Long Branch Sewerage Auth. v. Molnar Electrical Contractors, Inc.
This text of 363 A.2d 917 (Long Branch Sewerage Auth. v. Molnar Electrical Contractors, Inc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
LONG BRANCH SEWERAGE AUTHORITY, PLAINTIFF,
v.
MOLNAR ELECTRICAL CONTRACTORS, INC.; HEUER, INC.; WANDER IRON WORKS, INC.; C-K AIR CONDITIONING, INC.; SARBO, INC.; AMERICAN ARBITRATION ASSOCIATION, DEFENDANTS.
Superior Court of New Jersey, Chancery Division.
*493 Mr. Laurence C. Stamelman, for plaintiff (Messrs. Stein & Stamelman, attorneys).
Mr. Thomas L. Martin, for defendant Molnar Electrical Contractors, Inc. (Messrs. Ravin, Davis & Mandell, attorneys).
Mr. Ned J. Parsekian, for defendant Heuer, Inc.
Mr. Theodore W. Geiser, for defendant Wander Iron Works, Inc. (Messrs. McElroy, Connell, Foley & Geiser, attorneys).
YACCARINO, J.S.C.
Plaintiff filed an order to show cause and verified complaint seeking an order of arbitration. The matter was heard on the return date of the show cause order. The facts as revealed in the verified complaint indicate that plaintiff entered into a contract or contracts with defendant contractors for the construction of a wastewater treatment plant. The work was awarded to defendants in the following manner:
Contract 4A General construction Heuer, Inc.
Contract 4B Structural steel Wander Iron Works, Inc.
Contract 4C Plumbing C-K Air Conditioning, Inc.
*494 Contract 4D Heating/Ventilating Sarbo, Inc.
Contract 4E Electric Molnar Electrical Contractors, Inc.
While each contractor had a separate contract with plaintiff dealing with the specific work to be performed by the contractor, the contracts contained many of the same terms. One such common term related to arbitration and provided:
It is mutually agreed that any matters of controversy involving time or financial consideration that cannot be settled by the parties to this Contract shall be submitted to arbitration and that the award of the arbitrators, except when reached by fraud or mistake, shall be binding upon both parties.
Should there be any dispute or any questioned decision of the Owner or Engineer which is subject to arbitration, it shall be promptly submitted to arbitration upon demand by either party to the dispute. The Contractor shall not delay the work because arbitration proceedings are pending unless he shall have written permission from the Owner to do so, and such delay shall not extend beyond the time when the arbitrators shall have had the opportunity to determine whether the work shall continue or be suspended pending decision by the arbitrators of such a dispute. Any demand for arbitration shall be in writing and shall be delivered by the Owner and the adverse party either by personal delivery or by registered mail addressed to the last known address of each within ten (10) days of receipt of the Owners decision, and in no event after final payment has been made and accepted. Should the Owner fail within a reasonable period to make a decision, a demand for arbitration may then be made as if the Owner's decision had been rendered against the party demanding arbitration.
No one shall be qualified to act as an arbitrator who has directly or indirectly, any financial interest in the Contract or who has any business or family relationship with the Owner, the Contractor, or the Engineer. Each arbitrator selected shall be qualified by experience and knowledge of the work involved in the matter to be submitted to arbitration.
Arbitration shall be by and in accordance with the procedure and standards of the American Arbitration Association.
This was not a situation where the Authority engaged a general contractor who then employed subcontractors on the various phases of construction. It is important to note that the relationship between the various contractors was not contractual. They simply contracted with plaintiff to *495 perform particular portions of the project. The individual contractors had to have been aware that similar provisions for arbitration were in each contract, inasmuch as the provision was included in the specifications supplied to all bidders.
The contract completion date was December 4, 1975. The project was not completed by that date and is still in progress. The current schedule date for completion is September 5, 1976.
Defendant Molnar Electrical Contractors, Inc., has claimed delays caused by defendant Heuer, Inc., and by plaintiff. Defendant Heuer, Inc., claims that defendant Molnar has been responsible for the delay.
On or about June 3, 1976 defendant Molnar filed a demand for arbitration against plaintiff. Plaintiff sought to answer, counterclaim and third-party the other defendants into the arbitration. The American Arbitration Association (AAA) said there was no basis for such third-party arbitration practice, absent all parties consent. Molnar does not consent.
Plaintiff claims that it is necessary to conduct the arbitration as a unit to avoid conflicting claims and unnecessary expense in instituting separate arbitration proceedings.
Defendant Molnar has filed a brief and the affidavits of Mr. Patrick Westerkamp, a regional director of the AAA, Mr. John Molnar, president of defendant corporation, and Mr. Thomas Martin, counsel for defendant.
Defendant C-K Air Conditioning, Inc., has filed an answer which endorses the position of plaintiff, while defendant Sarbo, Inc., has answered seeking dismissal of the complaint.
The questions presented by this litigation are somewhat novel. In order to gain a proper perspective the history involved in the judicial attitude toward arbitration must be briefly reviewed. Justice Jacobs, in LaStella v. Garcia Estates, 66 N.J. 297 (1975), explained the relationship of the judiciary vis-a-vis arbitration as follows:
The English common law at the time of the American Revolution was undoubtedly hostile to arbitrations. See Frank, J., in Kulukundis *496 Shipping Co. v. Amtorg Trading Corp., 126 F.2d 987, 983 (2 Cir.1942), and Hough, J., in United States Asphalt R. Co. v. Trinidad Lake P. Co., 222 F. 1006, 1007 (S.D.N.Y. 1915). Thus it permitted either party to an arbitration of an existing dispute to withdraw at any time before the actual award, and, beyond that, it declared that an agreement to arbitrate future disputes was against public policy and not enforceable. See Kulukundis Shipping Co. v. Amtorg Trading Corp, supra, 126 F. 2d at 982-983; Birdseye, Arbitration and Business Ethics 62 (1926); cf. Sayre, "Development of Commercial Arbitration Law," 37 Yale L.J. 595 (1928). Whether the judicial hostility originated in ancient jealousies and fears of being ousted from jurisdiction (Lord Campbell in Scott v. Avery, 5 H.L. Cas. 811, 853, 10 Eng. Rep. 1121, 1138 (1856)) or whether it originated in less ignoble considerations (6A Corbin, Contracts § 1433 (1962) need not concern us; that there was in fact judicial hostility which must have had its effect on common law doctrines bearing on arbitrations would appear to be beyond dispute. See Shribman v. Miller, 60 N.J. Super. 182, 191 (Ch. Div. 1960).
The English common law permitting revocation prior to the award and declaring agreements to arbitrate future disputes to be unenforceable was carried over into the common law of the various states. See 6 Williston, Contracts § 1919 (Rev. ed 1938); 6A Corbin, supra, § 1433. In most states the common law has since been altered by statute. See 6
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
363 A.2d 917, 143 N.J. Super. 492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-branch-sewerage-auth-v-molnar-electrical-contractors-inc-njsuperctappdiv-1976.