Longhorn Estates LLC v. Charter Township of Shelby

CourtMichigan Court of Appeals
DecidedMarch 1, 2016
Docket324769
StatusUnpublished

This text of Longhorn Estates LLC v. Charter Township of Shelby (Longhorn Estates LLC v. Charter Township of Shelby) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Longhorn Estates LLC v. Charter Township of Shelby, (Mich. Ct. App. 2016).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

LONGHORN ESTATES, L.L.C., UNPUBLISHED March 1, 2016 Plaintiff/Counter Defendant,

v No. 324769 Macomb Circuit Court CHARTER TOWNSHIP OF SHELBY, LC No. 2011-001693-CZ

Defendant/Third-Party Plaintiff/Counter Plaintiff/Cross Plaintiff-Appellant,

v

CAPITAL CONTRACTING, INC.,

Defendant/Counter Plaintiff/Cross Defendant,

and

OHIO CASUALTY INSURANCE COMPANY,

Third-Party Defendant-Appellee,

ANDERSON ECKSTEIN & WESTRICK, INC.,

Third-Party Defendant.

Before: SAAD, P.J., and WILDER and MURRAY, JJ.

PER CURIAM.

Defendant Charter Township of Shelby (Shelby), appeals as of right the judgment entered after a jury trial in this action seeking payment under a maintenance and guarantee bond. Of relevance to this appeal, the trial court granted the motion for summary disposition filed by third-

-1- party defendant Ohio Casualty Insurance Company (Ohio Casualty), dismissing Shelby’s breach of the bond claims, and denied Shelby’s motion for relief from judgment. We affirm.

This case arises from the construction of a sanitary sewer system (the Project) on the property of plaintiff Longhorn Estates, L.L.C. (Longhorn). Shelby entered a contract with third- party defendant Anderson, Eckstein and Westrick, Inc. (AEW) to provide engineering services for the Project. Shelby hired defendant Capital Contracting, Inc. (Capital) to construct the Project. Based on the contract between Shelby and Capital, Ohio Casualty issued a maintenance and guarantee bond on July 21, 2008. The bond provided in relevant part:

[T]he above named principal has agreed with the said Owner that for a period of two years from the date of payment of Final Estimate, to keep in good order and repair any defect in all the work done under said contract either by the principal or his subcontractors, or his material suppliers, that may develop during said period due to improper materials, defective equipment, workmanship or arrangements, and any other work affected in making good such imperfections, shall also be made good all without expense to the Owner, excepting only such part or parts of said work as may have been disturbed without the consent or approval of the principal after the final acceptance of the work . . .

Construction of the project began in August 2008. AEW hired G2 Consulting Group to test Capital’s trench compaction during construction. The “Daily Reports” from G2 Consulting Group on August 28, 2008, August 29, 2008, September 17, 2008, September 18, 2008, and September 24, 2008, indicated that numerous field density tests were below the desired 90% compaction. On October 28, 2008, Steven Mancini, an authorized member of Longhorn, sent a letter to Shelby stating that additional compaction tests may be required and that final payment should not be made until the issue was resolved. On April 9, 2009, Mancini sent another letter to Shelby stating that there had been no response regarding the compaction testing and further payment should not be made to Capital until the issues were resolved.

Shelby hired Soil and Materials Engineers, Inc. (SME) to conduct a “Supplemental Geotechnical Evaluation” of the Project. A report from SME dated September 3, 2009, noted problems with the density of the backfill, but concluded that the sewer pipe “should function as intended.” On February 24, 2010, Shelby placed Capital on notice of defects in the Project, referencing the SME report, and demanded correction or repair. On March 8, 2010, Capital responded that there were no defects in its work.

The parties do not dispute that final payment, or “Final Estimate” under the bond, was made on December 13, 2010. On December 20, 2010, Somat Engineering, which was retained by Longhorn to evaluate compaction, indicated in a report that “the condition of the soil backfill above the sewer line is abysmal.” On February 17, 2011, Shelby demanded that Capital remedy the compaction issues.

