Lonergan v. Waldo

60 N.E. 479, 179 Mass. 135
CourtMassachusetts Supreme Judicial Court
DecidedMay 24, 1901
StatusPublished
Cited by11 cases

This text of 60 N.E. 479 (Lonergan v. Waldo) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lonergan v. Waldo, 60 N.E. 479, 179 Mass. 135 (Mass. 1901).

Opinion

Barker, J.

The question whether the verdict was ordered

rightly must be considered upon the state of facts most favorable to the plaintiff, which fairly could have been found if the case had been left to the jury.

He contended that he was entitled to large damages because of the caving in of a ditch resulting from the non-delivery of six inch drain pipe bought of the defendant on May 1, 1893, for the price of $13.50, then paid.

From his testimony it could be found that he first ordered the pipe on Thursday, April 28, by telephone, and that in giving the order he said that he was out of such pipe, and had his ditch all ready waiting for it, and a great deal of material on the bank, and that he could not leave it there very long; also that the answer to his order was that the pipe would be sent in the afternoon ; that the pipe did not come, and the plaintiff several times told the defendant’s agent over the telephone that it was necessary that the pipe should come out; that if a rain storm should come there was no possible chance of saving the ditch, as they were down twenty-four feet and there was a large amount of material on the banks.

The plaintiff further testified that on Monday; May 1, he was informed that the trouble was that he had reached the limit of his credit with the defendant; that he then went to the latter’s office, was referred from one man to another and another, to the last of whom he told the dangerous condition he was in at the work and how much he was in need of the pipe; that he told them the condition of the ditch, that it was down twenty-four feet, and about nine or ten feet wide, and would certainly cave in if there should be a rain storm; that they desired cash for any more goods, and thereupon he gave a check for the price of the pipe, and asked if they would attend to it right away; that they said that they would, that the pipe would be out there [137]*137perhaps before he was, and thereupon he went back to the work; that at noon on Monday the pipe had not reached the work, and he then telephoned again and asked where the pipe was, and was answered that it would be out there in the afternoon sure; that he then waited until Tuesday morning, and then asked by telephone why the defendant would not send the pipe, saying that the defendant knew the plaintiff’s condition at the work, and what the consequence would be, and was answered that the defendant would immediately attend to it; that no pipe came on that day, Tuesday, May 2, and none came on Wednesday, May 3, until after the plaintiff’s men had gone home; and that the pipe which so came was not six inch pipe as ordered and purchased but eight inch pipe which he could not place in the ditch, and which he would not be allowed to. use in it; also that a rain storm came on during Wednesday night, and on Thursday about noon the ditch was washed in, at a loss to him of about $1,240.

The plaintiff also testified that the ditch was sheathed with plank and was braced and that he had taken all the precautions to prevent its caving in whiéh could be taken, and that the weather was threatening, and that he made no effort in any other direction to get the pipe. He also testified upon his cross-examination, as follows:

“ Q. When they kept promising you and kept disappointing you, did you make any effort in any other direction to get that pipe? A. No.
Q. Do you know that within an eighth of a mile from your place there was a store that had been established for thirty years which kept drain pipe, and which could have furnished you that pipe at practically a moment’s notice ? A. I think I had gone to them, as you have refreshed my memory, and I think I have got 6-inch pipe, all they had there, I think, I have bought —
Q. You did buy some 6-inch pipe from Balkam, did you ? A. I can’t swear to it, but I am very sure I went down there for 6-inch pipe. I did n’t buy any prior to this time.
Q. You knew where the store was ? A. I did n’t know that they had 6-inch pipe.
Q- You didn’t inquire ? A. I must have inquired if I found out that he had it. I think I was down to him to buy some nails — some things like that, little incidentals that we would want.”

[138]*138The defendant offered evidence tending to show that no conversations occurred over the telephone or at his store such as the plaintiff testified to; that nothing was said about the danger to the ditch ; that no suggestion was made as to any special haste; that the pipe was sold to be, and was, delivered in the usual course of business the next day, May 2.

Experts called by the defendant testified that there was a perfectly practical way of protecting the ditch in question against caving in, and that if the plaintiff had used it the ditch would not have caved in.

Sewall D. Balkam, called by the defendant, testified that his place of business was, and had been since 1872, on Centre Street, Jamaica Plain, about five or six minutes’ walk from where the plaintiff was at work on the corner of Weld Park and the same street, Centre Street; that at the time in question he dealt in six inch pipe, and had it in stock for sale, and that its then fair market value in Jamaica Plain, delivered at Weld Park, was ten to twelve cents a foot, or from $15 to $18 for one hundred and fifty feet.

In reply to a question from the court the plaintiff’s counsel said that he did not claim to recover for any delay in delivery prior to May 1 when the pipe was paid for. In reply to another question from the court he said that he did not want to go to the jury on any question of damage other than the damage done by the washing in of the ditch, and the expense entailed in rebuilding the ditch.

The court ruled, on taking the case from the jury, “ I do not think that the plaintiff can recover in this action, which is an action of contract, for the damage done to the trench or ditch by tbe rainstorm, or for the expenses incurred in repairing that damage. The plaintiff’s counsel says that is the damage which he seeks to recover for, and the other damage will be so slight that he does not care to go to the jury upon it. In view of this statement I will order a verdict for the defendant, and the plaintiff excepts.”

Upon this state of the evidence it could not be ruled as a matter of law that the plaintiff was negligent in relying wholly upon the expected delivery, and in making no effort to get pipe elsewhere: nor in the means which he used to protect the ditch [139]*139from caving in. It could be found from the evidence that the purchase and sale were made upon a full disclosure of the special circumstances to which the plaintiff testified, and that both parties acted upon full knowledge that the pipe sold was bought by the plaintiff to be used in a ditch such as ,was described in his testimony; and that at the time of the sale, the caving in of the ditch was to be apprehended reasonably as a consequence of delay, and if the delay should be caused by failure to deliver the pipe the caving in might be found to be a damage which ordinarily would follow the breach.

If goods sold and paid for are not delivered the measure of damages usually is their market value at the time and place at which they should have been delivered, with interest thereon. Cutting v. Grand Trunk Railway, 13 Allen, 381, 385.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Queen City Terminals, Inc. v. Gen. Am. Transp. Corp.
1995 Ohio 285 (Ohio Supreme Court, 1995)
American Mechanical Corp. v. Union MacHine Co. of Lynn, Inc.
485 N.E.2d 680 (Massachusetts Appeals Court, 1985)
Stratton v. Posse Normal School of Gymnastics
265 Mass. 223 (Massachusetts Supreme Judicial Court, 1928)
Scofield v. Barowsky
249 Mass. 1 (Massachusetts Supreme Judicial Court, 1924)
Snyder v. Sargeant
197 Iowa 475 (Supreme Court of Iowa, 1923)
Fairbanks, Morse & Co. v. Austin
288 F. 1 (Ninth Circuit, 1923)
Horace Turner & Co. v. Munson S. S. Line
77 So. 61 (Alabama Court of Appeals, 1917)
McConnell v. United States Express Co.
146 N.W. 428 (Michigan Supreme Court, 1914)
Bixby-Theirson Lumber Co. v. Evans
52 So. 843 (Supreme Court of Alabama, 1910)
C. W. Hunt Co. v. Boston Elevated Railway Co.
85 N.E. 446 (Massachusetts Supreme Judicial Court, 1908)
Weston v. Boston & Maine Railroad
76 N.E. 1050 (Massachusetts Supreme Judicial Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.E. 479, 179 Mass. 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lonergan-v-waldo-mass-1901.