Longo-Puerto Rico, Inc. v. United States Environmental Protection Agency

575 F. Supp. 990, 21 ERC (BNA) 1591, 1983 U.S. Dist. LEXIS 11356
CourtDistrict Court, D. Puerto Rico
DecidedNovember 28, 1983
DocketCiv. No. 83-2654 HL
StatusPublished

This text of 575 F. Supp. 990 (Longo-Puerto Rico, Inc. v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Longo-Puerto Rico, Inc. v. United States Environmental Protection Agency, 575 F. Supp. 990, 21 ERC (BNA) 1591, 1983 U.S. Dist. LEXIS 11356 (prd 1983).

Opinion

OPINION AND ORDER

LAFFITTE, District Judge.

Plaintiff, LONGO-PUERTO RICO, INC. (LONGO) filed this action seeking injunctive relief, declaratory relief and review of a decision of the Regional Administrator, Region II, United States Environmental Protection Agency (EPA). Following a denial of plaintiff’s motion for a temporary restraining order, a consolidated hearing on a preliminary and permanent injunction was held on November 21, 1983. The Court has carefully considered the documents submitted by the parties, affidavits, the briefs, and oral arguments of counsel. For the reasons stated below, LONGO’s petition for preliminary and permanent injunction is denied and summary judgment is granted to the defendants.

THE FACTS.

On September 29, 1979, EPA awarded a Grant to the Puerto Rico Aqueduct and Sewer Authority (PRASA) for the construction of the Torrecilla Trunk Sewer and Force Main (Part I), and Dislodge Transfer Line (Part B), Grant No. C-72-94-10 under Title II of the Clean Water Act, 33 U.S.C. Section 1281, et seq., in the amount of $9,617,015 representing 75% of the estimated Grant eligible costs of the construction project, the total cost of which was $14,-822,686.

On May 6, 1981, PRASA opened bids for the contract concerning the construction portion of the grant. On May 22, 1981, the bid recommendation committee of PRASA recommended to the Board of Awards that the contract be awarded to LONGO. On May 28, 1981, the Board of Awards of PRASA concurred with the recommendation of the bid recommendation committee and recommended to the Executive Director of PRASA that the bid be awarded to LONGO. On June 2, 1981, the Executive Director of PRASA approved the recommendation of the Board of Awards. Acting on behalf of EPA, the Department of the Army Corps of Engineers approved PRASA’s award on July 31, 1981.

A formal notice of award was not given to LONGO and a written contract was not signed because PRASA was unable to pay the share of the cost of the contract which it was committed to pay under the terms of the Grant agreement between PRASA and EPA. Due to the gravity of PRASA’s financial problems, EPA determined that PRASA did not possess and would not acquire in the near future the necessary financial resources to initiate construction of the project. EPA, therefore, commenced termination of the grant for failure to initiate construction within twelve months of grant award as required by 40 CFR 35.935-9(c). Upon termination of the grant, the deobligated funds were treated as fiscal year 1982 funds, which allowed PRASA an extra year until September 30, 1983, to reobligate said funds or lose them.

By Congressional action, financing was made available authorizing EPA to make loans to PRASA for the non-federal costs of this Grant including other grants related to five major PRASA waste treatment projects, Public Law No. 97-357, 33 USC Sec. 1282(c). Congress was concerned about Puerto Rico’s inability to meet its non-federal payment requirements because of circumstances beyond its control, which circumstances put in jeopardy $30 million in unobligated federal funds. Under the Congressional scheme to aid Puerto Rico, the Island could use said funds to finance [992]*992the non-federal share of five treatment projects currently under construction, but must repay that sum, with interest, to EPA.1

EPA and PRASA began immediately to make arrangements to utilize the authority for the loans. On March 17, 1983, EPA and PRASA entered into an agreement concerning 24 separate grant projects with a maximum loan amount available of $42,-497,323. Having EPA and PRASA agreed to terms in connection with the EPA loan commitment, and since the amendment to the statute required that all loans be made by September 30, 1983, the Director of the Water Management Division of EPA’s Regional Office, Mr. William J. Muszynski, notified PRASA by letter dated March 8, 1983, that all of the contracts proposed in the financial plan would have to be formally advertised and awarded through the competitive bidding process, as a condition for the loans, even though bids were received for some of said contracts many months ago.

Meanwhile, since November 23, 1982, LONGO had advised PRASA that it was willing to perform the contract if it was awarded to it because funding would be available.2 On numerous occasions after June 2, 1981, when the Executive Director of PRASA approved the recommendation of the Board of Awards that the bids be awarded to LONGO, plaintiff had corresponded, met and discussed with PRASA its lack of matching funds to undertake the projects. LONGO even offered to finance PRASA’s matching funds process by either purchasing bonds or some mutually beneficial method of financing. This was rejected by PRASA. Other correspondence had ensued between LONGO and PRASA. LONGO always asserted its willingness of constructing the Torrecilla Trunk Sewer. During all this time, PRASA represented to LONGO that the Torrecilla project would be awarded to said firm. Consequently, LONGO assumed that it had an entitlement to the contract and incurred in substantial expenses in connection thereto.3

Following EPA’s requirement as a condition for the commitment of funds to PRASA, the Executive Director of PRASA, Mr. Wilson M. Loubriel, wrote LONGO on April 14, 1983, advising that: “According to the conditions included in the loan agreement between EPA and this agency, the award of this project to the company cannot be granted because all projects within this agreement have to be formally advertised and awarded through the competitive bidding process even though bids were previously received for some of these projects. It was also agreed that if the new bids are higher than the previously received, EPA would participate in the additional cost of the projects.” Loubriel’s letter further notified plaintiff that because there were three major revisions to the plans and specifications on the project, according to EPA regulations, PRASA could not negotiate with the lower bidder because they may proceed with the protest pursuant to 40 CFR 35.939. The revisions to the project included:

a. deletion of Dislodge Transfer Line;
b. a change in the proposal from unit price to lump sum basis; and
c. the section of the Trunk Sewer crossing the proposed channalization of [993]*993Río Grande de Loiza was raised changing the item for excavation accordingly.

The letter closed with the invitation to LONGO to bid in the project that the Authority would advertise in the future.

Plaintiff protested under the procedure of EPA 40 CFR 35.939. Such procedures require that a protest be initially filed with and decided by the Grant recipient, in this case, PRASA. Having not received what it considered adequate response from PRASA, plaintiff requested EPA’s review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens to Preserve Overton Park, Inc. v. Volpe
401 U.S. 402 (Supreme Court, 1971)
City of New Brunswick v. Borough of Milltown
519 F. Supp. 878 (D. New Jersey, 1981)
Schiavone Const. Co., Inc. v. Samowitz
451 F. Supp. 29 (S.D. New York, 1978)
Jaillet v. Hill & Hill
460 F. Supp. 1075 (W.D. Pennsylvania, 1978)
Herbert F. Darling, Inc. v. Beck
442 F. Supp. 978 (W.D. New York, 1977)
Jaffee v. United States
592 F.2d 712 (Third Circuit, 1979)
Sea-Land Service, Inc. v. Brown
600 F.2d 429 (Third Circuit, 1979)
Everlasting Development Corp. v. Descartes
342 U.S. 954 (Supreme Court, 1952)
Muth v. Aetna Oil Co.
342 U.S. 954 (Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
575 F. Supp. 990, 21 ERC (BNA) 1591, 1983 U.S. Dist. LEXIS 11356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/longo-puerto-rico-inc-v-united-states-environmental-protection-agency-prd-1983.