Lockheed Martin Corp. v. United States

664 F. Supp. 2d 14, 2009 U.S. Dist. LEXIS 98167, 2009 WL 3316846
CourtDistrict Court, District of Columbia
DecidedSeptember 29, 2009
DocketCivil Action 08-1160 (JR)
StatusPublished
Cited by2 cases

This text of 664 F. Supp. 2d 14 (Lockheed Martin Corp. v. United States) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Corp. v. United States, 664 F. Supp. 2d 14, 2009 U.S. Dist. LEXIS 98167, 2009 WL 3316846 (D.D.C. 2009).

Opinion

MEMORANDUM ORDER

JAMES ROBERTSON, District Judge.

From 1961 to 1975, the Lockheed Propulsion Company 1 developed and manufactured rocket systems for the United States government at three facilities in southern California (collectively, “the Site”). In the 1990s, state and federal agencies discovered chemical contamination in the soil and groundwater surrounding the Site and ordered Lockheed to prepare and implement a remedial action plan. Lockheed alleges that it has spent, and will continue to spend, millions of dollars to comply with that order. In this suit, it seeks to recover response costs from the United States under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), alleging that the government arranged for the disposal of chemical contaminants and effectively owned and operated the Site. See 42 U.S.C. § 9607.

The government moves for summary judgment on its so-called “double recovery defense.” The defense is a two-step argument: (1) that collateral estoppel requires the Court, and Lockheed, to accept the determination in Procter v. Lockheed Corp., Case No. 731752 (Cal.Super.Ct. Oct. 22, 2003), that the government is in fact reimbursing Lockheed for the response costs it incurs at the Site through various government contracts; and (2) that, because Lockheed is already being reimbursed by the government, it cannot recover response costs again under CERCLA.

Lockheed counters with a motion under Federal Rule of Civil Procedure 56(f), seeking leave to conduct additional discovery before responding to the government’s motion. It also moves for judgment on the pleadings that the government’s second and sixteenth affirmative defenses (which assert the double recovery defense) are invalid as a matter of law.

The government’s motion and Lockheed’s Rule 56(f) motion will be denied. Lockheed’s motion for judgment on the pleadings will be granted in part.

Background

In a conventional CERCLA case, the plaintiff seeks a ruling that the defendant (commonly referred to as the “potentially responsible party” or “PRP”) is liable for some portion of the response costs at a particular site. This is such a case, but it is complicated by the fact that the PRP— *16 the government — is also the plaintiffs largest client. Lockheed generates most of its revenue from government contracts, and the nature of those contracts creates the rub of this case.

The government pays its contractors in accordance with a byzantine set of rules known as the Federal Acquisition Regulation (FAR). Pursuant to the FAR, the government pays contractors their “direct” costs and their “indirect” costs, plus a profit. Direct costs are costs related to a specific contract, such as materials and labor. See 48 C.F.R. § 52.216-7(b). Indirect costs are costs that are not associated with a specific contract — essentially, overhead. Id. § 52.216-7(d).

The government will only reimburse a contractor for indirect costs that are “allowable” — “incurred by a reasonably prudent business person” — “allocable,” and not otherwise disallowed. Id. §§ 31.201-2, 201-3, 201-4. Environmental cleanup costs can be treated as indirect costs if they meet these three criteria.

During contract performance, a contractor can submit invoices (as frequently as every two weeks) requesting payment for certain costs, including “[p]roperly allocable and allowable indirect costs.” Id. § 52.216-7(b)(1)(F). These are only interim payments; once contract performance is complete, the government can pay more (as it usually does) or ask for a refund, depending on its final indirect cost calculations.

In the 1980s and 1990s, federal and state environmental agencies discovered contaminants at several of Lockheed’s former research and development facilities and ordered Lockheed to develop and implement remediation plans. As the response costs piled up, Lockheed found itself in disputes with both the government-as-client and the government-as-PRP. Lockheed and the government-as-client entered into negotiations about whether the response costs were “allowable” indirect costs, and, if so, how they should be allocated across Lockheed’s various government contracts. Simultaneously, Lockheed named the government as a PRP in United States v. Lockheed Martin Corp., No. 91-4527-MRP (C.D.Cal.), a CERCLA suit about the parties’ respective liability for response costs at Lockheed’s former research facility in Burbank.

The parties resolved the Burbank suit by agreement in January 2000. To discharge the CERCLA claim against it, the government agreed to pay a percentage of Lockheed’s past and future response costs at the site, plus interest. See Dkt. 26, Ex. 1, at 8-9. Under the terms of the consent decree, as Lockheed incurred costs, it would submit periodic reimbursement requests to the government, which would pay its share of the costs directly to Lockheed (not through any existing or future government contracts). Id., at 9-10. The agreement specified that the government-as-client could not defray the costs owed to Lockheed by the government-as-PRP: While the government could dispute Lockheed’s reimbursement requests on certain enumerated grounds, it could not challenge a request on the ground that the costs had been “previously reimbursed by the United States or another party through an overhead pool pursuant to contracts between Lockheed and any other person or entity, including the United States.” Id., at 13.

In September 2000, Lockheed and the government-as-client settled their dispute over the billing of Lockheed’s response costs. Their agreement (the “Billing Settlement”) defined “Settled Discontinued Operations Costs” as the response costs that Lockheed had incurred, or would incur, at facilities it had closed before January 1, 2000, including costs incurred at the Site at issue in this case and at the Bur *17 bank site. Dkt. 25, Ex. 3, § 1.8. The amount of Settled Discontinued Operations Costs would then be reduced in gross by $96 million 2 to form the “Discontinued Operations Pool.” Id. ¶ 2.1. The amount remaining in the Discontinued Operations Pool would be considered “allowable” indirect costs, id. ¶2.5, and allocated across Lockheed’s various business divisions according to a three-factor formula, id. ¶ 2.8. The business divisions could then treat their allocated portion of the Discontinued Operations Pool as indirect costs on their government contracts.

The Billing Settlement accounted for the parties’ agreement in the Burbank CERCLA suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lockheed Martin Corporation v. United States
833 F.3d 225 (D.C. Circuit, 2016)
Lockheed Martin Corporation v. United States
35 F. Supp. 3d 92 (District of Columbia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
664 F. Supp. 2d 14, 2009 U.S. Dist. LEXIS 98167, 2009 WL 3316846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-corp-v-united-states-dcd-2009.