Lockheed Martin Corp. v. RFI Supply, Inc.

440 F.3d 549, 2006 U.S. App. LEXIS 6832, 2006 WL 668711
CourtCourt of Appeals for the First Circuit
DecidedMarch 17, 2006
Docket05-1737, 05-1831
StatusPublished
Cited by26 cases

This text of 440 F.3d 549 (Lockheed Martin Corp. v. RFI Supply, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Corp. v. RFI Supply, Inc., 440 F.3d 549, 2006 U.S. App. LEXIS 6832, 2006 WL 668711 (1st Cir. 2006).

Opinion

TORRUELLA, Circuit Judge.

This case involves three parties: Plaintiff Lockheed Martin Corporation (“Lockheed”), Defendant Rantec Power Systems, Inc. (“Rantec”), and Third-Party Defendants Factory Mutual Research Corporation (“FMRC”) and Factory Mutual Insurance Corporation (collectively, the “FM Entities”). Lockheed appeals the district court’s grant of Rantec’s motion for summary judgment against Lockheed. Ran-tec, in turn, appeals the district court’s grant of the FM Entities’ motion for summary judgment against Rantec. We affirm the district court’s grant of Rantec’s motion for summary judgment against Lockheed and do not reach the district court’s grant of the FM Entities’ motion for summary judgment against Rantec. 1

1. Factual Background and Procedural History

A. Lockheed and Rantec

Lockheed is an advanced technology company incorporated in Maryland that also has its principal place of business in Maryland. Rantec is a Delaware corporation with its principal place of business in Missouri. Rantec designs and constructs anechoic chambers. 2 On April 15, 1992, *551 Lockheed and Rantec entered into a written contract in which Rantec agreed to design and construct an anechoic chamber at a Lockheed facility in Merrimack, New Hampshire. As part of the contract, Ran-tec was required to “design, fabricate, and install a fire detection and sprinkler system” in the chamber. The contract contained a warranty clause providing that “[a]ll equipment and workmanship shall be guaranteed to be free from defects by [Rantec] for a period of one (1) year after final acceptance, unless a different warranty is specified.” Rantec completed construction of the chamber in late 1992, and final acceptance occurred in 1993.

The fire detection system consisted of, inter alia, smoke detectors, fire alarms, valves, telescoping sprinkler assemblies (“TSAs”), and sprinkler heads. The TSAs were retracted above and outside the chamber and were designed to extend into the chamber when the detection system identified smoke or fire but not immediately release water. Once the temperature exceeded a certain level, a fusible link incorporated in the sprinkler head would melt and water would be released into the chamber.

The present case stems from two incidents involving flooding of Lockheed anechoic chambers. In December 1996, an anechoic chamber at a Lockheed facility in California suffered water damage when three of the TSAs broke and water flooded the chamber. On March 27, 1997, the sprinkler system at the anechoic chamber in New Hampshire malfunctioned. The fire suppression system activated due to a defect in an electronic panel sold and installed by another contractor not party to this suit. The TSAs extended and some of the sprinkler heads broke and released a large amount of water into the chamber. The foam and sub-flooring of the chamber suffered $400,000 of damage. According to Lockheed, also damaged by the flood were a pedestal and positioning system costing over $160,000. These items were not provided under the contract with Ran-tec. Lockheed did not include these items in its complaint and did not amend its complaint to add these items. 3

On December 20, 1999, Lockheed brought suit against Rantec in the United States District Court for the Northern District of California, 4 alleging claims stemming from the incidents in California and New Hampshire. On August 29, 2000, the district court in California severed Lockheed’s New Hampshire claims, and the parties then stipulated to transfer the New Hampshire claims to the United States District Court for the District of Massachusetts. Lockheed raised the following claims regarding the New Hampshire events: (1) negligence, (2) strict liability, and (3) implied warranties.

B. Rantec and the FM Entities

FMRC performs testing, issues product standards, and publishes a directory of “FM Approved” products for use in fire suppression systems. Rantec’s claims against the FM Entities stemmed from FMRC’s approval of Rantec’s TSAs on the condition that they be equipped with certain sprinkler heads — the sprinkler heads that broke when the TSAs extended into Lockheed’s anechoic chamber. After Lockheed sued Rantec, Rantec moved to add the FM Entities as Third-Party Defendants pursuant to Rule 14(a) of the Federal Rules of Civil Procedure. In their briefs, Rantec and the FM Entities dispute *552 when Rantec filed its Third-Party complaint against the FM Entities. Because we are not reaching Rantec’s appeal regarding the grant of summary judgment in favor of the FM Entities, we do not address this issue.

C. Proceedings Below

On April 12, 2001, Rantec moved for summary judgment against Lockheed. The district court denied this motion on June 6, 2001. On September 30, 2003, the court stayed all further proceedings pending resolution of the California litigation. The district court reopened litigation on December 9, 2004. Rantec re-filed its motion for summary judgment against Lockheed, and the FM Entities moved for summary judgment against Rantec. On April 20, 2005, the district court granted Ran-tec’s motion for summary judgment against Lockheed and granted the FM Entities’ motion for summary judgment against Rantec. Regarding Lockheed’s claims against Rantec, the district court found that the economic loss doctrine barred Lockheed’s tort claims and that the implied warranties’ claims were barred by the statute of limitations. Lockheed appealed on May 17, 2005. Rantec appealed on May 31, 2005.

II. Discussion
A. Standard of Review

“We review a district court’s grant of summary judgment de novo, viewing the facts in the light most favorable to the nonmovant.” Uncle Henry’s, Inc. v. Plaut Consulting Co., 399 F.3d 33, 41 (1st Cir.2005). Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). We may affirm a district court’s grant of summary judgment on any basis apparent in the record. Uncle Henry’s, 399 F.3d at 41.

B. Lockheed’s Tort Claims

The parties agree that New Hampshire law governs this case. The district court found that, under New Hampshire law, Lockheed’s tort claims were barred by what is known as the economic loss rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
440 F.3d 549, 2006 U.S. App. LEXIS 6832, 2006 WL 668711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-corp-v-rfi-supply-inc-ca1-2006.