Lone Mountain Production Co. v. Natural Gas Pipeline Co. of America

710 F. Supp. 305, 1989 WL 33794
CourtDistrict Court, D. Utah
DecidedApril 5, 1989
DocketCiv. 87-C-0187 A
StatusPublished
Cited by10 cases

This text of 710 F. Supp. 305 (Lone Mountain Production Co. v. Natural Gas Pipeline Co. of America) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lone Mountain Production Co. v. Natural Gas Pipeline Co. of America, 710 F. Supp. 305, 1989 WL 33794 (D. Utah 1989).

Opinion

MEMORANDUM DECISION

(In Lieu of Findings of Fact and Conclusions of Law — FRCP 52(a))

ALDON J. ANDERSON, Senior District Judge.

The plaintiff, Lone Mountain Production Company (“Lone Mountain”), brought this action to enforce the terms of a ten-year “take or pay” gas purchase contract under which its alleged predecessor in interest, GEO Oil and Gas Company of Houston (“GEO”), agreed to sell gas to the defendant, Natural Gas Pipeline Company of America (“Natural”).

Trial was bifurcated, with a non-jury trial being held on September 12-13, 1988 to determine Natural’s liability under the contract. At the conclusion of the trial, the court took the matter under advisement and invited the parties to submit post-trial briefs.

For reasons discussed below, the court finds that Lone Mountain is entitled to enforce the contract against Natural.

FACTUAL BACKGROUND

On June 8,1971, the State of Utah issued Mineral Lease 27564 covering a 600-acre tract located in Section 32, T16S, R26E, SLB & M to the Anschutz Corporation, Inc. (Plaintiffs Exhibit “1”). By April 1980, the lease had been divided into two parcels of 280 and 320 acres each. The lease had also been segregated vertically into upper and lower strata at a level 4,338 feet deep.

On April 18, 1980, Natural signed three contracts to purchase gas from the owners of interests in the upper stratum of the 280-acre parcel. (See Plaintiff’s Exhibits “3-5”.) The three contracts have identical terms. 1 They differ only in the identity of the sellers and the identity of the leasehold interests each seller committed to performance of the contract. The contracts enabled Natural to obtain the exclusive right to purchase all gas produced from the segregated parcel, regardless of who might ultimately become its owner. 2

The contracts require Natural either to take the gas at the contract price and in the contract quantities or to pay for the gas and take it at a later date. These “take or pay” contracts, common in oil and gas transactions, give the seller access to a delivery system and market for its gas, while assuring the buyer of a gas supply at the bargained-for contract price. See 4 H. Williams, Oil and Gas Law § 724.5 (1988).

The first gas purchase contract was with GEO, which owned 100% of the operating rights (the working interest minus the royalty interest), subject to a 6Vi% overriding royalty and a reversionary interest. The second contract was with Texoma Company (“Texoma”), which owned 50% of both the overriding royalty and the reversionary interest. The third contract was with Nicor Exploration Company (“Nicor”), which owned the remaining 50% of the overriding royalty and the reversionary interest.

The reversionary interest gave Texoma and Nicor the option to convert their overriding royalty into a 50% working interest upon payout.

Quinoco Oil & Gas Programs (“Quinoco”) succeeded to GEO’s interest, and MidCon Central Exploration Company (“MidCon”) succeeded to Texoma’s interest. The options to convert the overriding royalty into a working interest were exercised. Thus, Natural recognizes that the succession and/or titles to the operating rights were as follows: Quinoco 50%, Nicor 25% and MidCon 25% (Pretrial Order, at 20.).

Lone Mountain then entered into farm-out agreements with Quinoco, Nicor and MidCon (Plaintiff’s Exhibits “14-16”). Under the farmout agreements, Lone Mountain would receive all of Quinoco’s and *308 Nicor’s operating rights and most of Mid-Con’s operating rights in exchange for drilling a producing well.

MidCon assigned its operating rights to Apache Corporation (“Apache”) (Plaintiffs Exhibit “21”).

Lone Mountain succeeded in drilling a producing well and received the promised assignments of operating rights from Qui-noco, Nicor and Apache (Plaintiff’s Exhibits “18-20” & “22”).

Before beginning to drill on the contract acreage, Lone Mountain notified Natural that Quinoco had designated it as operator, that it intended to drill a well, that the well location was committed under the GEO contract, 3 and that the drilling operations would commence by May 15, 1986 (Plaintiff’s Exhibit “17”). Natural did not respond to this notification.

Upon completion of the well, Lone Mountain provided Natural with state completion notices and a drilling and completion history (Plaintiff's Exhibit “23”). Pursuant to the GEO contract, Lone Mountain then made demand upon Natural to connect the well to its gathering system.

On July 22, 1986, Natural acknowledged that the well had been submitted for contract consideration and demanded that its delivery agent, Northwest Pipeline Company, establish a point of delivery (Plaintiff’s Exhibit “36”). However, on September 9, 1986, Natural declined to connect Lone Mountain’s well to its gathering facilities, invoking the force majeure clause of the GEO contract (Plaintiff’s Exhibits “24” & “30”). Natural requested copies of the assignments of interest and farmout agreements and offered to release Lone Mountain from its obligations under the GEO contract (Plaintiff’s Exhibit “26”).

On September 30, 1986, Lone Mountain advised Natural of its intent to exercise the option of proceeding on its own to connect the well to the gathering facilities (Plaintiff's Exhibit “25”). Natural then directed Lone Mountain to coordinate the pipeline connection. Lone Mountain made the connection at a mutually acceptable point on October 15, 1986, at a cost of $25,000.00.

On December 2, 1986, Lone Mountain furnished Natural with copies of its assignments of interest and farmout agreements (Plaintiff’s Exhibit “31”). By letter dated December 9, 1986, Natural replied that it would recognize Lone Mountain’s interest in the gas “with the understanding that a succession letter agreement substantially in the form of the attached will be exe-cuted_” (Plaintiff’s Exhibit “32”). On February 17, 1987, Lone Mountain sent Natural the executed succession agreements in the requested form (Plaintiffs Exhibits “33” & “34”).

Lone Mountain commenced this action to enforce the GEO contract on March 6, 1987.

ISSUES

On January 14, 1988, nearly two years after the well connection was made, Natural began arguing that a formal contractual assignment was needed, in addition to the succession agreements.

Before this action was commenced, Natural sought to justify its failure to perform on the basis of force majeure. During the course of the litigation, Natural argued that its failure to perform was justified because of impossibility of performance, commercial impracticability, frustration of purpose, and because the' “take or pay” provision is contrary to public policy and the original intent of the parties. At trial, Natural dropped these defenses and instead asserted that the farmout and succession agreements did not constitute a proper assignment of the original contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
710 F. Supp. 305, 1989 WL 33794, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lone-mountain-production-co-v-natural-gas-pipeline-co-of-america-utd-1989.