Moreira Constr. Co., Inc. v. Wayne Tp.

238 A.2d 185, 98 N.J. Super. 570
CourtNew Jersey Superior Court Appellate Division
DecidedJanuary 19, 1968
StatusPublished
Cited by26 cases

This text of 238 A.2d 185 (Moreira Constr. Co., Inc. v. Wayne Tp.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moreira Constr. Co., Inc. v. Wayne Tp., 238 A.2d 185, 98 N.J. Super. 570 (N.J. Ct. App. 1968).

Opinion

98 N.J. Super. 570 (1968)
238 A.2d 185

MOREIRA CONSTRUCTION CO., INC., A NEW JERSEY CORPORATION, PLAINTIFF-APPELLANT,
v.
TOWNSHIP OF WAYNE, A BODY POLITIC, DEFENDANT-RESPONDENT.

Superior Court of New Jersey, Appellate Division.

Argued December 4, 1967.
Decided January 19, 1968.

*571 Before Judges CONFORD, COLLESTER and LABRECQUE.

*572 Mr. George J. Kenny for appellant (Messrs. Pindar, McElroy, Connell & Foley, attorneys).

Mr. Peter J. Van Norde for respondent.

The opinion of the court was delivered by CONFORD, S.J.A.D.

This is an appeal by a contractor on a contract to build a trunk sewer line for the Township of Wayne, from an order of the Chancery Division denying a demand for arbitration (except in one minor respect) by plaintiff contractor of claims for extras against defendant municipality. The claims for extras amount to $325,862.71. Performance of the contract took three years, and we are informed that the basic contract price was $444,782.40. The last work on the job seems to have been done about October 1964.

Apparently, sometime during the summer of 1966 (or perhaps earlier; the date is not specified in the appendix) plaintiff submitted to defendant a detailed 75-page specification of extras wherein each item claimed is broken down as to labor, materials, use of equipment and the date of rendition. In each case, also, there is a general indication of the reason for the particular extra, e.g., "change on plans, moving * * * sewer closer to brook * * *"; "removal two lengths of 24" R.C.P. ordered by the engineer * * *"; "due to wrong line and grade furnished by engineer * * * time lost"; "due to stop order of January 24, 1962"; "2.755 MFBM ordered by engineer"; "due to a water service * * * which was not shown on plans * * * lost 5 hours * * *," etc.

This specification of extras is not contained in the appendix nor was it an item of evidence before the trial court (which, without objection by any party, decided the matter on the return of an order to show cause on the basis of the pleadings, affidavits and argument). We requested it at the oral argument in order to have some minimal understanding of the basic dispute on the merits.

*573 The contract is apparently a lengthy document not made an exhibit. Certain sections of it are incorporated in the affidavits. The arbitration clause, construction of which is the central issue on this appeal, is set forth on page 39 of the specifications and reads as follows:

"(a) Appeal by the Contractor — Should the Contractor take exception to any determination of, or revision by the Engineer relating to the interpretation of this contract, or the performance of work thereunder, the Contractor shall, within two (2) days, after receiving notification of such decision, or revision, file with the Owner a notice of appeal therefrom, together with a full statement of facts as he believes them to be true, and he shall also furnish the Engineer a copy of said notice and statement of facts.

Upon completion of the work, all matters of appeal shall be submitted to a Board of Referees composed of three members, one of whom shall be appointed by the Owner, one by the Contractor, and the third shall be chosen by the first two. The cost of appeal shall be borne by the Contractor in matters wherein the decisions of the Engineer are affirmed, and in other matters, the costs shall be borne jointly by the Contractor and the Owner in such proportion as the Board of Referees shall determine.

The decision of the Board of Referees shall be conclusive and binding upon both the Contractor and the Owner."

Defendant argued below, and Judge Mountain in the Chancery Division agreed (with the one exception referred to above), that none of the presently disputed extra items became subject to arbitration under the foregoing agreement because they were never made "matters of appeal" by plaintiff in the manner specified by the contract, and only such matters of appeal were made subject to arbitration by the agreement of the parties. Plaintiff, on the other hand, argues that the question whether the disputed items are, indeed, "matters of appeal," is itself for the arbitrators rather than the court, because defendant's claim that they do not fall within the clause constitutes an issue of "procedural arbitrability," which, it is asserted, is always for determination by the arbitrator rather than the court. Prime reliance is placed on Standard Motor Freight, Inc. v. Local Union No. 560, 49 N.J. 83 (1967), and certain *574 decisions of the United States Supreme Court, all discussed hereinafter.

The factual record before us is not too illuminative.

