railroad by a switch at the existing grade of the railroad as established by the city. Afterward the city passed an ordinance requiring the railroad company to elevate its tracks seven and one-half feet opposite the appellants’ property, and providing that the city should pay all damages to property caused by the traclc-elevation ordinance. The tracks of the railroad company were accordingly elevated seven and one-half feet, and in doing so the appellants’ switch track was torn up and destroyed, and it is impossible to construct a new switch track to the building of the appellants as it is constructed, so that the building cannot be used as an elevator and public warehouse. The building is substantially a total loss to its owners and the land has depreciated in value.

The appellants base their right to a recovery, first, upon the provision of section 5 of article 13 of the constitution which imposes upon all railroad companies receiving and transporting grain, the duty to deliver it to any consignee thereof or to any elevator or public warehouse to which it may be consigned, and the duty of permitting connections to be made with their tracks, so that any consignee and any public warehouse, coal bank or coal yard may be reached by the cars on the said railroad; second, on the act of the General Assembly requiring common carriers of freight to provide and maintain side-tracks or switch connections for-shippers and receivers of freight, approved June 14, 1909, (Laws of 1909, p. 307,) which imposes upon any railroad being a common carrier of freight, upon application of any shipper tendering or receiving freight or merchandise in car-load lots, the duty of constructing, maintaining and operating upon reasonable terms, upon its own right of way, at any regular station, a switch connection with any such shipper’s railroad tracks, which may be constructed to connect with its railroad on its right of way, where such connection is reasonably practicable and can be put in with safety and will furnish sufficient revenue business to the railroad company to justify the construction and maintenance of the same; and third, upon section 12 of article 11 of the constitution, which declares railways to be public highways, free to all persons for the transportation of persons and property thereon.

The city had the right, in the exercise of its police power, to require the elevation of the railroad tracks. This power is not questioned, and it is not claimed that the city or the railroad company committed any wrongful act in changing the grade and elevating the tracks. We have held that where, in elevating the tracks of a railroad company in accordance with an ordinance requiring such elevation, the grade of a street is so changed as to obstruct the ingress to and egress from private property, the railway company which did the work and the city which agreed to pay the damages were both liable for the damages to the adjoining property because of the obstruction to the street, regardless of the elevation of tracks. In Otis Elevator Co. v. City of Chicago, 263 Ill. 419, we held that a railway company owning its right of way was not liable to the owner of adjacent property for the destruction of a grade switch-track connection of the property with the railroad tracks by the elevation of the tracks in compliance with the requirements of a track-elevation ordinance, where the railroad company was under no contract or legal obligation to maintain such connection. The Otis Elevator Company was a manufacturing corporation, which had constructed the buildings of its plant with reference to the existing grade of the railroad and had a switch-track connection with the railroad at that grade but had no contract for the maintenance of such connection.

Free access — add to your briefcase to read the full text and ask questions with AI

Lord v. City of Chicago, 274 Ill. 313 (Ill. 1916).

274 Ill. 313 (Lord v. City of Chicago) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lo-Vaca Gathering Co. v. Missouri-Kansas-Texas Railroad
476 S.W.2d 732 (Court of Appeals of Texas, 1972)
Engebretson v. State
22 Ill. Ct. Cl. 543 (Court of Claims of Illinois, 1957)
Posinski v. C., M., St. P. P.R.R. Co.
33 N.E.2d 869 (Illinois Supreme Court, 1941)
Posinski v. Chicago, Milwaukee, St. Paul & Pacific Railroad
376 Ill. 346 (Illinois Supreme Court, 1941)
Edward v. State
10 Ill. Ct. Cl. 671 (Court of Claims of Illinois, 1939)
Stein v. State
8 Ill. Ct. Cl. 251 (Court of Claims of Illinois, 1934)