Lommen v. Adolphson & Peterson Construction Co.

168 N.W.2d 673, 283 Minn. 451, 1969 Minn. LEXIS 1174
CourtSupreme Court of Minnesota
DecidedMay 29, 1969
Docket41378
StatusPublished
Cited by4 cases

This text of 168 N.W.2d 673 (Lommen v. Adolphson & Peterson Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lommen v. Adolphson & Peterson Construction Co., 168 N.W.2d 673, 283 Minn. 451, 1969 Minn. LEXIS 1174 (Mich. 1969).

Opinion

Rogosheske, Justice.

Appeal from an order of the district court denying defendant’s alternative motion for judgment notwithstanding a jury verdict or a new trial.

On January 13, 1964, plaintiff suffered serious injuries as the result of a fall from a scaffold while installing a folding partition during the construction of the Minnetonka West Junior High School gymnasium. The folding partition was designed to operate upon a track supported by a large, steel, I-shaped, double bar joist which extended across the full *452 80-foot width of the ceiling of the gymnasium approximately 20 feet above the floor. Defendant was the general construction contractor and had subcontracted the furnishing and installation of the partition to Mahin-Walz Company, which in turn had subcontracted the actual installation of the partition to plaintiff’s employer, the Jerry Fisher Company.

To hide the steel bar joist from view and to aid in soundproofing, defendant was required to “box in” the bar joist by covering it with plywood panels. This was to be accomplished by constructing a framework of two-by-fours to which the plywood panels would be nailed. Two-by-fours, 16 feet in length, were ram-set 1 horizontally, wide side down, inside both the top and the bottom flanges of the I-shaped bar joist. To keep these two-by-fours firmly in place for ram-setting, two-by-fours about 3 Vi feet long were wedged between them vertically at about 4-foot intervals. After the horizontal two-by-fours were secured to the steel flanges with ram-set spikes, the vertical wedges were removed and vertical two-by-fours about 4 feet in length, which extended about 4Vi inches below the bottom of the bar joist, were then permanently nailed, wide side out, to the outside edge of the horizontal two-by-fours at 16-inch intervals. The plywood panels were then nailed to the vertical two-by-fours.

When the boxing-in had been completed to within 20 feet of the north wall, defendant’s carpenters had to stop until the remainder of the track assembly and the partition had been installed. Eight to ten feet of horizontal two-by-fours extended beyond the point where the plywood sheathing ended, both above the bottom flange and below the top flange of the bar joist.

These visible horizontal two-by-fours could not be permanently ram-set to the bar joist because the clamps which were to hold the remaining track assembly to the bar joist when it was installed had to be fastened to the steel bar joist beneath the two-by-fours. In order to keep these two-by-fours from warping before they could be ram-set, defendant’s carpentry foreman wedged the 3 Vi-foot two-by-fours, narrow side *453 out, vertically between them, one of the vertical two-by-fours being placed about 4 feet beyond the point at which the plywood sheeting ended. Without moving the scaffold upon which he was working, so that he could reach the top as well as the bottom of this wedge, defendant’s foreman leaned out from the scaffold and, after jamming the wedge into place, secured it only with a small sixpenny nail, toe-nailed at its base.

Plaintiff, intending to throw a rope over the bar joist so that the heavy crate containing the partition could be moved into place without damaging the gymnasium floor, climbed the end of a tubular steel scaffold placed under the bar joist. He stopped at a point where the top of the scaffold was near his waist and threw the rope over the bar joist. The rope did not fall far enough over the joist for the workmen on the floor to reach it. Thereupon, plaintiff reached up to feed it over the joist by hand and, in doing so, with his right hand grabbed the vertical two-by-four which had been placed about 4 feet beyond the plywood sheeting. The top of the two-by-four moved out and plaintiff fell from the scaffold, sustaining substantial injuries.

He brought suit against defendant, alleging that it had been negligent in its use of the temporary vertical wedge which he sought to use as a “handhold.” Plaintiff recovered a jury verdict of $15,000. Defendant moved alternatively for judgment notwithstanding the verdict on the grounds that (1) defendant had not violated any duty which it had toward plaintiff, (2) plaintiff had failed to establish that any negligent act by defendant was the proximate cause of plaintiff’s injuries, (3) plaintiff was contributorily negligent as a matter of law, and (4) that he assumed the risk as a matter of law, or for a new trial. This motion was denied and defendant appeals.

On appeal defendant makes three basic arguments: (1) That as a matter of law defendant had no duty to foresee that someone might use the temporary wedge as a handhold; (2) that the trial court erred in not expressly instructing the jury that plaintiff, in order to recover, must have established that defendant should have foreseen that someone was likely to use the wedge as a handhold; and (3) that plaintiff in using the wedge as a handhold was contributorily negligent as a matter of law.

*454 Defendant argues here, as before the trial court, that its employees had no duty to anticipate that someone would use this “obviously temporary” wedge as a handhold. Plaintiff, on the other hand, argues that defendant’s foreman was negligent in using only one small nail to secure this wedge, which deceptively appeared to be a part of the permanent construction, when he knew the partition construction crew would be working in that area.

Since it is undisputed that defendant’s employees knew that the partition contractor’s employees would be working in close proximity to the wedge while installing the folding partition, resolution of the issue of foreseeability of the risk depends upon whether the evidence permitted the jury to conclude that defendant’s foreman should have reasonably foreseen that one of these employees would assume that the wedge was a permanent part of the construction and would use it as a handhold. Clearly, if the evidence does not permit that conclusion, defendant’s argument is correct, for its employees had no duty to foresee any improbable or unusual use of obviously incomplete or temporary construction. Italiano v. Jeffrey Garden Apts. Section II, 3 App. Div. (2d) 677, 159 N. Y. S. (2d) 338, affirmed, 3 N. Y. (2d) 977, 169 N. Y. S. (2d) 737, 147 N. E. (2d) 245. See, McDonald v. Fryberger, 233 Minn. 156, 46 N. W. (2d) 260.

Viewing the evidence in the light most favorable to sustain the jury’s verdict, as we must, there is sufficient evidence from which the jury could reasonably conclude that the wedge did appear to be a part of the permanent construction and that construction workers commonly do use permanent studs as handholds. Plaintiff testified that not only was the use of vertical studs between horizontal two-by-fours a common method of permanent construction of framework for plywood sheeting but also that it was the only type with which he was familiar. Furthermore, it is a fair inference from the testimony of defendant’s superintendent and foreman that this was a common method of permanent construction, especially in view of the foreman’s failure to deny that such studs were left in the other part of the permanent construction which had been enclosed with plywood sheeting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gfroerer v. Menard, Inc.
D. Minnesota, 2021
Van Tassel v. Hillerns
248 N.W.2d 313 (Supreme Court of Minnesota, 1976)
Wilson v. State
208 N.W.2d 134 (Wisconsin Supreme Court, 1973)
Berry v. Haertel
170 N.W.2d 558 (Supreme Court of Minnesota, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
168 N.W.2d 673, 283 Minn. 451, 1969 Minn. LEXIS 1174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lommen-v-adolphson-peterson-construction-co-minn-1969.