On October 4, 1966 defendant's attorney wrote to plaintiff's attorney stating the township's position on the claim for extras theretofore submitted by plaintiff, as noted above. The letter offered a total of $9,807.02 in settlement of certain items and rejected the claims for the balance. It called attention to the fact that $79,014.65 of the items claimed pertained to a railroad crossing as to which an enclosed copy of a letter from plaintiff to defendant's consulting engineers of August 9, 1962 had stated that the work could be done "without any additional cost to the Township of Wayne."

Plaintiff's attorney responded by letter of October 13, 1966 indicating he was construing the letter of October 4, 1966 as "the decision of the Owner * * * and a disposition of the Contractor's appeal from the Engineer's decision." Stating that the determination by the owner was not satisfactory, the letter went on to "invoke the further provisions of the Contract," but quoting only the second and not the first paragraph of the arbitration clause (a) quoted hereinabove.[1] Request was made that the owner select its "member" arbitrator so that the arbitration could be instituted.

Defendant's attorney responded to the demand by its letter of November 14, 1966, that it was the "Township's position that if there is a dispute as to the amount to be paid under a valid claim such a matter is one for arbitration" but that "if there is a denial as to the validity of the claim, then it is not a proper subject for arbitration." This was followed by the present action in which defendant has abandoned the rationale for its rejection of the arbitration stated in the November 14 letter and stands on its position, stated above, and formulated in its answer to the complaint, *575 that the parties have not by their agreement undertaken to arbitrate these claims.

The record shows only one instance in the course of performance of this contract wherein the contractual "Appeal by the Contractor" (arbitration clause of the contract) was invoked. This occurred when, on October 1, 1962, plaintiff wrote the consulting engineer demanding an increase in the contract price for stone and the request was disallowed by the latter in a letter informing plaintiff that if it took exception to the decision it could proceed under the "Appeal by the Contractor Clause." Plaintiff thereupon notified the defendant, "we hereby appeal pursuant thereto" (the clause on page 39 of the specifications). The order under appeal herein directs arbitration of the claim for stone, but for that item only.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.H. v. the Lawrenceville School
New Jersey Superior Court App Division, 2026
SYMRISE, INC. v. KENNISON
D. New Jersey, 2024
Sarbak v. Citigroup Global Markets, Inc.
354 F. Supp. 2d 531 (D. New Jersey, 2004)
Camden Board of Education v. Alexander
854 A.2d 342 (Supreme Court of New Jersey, 2004)
Alamo Rent a Car, Inc. v. Galarza
703 A.2d 961 (New Jersey Superior Court App Division, 1997)
Commerce Bank, N.A. v. DiMaria Construction, Inc.
692 A.2d 54 (New Jersey Superior Court App Division, 1997)
Singer v. Commodities Corp.
678 A.2d 1165 (New Jersey Superior Court App Division, 1996)
Marchak v. Claridge Commons, Inc.
633 A.2d 531 (Supreme Court of New Jersey, 1993)
Casino Distributors, Inc. v. Teamsters Local 331
631 A.2d 993 (New Jersey Superior Court App Division, 1993)
Duerlein v. New Jersey Automobile Full Insurance Underwriting Ass'n
619 A.2d 664 (New Jersey Superior Court App Division, 1993)
Duerlein v. NJ AUTO. FULL INS.
619 A.2d 664 (New Jersey Superior Court App Division, 1993)
NJ Auto. Full Ins. v. Jallah
606 A.2d 839 (New Jersey Superior Court App Division, 1992)
Board of Educ. v. EDUC. ASS'N
598 A.2d 518 (New Jersey Superior Court App Division, 1990)
Cohen v. Allstate Ins. Co.
555 A.2d 21 (New Jersey Superior Court App Division, 1989)
Laborers' Local Union Nos. 472 & 172 v. Interstate Curb & Sidewalk
448 A.2d 980 (Supreme Court of New Jersey, 1982)
Barcon Associates, Inc. v. Tri-County Asphalt Corp.
430 A.2d 214 (Supreme Court of New Jersey, 1981)
Aysseh v. Lawn
434 A.2d 1146 (New Jersey Superior Court App Division, 1981)
Brick Tp. Mun. Util. Auth. v. Diversified RB & T. Construction Co.
409 A.2d 806 (New Jersey Superior Court App Division, 1979)
J. Baranello & Sons, Inc. v. City of Paterson
403 A.2d 919 (New Jersey Superior Court App Division, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
238 A.2d 185, 98 N.J. Super. 570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moreira-constr-co-inc-v-wayne-tp-njsuperctappdiv-1968.