On April 20, 2011, Longhorn filed a complaint against Shelby and Capital. On September 13, 2011, Shelby filed a third-party complaint against Ohio Casualty, alleging that Capital breached its contract with Shelby “by failing to compact the trench as required” and refused to remediate “the compaction defects.” Shelby further alleged that Ohio Casualty

-2- refused to respond to Shelby’s demand that it remediate the compaction pursuant to the bonds.1 Shelby claimed that Ohio Casualty breached its contract and sought damages. On December 13, 2011, Shelby filed a first amended third-party complaint, adding AEW as a defendant. The first amended complaint continued to refer to the alleged defect as “compaction.”

A Somat report dated July 17, 2012, noted settlement, leaking, as well as possible deformation of the pipe. Based on that report, on October 12, 2012, Shelby’s counsel sent a demand on the bond to Ohio Casualty.

On October 23, 2013, Ohio Casualty filed a motion for summary disposition on Shelby’s claims related to the maintenance and guarantee bond. Ohio Casualty argued that Shelby did not have a valid claim because the defect did not develop during the two-year period starting from the date of payment of the Final Estimate. Ohio Casualty further argued that, in its first amended third-party complaint, Shelby claimed that the lack of compaction was the defect, but this defect developed well before the final payment was made on December 13, 2010. Ohio Casualty contended that Shelby knew that Capital had not met the 90% compaction standard before making the final payment. Ohio Casualty also argued that Shelby had not incurred any damages that it could recover under the bond because, after Capital took no action in response to Shelby’s letter demanding that it implement remedial repairs, Shelby failed to perform the remedial repairs.

On November 7, 2013, the trial court granted, in part, Shelby’s motion for leave to file a second amended complaint, which was filed on October 21, 2013.2 The trial court took Ohio Casualty’s motion for summary disposition under advisement.

On November 21, 2013, Shelby filed a response to Ohio Casualty’s motion for summary disposition. Shelby argued that it had a valid claim under the bond because a defect may develop, due to improper materials and workmanship, within two years from the date of the final estimate. Shelby further argued that the two requirements of the bond were met because (1) Ohio Casualty conceded that there was “improper materials, defective equipment, workmanship or other arrangements” (“Deficient Work”), and (2) as a result of the Deficient Work, a defect developed during the coverage period, which was December 13, 2010, to December 13 2012, as Somat and SME concluded that the soil may fail during that period. Regarding the alleged defect, Shelby claimed that it “relied on the findings of SME and Somat that the failure to compact the backfill would lead to a defect—the soil settling more than permissible—if Longhorn constructed the planned improvements.” Shelby further argued that the bond only required that the defective settlement may occur during the coverage period; in other words,

1 Ohio Casualty also issued a Performance Bond, which is not at issue in this appeal. 2 According to the trial court’s opinion and order, Shelby moved to amend its third-party and cross complaints “in an effort to reflect the intent of the Amended Liquidation Agreement [between Longhorn and Shelby] and cure the issues identified in AEW and Ohio Casualty’s motions for summary disposition.” The trial court denied Shelby’s motion “to the extent that it seeks to state claims against Ohio Casualty under the Performance Bond.”

-3- Shelby or Longhorn was not required to build a road and utilities to prove that the defective settlement would occur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yee v. Shiawassee County Board of Commissioners
651 N.W.2d 756 (Michigan Court of Appeals, 2002)
Limbach v. Oakland County Board of County Road Commissioners
573 N.W.2d 336 (Michigan Court of Appeals, 1998)
Fisher v. Belcher
713 N.W.2d 6 (Michigan Court of Appeals, 2006)
Grzesick v. Cepela
603 N.W.2d 809 (Michigan Court of Appeals, 2000)
Bronson Methodist Hospital v. Auto-Owners Insurance
295 Mich. App. 431 (Michigan Court of Appeals, 2012)
Vittiglio v. Vittiglio
297 Mich. App. 391 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Longhorn Estates LLC v. Charter Township of Shelby, Counsel Stack Legal Research, https://law.counselstack.com/opinion/longhorn-estates-llc-v-charter-township-of-shelby-michctapp-2016.